A3 Project Specifications.pdf
PDF 161 KB Posted
- Attached to
- White Mountain NF Pine Street Garage Roof Repair
- Solicitation number
- 12445524Q0112
- Issued by
-
Department of Agriculture Forest Service
About this file
This document appears to be a project specification for the repair and replacement of a historic garage roof in Bartlett, NH within the White Mountain National Forest, Saco Ranger District. The project will involve historic preservation requirements and includes repairing or replacing wood trim, rafters, and plank sheathing. Key details include the use of wood consolidants, patching compounds, and borate preservative treatments to repair and restore the historic wood components. The project also requires full tear-off of the existing roofing system down to the roof deck. The solicitation is being issued by the Department of Agriculture Forest Service under Solicitation Number 12445524Q0112.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12445524Q0112 Solicitation.pdf | ||
| A1 Wage Determination NH20240016 Carroll Cty.pdf | ||
| A4 Project Map.pdf | ||
| A2 Statement of Work.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
03/18/24
Pine Street Garage Roof Repair Pine Street
Bartlett, NH 03812
Saco Ranger District White Mountain National Forest
33 Kancamagus Highway Conway, NH 03818
671041
Copyright 2020 AIA MasterSpec Short Form 06/20
HISTORIC WOOD REPAIR 060312 - 1
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 060312 - HISTORIC WOOD REPAIR
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes historic treatment of wood in the form of repairing wood features as follows:
1. Repairing wood trim, rafters, and plank sheathing.
2. Replacing wood trim, rafters, and plank sheathing.
1.2 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1. Review methods and procedures related to historic wood repair.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
PART 2 - PRODUCTS
2.1 HISTORIC WOOD REPAIR, GENERAL
A. Quality Standard: Comply with applicable requirements in Section 12, "Historic Restoration
Work," and related requirements in AWMAC/WI's "North American Architectural Woodwork
Standards" for construction, finishes, grade rules, and other requirements unless otherwise indicated.
1. Exception: Industry practices cited in Section 12, Paragraph 6, "Industry Practices," under Article 12.1, "Basic Considerations," of AWMAC/WI's "North American
Architectural Woodwork Standards" do not apply to the Work of this Section.
2.2 WOOD-REPLACEMENT MATERIALS
A. Wood, General: Clear fine-grained lumber; kiln dried to a moisture content of 6 to 12 percent at time of fabrication; free of visible finger joints, blue stain, knots, pitch pockets, and surface checks larger than 1/32 inch deep by 2 inches wide.
1. Species: Match species of each existing type of wood component or assembly unless otherwise indicated.
HISTORIC WOOD REPAIR 060312 - 2
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
Treaties. A valid, current MasterSpec license is required for editing or use of this document.
2.3 WOOD-REPAIR MATERIALS
A. Wood Consolidant: Ready-to-use product designed to penetrate, consolidate, and strengthen soft fibers of wood materials that have deteriorated due to weathering and decay and designed specifically to enhance the bond of wood-patching compound to existing wood.
B. Wood-Patching Compound: Two-part, epoxy-resin, wood-patching compound; knife-grade formulation as recommended in writing by manufacturer for type of wood repair indicated, tooling time required for the detail of work, and site conditions. Compound must be designed for filling voids in damaged wood materials that have deteriorated due to weathering and decay.
Compound must be capable of filling deep holes and spreading to featheredge.
2.4 MISCELLANEOUS MATERIALS
A. Borate Preservative Treatment: Inorganic, borate-based solution, with disodium octaborate tetrahydrate as the primary ingredient; manufactured for preserving weathered and decayed wood from further damage caused by fungi and wood-boring insects; complying with
AWPA P5; containing no boric acid.
B. Cleaning Materials:
1. Detergent Solution: Solution prepared by mixing 2 cups of tetrasodium pyrophosphate
(TSPP), 1/2 cup of laundry detergent that contains no ammonia, 5 quarts of 5 percent sodium hypochlorite bleach, and 15 quarts of warm water for each 5 gal. of solution required.
2. Mildewcide: Commercial, proprietary mildewcide or a solution prepared by mixing 1/3 cup of household detergent that contains no ammonia, 1 quart of 5 percent sodium hypochlorite bleach, and 3 quarts of warm water.
C. Adhesives: Wood adhesives with minimum 15- to 45-minute cure at 70 deg F, in gunnable and liquid formulations as recommended in writing by adhesive manufacturer for each type of repair and exposure condition.
D. Fasteners: Use fastener metals that are noncorrosive and compatible with each material joined.
1. Match existing fasteners in material and type of fastener unless otherwise indicated.
2. Use concealed fasteners for interconnecting wood components.
3. Use concealed fasteners for attaching items to other work unless exposed fasteners are unavoidable or the existing fastening method.
4. For fastening metals, use fasteners of same basic metal as fastened metal unless otherwise indicated.
5. For exposed fasteners, use Phillips-type machine screws of head profile flush with metal surface unless otherwise indicated.
6. Finish exposed fasteners to match finish of metal fastened unless otherwise indicated.
HISTORIC WOOD REPAIR 060312 - 3
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
Treaties. A valid, current MasterSpec license is required for editing or use of this document.
2.5 WOOD FINISHES
A. Unfinished Replacement Units: Provide exposed exterior and interior wood surfaces of replacement units unfinished; smooth, filled, and suitably prepared for on-site priming and finishing.
PART 3 - EXECUTION
3.1 PREPARATION
A. Clean wood of mildew, algae, moss, plant material, loose paint, grease, dirt, and other debris by scrubbing with bristle brush or sponge and detergent solution. Scrub mildewed areas with mildewcide. After cleaning, rinse thoroughly with fresh water. Allow to dry before repairing or painting.
B. Condition replacement wood members and replacement units to prevailing conditions at installation areas before installing.
3.2 HISTORIC WOOD REPAIR, GENERAL
A. General: In treating historic items, disturb them as minimally as possible and as follows:
1. Stabilize and repair wood to reestablish structural integrity and weather resistance while maintaining the existing form of each item.
2. Repair items in place where possible.
3. Install temporary protective measures to protect wood-treatment work that is indicated to be completed later.
B. Mechanical Abrasion: Where mechanical abrasion is needed for the Work, use only the gentlest mechanical methods, such as scraping and natural-fiber bristle brushing, that will not abrade wood substrate, reducing clarity of detail. Do not use abrasive methods, such as sanding, wire brushing, or power tools, except as approved by Owner.
C. Repair Wood: Match existing materials and features, retaining as much original material as possible to perform repairs.
1. Unless otherwise indicated, repair wood by consolidating, patching, splicing, or otherwise reinforcing wood with new wood matching existing wood or with salvaged, sound, original wood.
2. Where indicated, repair wood by limited replacement matching existing material.
D. Replace Wood: Where indicated, duplicate and replace units with units made from salvaged, sound, original wood or with new wood matching existing wood. Use surviving prototypes to create patterns for duplicate replacements.
E. Identify removed items with numbering system corresponding to item locations, to ensure reinstallation in same location.
HISTORIC WOOD REPAIR 060312 - 4
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
Treaties. A valid, current MasterSpec license is required for editing or use of this document.
3.3 WOOD PATCH-TYPE REPAIR
A. General: Patch wood that exhibits depressions, holes, or similar voids, and that has limited amounts of rotted or decayed wood.
1. Treat wood with wood consolidant prior to application of patching compound. Coat wood surfaces by brushing, applying multiple coats until wood is saturated and refuses to absorb more. Allow treatment to harden before filling void with patching compound.
B. Apply borate preservative treatment to accessible surfaces either before applying wood consolidant or after removing rotted or decayed wood.
C. Apply wood-patching compound to fill depressions, nicks, cracks, and other voids created by removed or missing wood.
1. Prime patch area with application of wood consolidant or manufacturer's recommended primer.
2. Apply patching compound in layers as recommended in writing by manufacturer until the void is completely filled.
3. Sand patch surface smooth and flush with adjacent wood, without voids in patch material, and matching contour of wood member.
3.4 WOOD-REPLACEMENT REPAIR
A. General: Replace parts of or entire wood items at locations scheduled and where damage is too extensive to patch.
1. Remove broken, rotted, and decayed wood down to sound wood.
2. Custom fabricate new wood to replace missing wood; either replace entire wood member or splice new wood part into existing member.
3. Secure new wood using finger joints, multiple dowels, or splines with adhesive and nailing to ensure maximum structural integrity at each splice. Use only concealed fasteners. Fill nail holes and patch surface to match surrounding sound wood.
B. Apply borate preservative treatment to accessible surfaces after replacements are made. Apply treatment liberally by brush to joints, edges, and ends; top, sides, and bottom.
C. Repair remaining depressions, holes, or similar voids with patch-type repairs.
D. Reinstall items removed for repair into original locations.
END OF SECTION 060312
Copyright 2021 AIA MasterSpec Short Form 09/21
PREPARATION FOR REROOFING 070150.19 - 1
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
Treaties. A valid, current MasterSpec license is required for editing or use of this document.
SECTION 070150.19 - PREPARATION FOR REROOFING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Full tear-off of entire roof system.
1.2 PREINSTALLATION MEETINGS
A. Preliminary Roofing Conference: Before starting removal Work, conduct conference at Project site.
1.3 INFORMATIONAL SUBMITTALS
A. Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including exterior and interior finish surfaces, that might be misconstrued as having been damaged by reroofing operations.
1. Submit before Work begins.
1.4 FIELD CONDITIONS
A. Existing Roofing System: Built-up asphalt roofing.
B. Owner will not occupy portions of building immediately below reroofing area.
1. Conduct reroofing so Owner's operations are not disrupted.
2. Provide Owner with not less than 72 hours' written notice of activities that may affect
Owner's operations.
3. Coordinate work activities daily with Owner so Owner has adequate advance notice to place protective dust and water-leakage covers over sensitive equipment and furnishings, shut down HVAC and fire-alarm or -detection equipment if needed, and evacuate occupants from below work area.
C. Protect building to be reroofed, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from reroofing operations.
D. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
E. Limit construction loads on existing roof areas to remain, and existing roof areas scheduled to be reroofed to 20 pounds per square foot for uniformly distributed loads.
PREPARATION FOR REROOFING 070150.19 - 2
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
Treaties. A valid, current MasterSpec license is required for editing or use of this document.
F. Weather Limitations: Proceed with reroofing preparation only when existing and forecasted weather conditions permit Work to proceed without water entering existing roofing system or building.
1. Remove only as much roofing in one day as can be made watertight in the same day.
PART 2 - PRODUCTS
2.1 AUXILIARY REROOFING MATERIALS
A. General: Use auxiliary reroofing preparation materials recommended by roofing system manufacturer for intended use and compatible with components of new roofing system.
PART 3 - EXECUTION
3.1 PREPARATION
A. Seal or isolate windows that may be exposed to airborne substances created in removal of existing materials.
B. During removal operations, have sufficient and suitable materials on-site to facilitate rapid installation of temporary protection in the event of unexpected rain.
3.2 ROOF TEAR-OFF
A. Notify Owner each day of extent of roof tear-off proposed for that day.
B. Lower removed roofing materials to ground and onto lower roof levels, using dust-tight chutes or other acceptable means of removing materials from roof areas.
C. Full Roof Tear-off: Remove existing roofing and other roofing system components down to the existing roof deck.
1. Remove substrate board, vapor retarder, roof insulation, and cover board.
2. Remove base flashings and counter flashings.
3. Remove perimeter edge flashing and gravel stops.
4. Remove copings.
5. Remove wood blocking, curbs, and nailers.
6. Remove fasteners from deck.
3.3 DECK PREPARATION
A. Inspect deck after tear-off of roofing system.
B. If broken or loose fasteners that secure deck panels to one another or to structure are observed, or if deck appears or feels inadequately attached, immediately notify Owner.
PREPARATION FOR REROOFING 070150.19 - 3
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S. Copyright Law and International
Treaties. A valid, current MasterSpec license is required for editing or use of this document.
1. Do not proceed with installation until directed by Owner.
C. If deck surface is unsuitable for receiving new roofing or if structural integrity of deck is suspect, immediately notify Owner.
1. Do not proceed with installation until directed by Owner.
D. Replace roof sheathing as directed by Owner.
END OF SECTION 070150.19
| ProjectCover |
| 060312 SF - Historic Wood Repair_edit |
| 070150.19 SF - Preparation for Reroofing_edit |
File details come from the government source that posted it. Updated .