STURGEON ISLAND

EROSION PROJECT

RIPRAP SUPPLY

SCOPE OF WORK

Solicitation: W912ES21Q0077 i

Contents

1. GENERAL

1.1 SCOPE

1.2 APPLICABLE PUBLICATIONS

1.3 SUBMITTALS

1.3.1 General

1.3.2 Submission of Submittals

1.3.3 Submittal Control

1.4 MEASUREMENT AND PAYMENT

1.4.1 MEASUREMENT

1.4.2 WEIGHING OPERATIONS

1.4.3 WEIGHING OPERTIONS PLAN

1.4.4 PAYMENT

1.5 LIST OF ATTACHMENTS

2. PRODUCTS

2.1 MATERIALS

2.1.1 GENERAL

2.1.2 SPECIFIC GRAVITY

2.1.3 RIPRAP SHAPE

2.1.4 RIPRAP GRADATION

2.1.5 RIPRAP GRADATION PROCESSING

2.2 SOURCES AND EVALUATION

2.2.1 APPROVAL OF MATERIAL SOURCE

2.2.2 SAMPLES FOR TESTING

2.2.4 PROHIBITED RIPRAP MATERIAL SOURCE LOCATIONS

2.3 TESTS FOR ACCEPTABILITY OF SOURCE MATERIAL

2.3.1 MATERIAL TESTING

2.3.2 SAMPLES

2.4 RIPRAP GRADATION TESTING

2.4.1 GENERAL REQUIRMENTS

2.4.2 TEST METHOD A

2.4.3 TEST METHOD B

2.4.4 SCALE ACCURACY REQUIRMENTS

ii

2.4.5 TESTING

2.4.6 TESTING FREQUENCY

2.4.6 CORRECTIVE ACTION

3. EXECUTION

3.1 SCHEDULE AND ORDERING

3.2 COORDINATION

3.3 DELIVERY LOCATION

3.4 DELIVERY AND BARGE LOADING

3.4.1 LOADING RIPRAP

3.4.2 DELIVERY RATE

3.5 QUALITY CONTROL

3.6 SAFETY

3.7 PROTECTION OF GOVERNMENT BUILDINGS, EQUIMENT, FACILITIES, AND VEGETATION

STURGEON ISLAND EROSION PROJECT

RIPRAP SUPPLY

SCOPE OF WORK

1. GENERAL.

1.1 SCOPE

The Contractor shall provide all plant labor and material necessary to furnish and deliver R45 riprap to the Sturgeon Lake Road Boat Ramp. The delivery point is located in Goodhue County, Minnesota on the right bank of the Mississippi River. The boat ramp is approximately .8 of a mile east of the Treasure Island Resort and Casino. The delivery location is shown on the Diamond Bluff West USGS 7.5 quadrangle at MGRS grid coordinate 15T WK 28978 41801.

1.2 APPLICABLE PUBLICATIONS

The publications listed below form a part of this scope of work to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. Army Corps of Engineers, Engineer Manual (EM).

EM 385-1-1 Safety and Health Requirements Manual, (30 November 2014).

1.3 SUBMITTALS

1.3.1 General

The Contractor shall submit the following as required. Approval of submittals will not relieve the Contractor of responsibility to furnish materials as required. In order to make the submittal process as efficient as possible, the Contracting Officer may give verbal responses to a submittal followed by the written response at a later date. In this case, the submittal response date will be the date that the verbal response was given.

a. Submittal Register as specified in PARAGRPAH 1.3.3

b. Material Source as specified in PARAGRAPH: 2.2 Sources and Evaluation

c. Method of Processing Riprap as specified in PARAGRAPH: 2.1.5 Riprap Gradation

Processing

d. Gradation Test Results as specified in PARAGRAPH: 2.4 Riprap Gradation Testing

e. Plan Indicating location and schedule of Weighing Operations as specified in

PARAGRAPH: 1.4.3 Weighing Operations Plan

f. Delivery Tickets as specified in PARAGRAPH: 1.4.2 Weighing Operations

g. Scale Accuracy Certification as specified in PARAGRAPH: 1.4.1 Measurement

h. Daily Delivery Report as specified in PARAGRAPH: 1.4.2 Weighing Operations

i. Pre-Delivery Site Survey as specified in PARAGRAPH: 3.7 Protection of Government

Buildings, Equipment, Facilities, and Vegetation.

1.3.2 Submission of Submittals

Submittals shall be submitted to the Contracting Officer in ample time to secure approval prior to the time the items covered are to be delivered to the site. ENG Form 4025 (Attachment 5) shall be used for the transmittal of submittals. One electronic copy of all submittals shall be provided. Hard copies of submittals are generally not required unless specifically noted. The Government shall be provided at least ten working days to review a submittal unless specified otherwise.

1.3.3 Submittal Control

Within 7 calendar days after contract award date, the Contractor shall submit to the Contracting Officer for review and approval, a submittal register in electronic format listing and scheduling all items required to be furnished for review by the Government. A sample submittal register is included in Attachment 5. Primary responsibility for submittals shall rest with the Contractor. The Contractor shall furnish submittals for all deviations from the specifications.

1.4 MEASUREMENT AND PAYMENT

1.4.1 MEASUREMENT

Riprap shall be weighed on an accurate, approved scale furnished or made available by the Contractor.

Before being approved for use, the scale shall have been tested by the applicable State’s Department of Weights and Measures or by a reliable scale servicing company so as to operate within a degree of error not greater than 1 percent and to be sensitive to a change in load of 1/5 of 1 percent, both percentages being based on the total required weight of material normally weighed as a unit on the scale. The Contractor shall submit the certification document from the appropriate state’s Department of Weights and Measures or scale servicing company that the proposed scale complies with the requirements listed above. Scales shall be spot checked for accuracy and sensitivity as often as directed by the Contracting Officer during stone delivery. When materials are weighed in hauling vehicles, gross weights shall be checked, and the vehicle tare weight determined as often as the Contracting Officer directs. The Contractor shall furnish such weights, accessories, and assistance as the Contracting Officer may require for conducting weighing equipment tests.

1.4.2 WEIGHING OPERATIONS

Weighing operations shall be performed, as approved, in the presence of the Contracting Officer, unless waived. Each load shall be accompanied by duplicate copies of delivery tickets certified by the weighmaster. As a minimum, each ticket shall contain the following information:

a. Date and Time.

b. Vehicle Number.

c. Gross Weight.

d. Vehicle Tare Weight.

e. Net Weight of Riprap.

f. Material weighed (Description of Load Contents).

g. Signature of Weighmaster.

The Government will collect a copy of the delivery ticket from each truck as it arrives on site.

The Contractor shall submit a daily report detailing the number of trucks that made deliveries to the site as well as an overall quantity of material delivered to the site that day. All daily reports shall be submitted no later than 24 hours after the report period end date and time.

1.4.3 WEIGHING OPERATIONS PLAN

A plan indicating the location and proposed schedule of weighing operations shall be submitted for approval in accordance with PARAGRAPH: 1.3 Submittals.

1.4.4 PAYMENT

Riprap material shall be measured and paid for by the net ton (2,000 pounds avoirdupois) of acceptable material delivered as specified to the designated delivery site.

1.5 LIST OF ATTACHMENTS

1 - Blank Submittal Transmittal Form (ENG Form 4025) Gradation Forms:

2 - R45 Riprap Gradation Curve 3 - Riprap Gradation Analysis Worksheet, Method A 4 - Riprap Gradation Analysis Worksheet, Method B 5 - Sample Submittal Register 6 – Diamond Bluff West USGS 7.5 Quadrangle

2. PRODUCTS.

2.1 MATERIALS

2.1.1 GENERAL

Riprap material shall be durable quarried stone of suitable quality to ensure permanence in the Upper Mississippi River environment. Stone shall be free from cracks, seams and other defects that would unduly increase its deterioration from natural causes. A crack is considered to be detrimental if it is more than four (4) mils wide and is continuous for one-third the dimension of at least two sides of the stone.

2.1.2 SPECIFIC GRAVITY

All Stone shall have a specific gravity of not less than 2.55 and not more than 2.75.

2.1.3 RIPRAP SHAPE

Neither the breadth nor thickness of any individual stone shall be less than one-third its length.

2.1.4 RIPRAP GRADATION

Riprap shall be well graded within the specified limits shown on the riprap gradation curve contained in Attachment 2 to permit construction of relatively dense riprap sections. Inclusion of objectionable quantities of dirt, sand, clay, rock fines, or other deleterious materials will not be allowed or measured for payment.

2.1.5 RIPRAP GRADATION PROCESSING

On the same date the Contractor provides the submittal for material sources, the Contractor shall also submit for approval the method of processing riprap at the quarry that will preclude the inclusion of objectionable amounts of fine material and organic matter. All riprap shall be processed in accordance with the approved method. Quarry-run riprap material will not be accepted. All rock designated for use as riprap shall be processed over a vibratory grizzly or by an approved method to insure the exclusion of poor-quality rock.

2.2 SOURCES AND EVALUATION

2.2.1 APPROVAL OF MATERIAL SOURCE

The Contractor shall submit the proposed riprap material source for Government approval within 7 days of Contract Award and prior to commencing any deliveries. The Government shall complete all necessary inspections of the proposed material sources within 15 days of receiving the name and location of the proposed material source. The riprap material source the Contractor intends to obtain the stone from must be approved by the Contracting Officer prior to commencing any delivery and must meet the conditions hereinafter stated. The Government Geologist will make such investigations and evaluations as necessary to determine whether or not materials meeting the requirements of this contract can be produced from the proposed source. The Contractor shall be responsible for making its own investigations for sources of suitable materials and for making its own arrangements with the owners of the quarries or land for procuring the required quantities of suitable materials. The Contractor will obtain all material for this Contract from one approved material source. Approval of a source of material is not to be construed as approval of all material from that source. The right is reserved by the Government to reject materials from certain localized areas, zones, strata, or channels when such material is unsuitable as determined by the Government Geologist. Materials produced from an approved source shall meet all of the requirements of this specification.

2.2.2 SAMPLES FOR TESTING

Samples for acceptability testing shall be provided as required by the PARAGRAPH: 2.3 Tests for Riprap Material Acceptability.

2.2.4 PROHIBITED RIPRAP MATERIAL SOURCE LOCATIONS

No riprap material shall be used from any river facing bluffs that are visible from the Mississippi River.

2.3 TESTS FOR ACCEPTABILITY OF SOURCE MATERIAL

2.3.1 MATERIAL TESTING

Quality tests and service records will be used to determine the acceptability of stone materials. In the event suitable test reports and satisfactory service records are not available, as in the case of newly operated sources, the materials will be tested to determine acceptability. Tests to which the materials may be subjected to include petrographic analysis, specific gravity, soundness, abrasion, absorption, freezing and thawing, and other tests considered necessary to demonstrate acceptability. Tests will be made by, or under the supervision of, the Government and at the Government’s expense.

2.3.2 SAMPLES

When directed by the Contracting Officer, suitable samples of materials shall be submitted for approval prior to delivery of materials to the work site. Samples shall be obtained by the Contractor, in the presence of the Contracting Officer or its designated representative, and delivered at the Contractor’s expense to a point designated by the Contracting Officer, at least 15 calendar days in advance of the date that the material is required to be delivered.

2.4 RIPRAP GRADATION TESTING

2.4.1 GENERAL REQUIRMENTS

General Requirements. Gradation tests shall be performed by the methods and frequency listed below.

Testing listed herein shall be completed by and at the expense of the Contractor. Gradation testing results shall be submitted utilizing the gradation plots for the required riprap gradation and the WORKSHEET FOR GRADATION ANALYSIS OF RIPRAP (gradation plots and blank copies of the worksheet are included in the attachments section). The Contracting Officer shall direct the time and location of sampling, unless waived. The Contracting Officer shall be informed a minimum of 24 hours before each test is to be performed. The results of all tests, including failing tests shall be submitted on the appropriate gradation plots and worksheets. The Contracting Officer shall be informed immediately of test results and draft copies of test results shall be submitted at the Contracting Officers request. Tests performed on material that does not meet gradation and shape requirements will not be counted as part of the tests required.

2.4.2 TEST METHOD A

Test Method A. Test method A shall consist of weighing all stones larger than 5 pounds in a sample. Five to seven weight classes shall be selected within the range of stone sizes. Each stone shall be weighed and recorded on the worksheet for method A. The weight of stones shall be summed for each weight class; after which calculations and a plot of the gradation shall be completed in accordance with accepted practice for soil and aggregate gradations.

2.4.3 TEST METHOD B

Test Method B. Test method B shall consist of separating the stones into 5 to 7 piles, ordered by size.

The sample shall be separated on a clean, hard surface that is free of smaller stones that could become mixed with the sample. The stones shall be visually screened to place them into appropriate piles. All stones shall be separated and placed into a pile before weighing. After separating, the smallest and the largest rock in each pile shall be weighed and recorded. The stones shall be adjusted as necessary so that the weight classes do not overlap. After adjustment is adequate and weight classes have been established, each pile of stone shall be weighed and recorded on the worksheet for method B.

Calculations and a plot of the gradation shall be completed in accordance with accepted practice for soil and aggregate gradations.

2.4.4 SCALE ACCURACY REQUIRMENTS

Accuracy of scales shall be as required in PARAGRAPH: 1.4.1 Measurement.

2.4.5 TESTING

A sample shall be obtained from the approved material source for the gradation required and the sample shall be tested in accordance with either method A or B. A satisfactory test shall be obtained from the approved source for the gradation required prior to hauling any riprap from that quarry. Each sample shall have a minimum gross weight of not less than 25 times the maximum stone size in the specified gradation (25∙W100).

2.4.6 TESTING FREQUENCY

Gradation tests will be required at a frequency of 1 per 700 tons of each gradation of material from a specific source that is brought on site, with a minimum of one test per gradation. Tests that do not meet gradation requirements will not be counted.

2.4.6 CORRECTIVE ACTION

If materials fail to meet gradation or shape requirements, the Contractor shall adjust its operations and verify with necessary tests that acceptable materials are being produced, or it shall propose another source and verify, with necessary tests, that acceptable material can be produced from that source.

3. EXECUTION.

3.1 SCHEDULE AND ORDERING

The Contracting Officer will notify the Contractor 15 calendar days in advance of when delivery is to commence via email. The Contractor shall provide the riprap gradation submittals for approval no later than 7 calendar days prior to delivery of materials to the specified delivery location. It is anticipated that commencement of delivery will occur between the dates of 7 September and 1 December 2021.

Delivery shall commence no later than 15 calendar days after the email is sent and shall continue Monday through Thursday, as required by the Government until completed, unless directed otherwise by the Contracting Officer. The Contracting Officer may temporarily suspend deliveries for up to five consecutive days. The Contracting Officer shall provide the Contractor with at least 48 hours advance notice prior to temporarily suspending deliveries. The Contracting Officer may temporarily suspend deliveries as many times as required during the Contract performance period. The delivery hours shall be between the hours of 7:30 a.m. and 5:00 p.m. (local time), Monday through Thursday. Friday deliveries may be required if directed by the Contracting Officer. The Government will give the Contractor at least 24 hours notice prior to requiring a Friday delivery. No deliveries shall be made on weekends or on Federal holidays.

3.2 COORDINATION

The Contractor shall coordinate loading access routes and dock use with the following:

Contracting Officer’s Representative (COR) Mr. Todd Decosse Contracting Officer’s Representative

651.792.6073 Todd.M.Decosse@usace.army.mil

Alternate:

Mr. Christopher Stai Chief, Maintenance and Repair

651.290.5144 (office) 612.790.2675(mobile) Christopher.J.Stai@usace.army.mil

Alternate:

Josh Isakson Foreman/Site Supervisor

608.687.8753 (office)

608.405.0138 (mobile) Joshua.W.Isakson@usace.army.mil

3.3 DELIVERY LOCATION

All riprap required under this contract shall be delivered to the Sturgeon Lake Road Boat Ramp. The delivery point is located in Goodhue County, Minnesota on the right bank of the Mississippi River. The boat ramp is approximately .8 of a mile east of the Treasure Island Resort and Casino. The delivery location is shown on the Diamond Bluff West USGS 7.5 quadrangle at MGRS grid coordinate 15T WK 28978 41801.

3.4 DELIVERY AND BARGE LOADING

Delivery of riprap by the Contractor shall include placing material directly from the delivery trucks into a stockpile area on site and/or loading directly from the delivery trucks onto U.S. Government-owned barges. Each barge on which riprap material is to be loaded will have a capacity of 200 tons, with a 20 foot by 85 foot holding area with 2.5 foot high side barriers, with ramps that can be used to drive the delivery trucks directly onto the barges. The barges and access ramps will be maneuvered by Government Personnel. Government personnel and equipment will stockpile material. The Contractor shall provide all other equipment and personnel needed to place the riprap directly onto the barges, except that no secondary loading or repositioning of riprap will be required after the riprap has been dumped from the delivery trucks. The Contracting Officer will direct the Contractor where to unload riprap. It is intended that delivery will be directly onto the barge.

3.4.1 LOADING RIPRAP

Delivery trucks used by the Contractor for loading riprap onto barges or stockpiles shall be straight tandem, tri, or quad axle dump trucks with maximum 18-ton capacity. If the maximum capacity of a straight tandem, tri, or quad axle dump truck is greater than 18 tons, it may only be loaded with up to a maximum of 18 tons of cargo. The use of articulated end-dump trailers, side dump, or belly dump trailers will not be allowed. The Contracting Officer reserves the right to reject delivery from any truck that cannot safely discharge its cargo at the point of delivery or adversely affects the stability of the floating plant.

3.4.2 DELIVERY RATE

The riprap material delivery rate will vary between 100 tons and 900 tons per day, as requested by the Contracting Officer’s Representative. The Contractor shall be required to increase or decrease the delivery rate within the above stated delivery rate range on a daily basis until the required quantity of material is met.

3.5 QUALITY CONTROL

The Contractor shall establish and maintain quality control and shall maintain records of the quality control for work under this section to ensure compliance with contract requirements. A copy of inspections and tests, as well as corrective actions taken, shall be furnished to the Government.

3.6 SAFETY

The Contractor shall comply with all state and Federal OSHA requirements as well as all pertinent provisions of the latest version of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. If a conflict exists between the guidance provided between the sources listed above, the Contractor shall follow the most stringent standard given. A current copy of EM 385-1-1 can be found at https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

3.7 PROTECTION OF GOVERNMENT BUILDINGS, EQUIMENT, FACILITIES, AND

VEGETATION

The Contractor shall use reasonable care to avoid damaging existing structures, equipment, and vegetation on the Government site. The Contractor shall submit a pre-delivery site survey providing photographic documentation of the roads and streets to be used for delivery to Sturgeon Lake Road Boat Ramp. The pre-delivery survey is to include access roads, parking lots, and the loading ramp area submitted for Government Approval prior to commencing any rock deliveries. The photographs shall be full color submitted in a .pdf format. The survey shall contain as a minimum a title cover page, a short narrative stating the names of the persons who took the photos, the date the photos were taken, any items of pre-existing damage, and each photo shall contain a descriptive caption. The Contractor shall take enough photos of the site to adequately document the pre-delivery condition of all access roads, parking lots, and the loading dock. This contract may require delivery on Government owned barges.

Reasonable care shall be used in the loading of material on Government barges as to not damage the barge, barriers, or ramps in the process of unloading material. If the Contractor’s failure to use reasonable care causes damage to any of this property, the Contractor shall replace or repair the damage at no expense to the Government as the Contracting Officer directs. If the Contractor fails or refuses to make such repair or replacement, the Contractor shall be liable for the cost, which may be deducted from the contract price.