A21. Combined SynSol.pdf
PDF 7 MB Posted
- Solicitation number
- W912P922R0043
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Lithia Springs Wastewater Treatment Facility Rehab Site Visit Questions.docx | DOCX document | |
| Opossum Creek Ref WWT Pump and Motor Submittal 1992 - Copy.pdf | ||
| Sign In for Lithia WWT Contract Site Visit.pdf | ||
| WWT Corrected Diagram.pdf | ||
| A02. Bid Schedule.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers St. Louis District
Lithia Springs Wastewater Treatment Rehab Lake Shelbyville
Shelbyville Lake Project Office 1989 State Highway 16 Shelbyville, IL 62565
COMBINED SYNOPSIS & SOLICITATION
W912P922R0043
This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Federal Acquisition Regulation (FAR) Subpart 12.6, "Streamlined Procedures for Evaluation and Solicitation for Commercial Items," as supplemented with additional information included in this notice.
This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued.
Solicitation Number: W912P922R0043
This solicitation is issued as a Request for Quotation.
The solicitation document and incorporated provisions and clauses are those in effect through the date of posting.
This solicitation is set-aside for total small businesses associated with North American Industrial Classifications System (NAICS) code 221320, size standard $31M.
Please provide a completed copy of the provision at 52.212-3, Offeror Representations and Certifications
– Commercial Items with your offer.
CAGE Code:
Offeror Name:
Offeror Signature:
Date of Offer:
Submit offer to Jessica Nies, Contract Specialist, via email at jessica.l.nies@usace.army.mil.
Section SF 1449 - CONTINUATION SHEET
BID SCHEDULE
SCOPE OF WORK
1. GENERAL.
1.1 SCOPE OF WORK. Supply, deliver and replace existing irrigation spray field pumps, duplex control panel, power feeders, electrical junction box and safety disconnect switches including stand, and all necessary accessories. Spray field system consists of an irrigation wet well with two vertical turbine pumps each rated 90 gpm at 155 feet of total dynamic head capacity with a check valve, gate valve and solenoid actuated globe valve on the discharge side of each pump. Pump operation is controlled by a timer system communicating with a duplex motor controller that alternates which pump should run and determines which globe valve should be closed. Pumps, check valves and gate valves shall be replaced with existing piping and wet well remaining in place. Replacement of equipment and components shall be furnished and installed new.
1.2 CONTRACTOR. The "Contractor" is the individual whose contract bid was accepted by the U.S. Army Corps of Engineers and who has gained the responsibility of performing the duties governed by the specifications of this contract.
1.3 CONTRACTING OFFICER. The term "Contracting Officer" shall mean the person executing this contract on behalf of the Government, and any other officer or civilian employee who is acting on his/her behalf.
1.3.1 CONTRACTING OFFICER’S REPRESENTATIVE (COR). An individual designated in writing by the Contracting Officer to be responsible for administration of the contract and Quality Assurance Representative.
1.4 REQUIRED INSURANCE.
1.4.1 As required by the Contract Clause entitled “Insurance--Work on a Government Installation,” following award and prior to commencement of work, the Contractor shall furnish to the Contracting Officer a written statement as evidence of the following minimum insurance.
Workmen’s Compensation - Amounts required by applicable jurisdictional statutes.
Employer’s Liability Insurance - $100,000.00
Comprehensive General Liability Insurance
Bodily Injury - $500,000.00 Comprehensive Automobile Insurance Bodily Injury - $200,000.00 each person
$500,000.00 each person Property Damage $ 20,000.00 each accident
1.4.2 Statements of insurance shall be submitted to the following address: St.
Louis District, Corps of Engineers
Item No. Description Estimated Quantity
Unit Unit Price Amount
0001 Lithia Springs WWT Upgrade
1 JOB
**The contactor shall furnish all labor, equipment, and materials necessary to replace the motors, pumps, valves, motor control panel, and electrical components, in accordance with all sections listed within the contact specifications.
Shelbyville Lake Project Office 1989 State Highway 16 Shelbyville, IL 62565
1.5 CONFINED SPACE ENTRY. The existing wet wells are confined spaces and require a “Confined
Space Entry Permit” to perform work in this space. The Contractor shall complete a confined space entry permit for approval to enter the space daily or for each successive entry period. The Contractor shall submit a copy of their confined space program in accordance with 29 CFR 1910.146 to the Government.
All work in this confined space shall be accomplished in accordance with OSHA requirements and safety requirements set forth in Corps of Engineers Manual, EM 385-1-1, entitled “Safety and Health Requirements Manual”.
1.6 SECURITY.
Access and General Protection/Security Policy and Procedures.
All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.
Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something). The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
1.7 SAFETY. This paragraph applies to contracts and purchase orders that require the Contractor to comply with EM 385-1-1 (e.g., contracts that include the Accident Prevention clause at FAR 52.235-13 and/or other safety provisions). EM 385-1-1 and its changes are available at http://www.hq.usace.army.mil (at the HQ homepage, select Safety and Occupational Health). The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation. The Government may inspect all equipment and materials. Any equipment or material found not in conformity with the requirements of this contract shall be removed from Government property immediately. The Contractor shall develop and submit an Accident Prevention Program using the forms located in Appendix A together with a copy of the Company Policy on Safety.
1.7.1 References. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the test by the basis designation only.
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA MG 1 (2016) Motors and Generators
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2002) Portable Fire Extinguishers
NFPA 70 (2017) National Electrical Code
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2003) Safety - Safety and Health Requirements
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
1.7.2 Site Safety and Health Officer (SSHO). Site Safety and Health Officer (SSHO) shall be provided at the work site at all times to perform safety and occupational health management, surveillance, inspections and safety enforcement for the Contractor. The Contractor Quality Control (QC) person can be the SSHO on this project. The SSHO shall meet the following requirements.
1.7.2.1 Work on similar projects
1.7.2.2 10-hour OSHA safety class or equivalent within the last three (3) years
1.7.2.3 Competent person training as needed
1.7.3 Accident Prevention Plan (APP)
1.7.3.1 The Contractor shall use a qualified person to prepare the written site-specific APP.
Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE EM 385-1-1, Appendix A, ‘Minimum Basic Outline for Accident Prevention Plan”. Specific requirements for some of the APP elements are described below. The APP shall be job-specific and shall address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the Contractor’s overall safety and health program. Any portions of the Contractor’s overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the “controlling authority” for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
The APP shall be signed by the person and firm (senior person) preparing the APP, the Contractor, the on-site superintendent, the designated site safety and health officer and any designated CSP and/or CIH.
1.7.3.2 Submit the APP to the Contracting Officer’s Representative (COR) for acceptance following award and prior to the post award conference for acceptance. Work cannot proceed without an accepted APP.
1.7.3.3 Once accepted by the COR, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the COR, until the matter has been rectified.
1.7.3.4 Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the COR, project superintendent, SSHO and quality control manager. Should any hazard become evident, stop work in the area, secure the area, and develop a plan to remove the hazard. Notify the COR within 24 hours of discovery. Eliminate/remove the hazard. In the interim, all necessary action shall be taken to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public and the environment.
1.7.3.5 Copies of the accepted plan will be maintained at the Shelbyville Lake Project Office.
The APP shall be continuously reviewed and amended, as necessary, throughout the life of the contract.
Unusual or high-hazard activities not identified in the original APP shall be incorporated in the plan as they are discovered.
1.7.4 Activity Hazard Analysis (AHA)
1.7.4.1 The Activity Hazard Analysis (AHA) format shall be in accordance with USACE EM 385-1-1. Submit the AHA to the COR for review following award and prior to the post award conference.
Format subsequent AHAs as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activities safety and health controls.
1.7.4.2 The AHA list will be reviewed periodically and updated as necessary when procedures, scheduling or hazards change.
1.7.4.3 The activity hazard analyses shall be developed for activities being performed. The AHAs will be developed by the contractor, supplier or subcontractor and provided to the prime contractor for submittal to the COR.
1.7.5 Emergency Medical Treatment. Contractors will arrange for their own emergency medical treatment. Government has no responsibility to provide emergency medical treatment.
1.7.6 Reports
1.7.6.1 Accident Reports. For recordable injuries and illnesses, and property damage accidents resulting in at least $2,000 in damages, the Prime Contractor shall conduct an accident investigation to establish the root cause(s) of the accident, complete USACE Accident Report Form 3394 and provide the report to the COR within two (2) calendar days of the accident. The COR will provide copies of any required special forms.
1.7.6.2 Accident Notification. Notify the COR as soon as practical, but not later than Four (4) hours, after any accident meeting the definition of Recordable Injuries or Illnesses or High Visibility Accidents, or property damage equal to or greater than $2,000. Information shall include contractor name;
contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of equipment used, PPE used, etc. Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted.
1.7.6.3 Monthly Exposure Reports. Monthly exposure reporting to the COR is required to be attached to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both prime and subcontractor. The COR will provide copies of any special forms.
1.7.7 Meetings
1.7.7.1 Pre-Bid Meeting and Site Visit
There will be a pre-bid meeting and site visit held at the Lithia Springs Waste Water treatment facility at 9:00am on Tuesday, August 2, 2022. The treatment facility is located ¼ mile East of the campground entrance. Attendance is not required but strongly recommended. Address is:
Lithia Springs Campground 2042 E 1500 North Rd.
Shelbyville, IL 62565
GPS: 39.4339, -88.7488
1.7.7.2 Post Award Conference
1.7.7.2.1 Contractor representatives who have a responsibility or significant role in accident prevention on the contract shall attend the post award conference. This includes the project superintendent, site safety and health officer, quality control supervisor, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).
1.7.7.2.2 The Contractor shall discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the COR as to which phases will require an analysis. In addition, a schedule for the preparation, submittal, review and acceptance of AHAs shall be established to preclude delays.
1.7.7.2.3 Deficiencies in the submitted APP will be brought to the attention of the Contractor at the post award conference and the Contractor shall revise the plan to correct deficiencies and resubmit it for acceptance. Work shall not begin until there is an accepted APP.
1.7.7.3 Safety Meetings. Shall be conducted and documented as required by EM 385-1-1.
1.8 LOCATION AND CONTRACT LIMITS. The location of the work to be performed is at the
Opossum Creek Recreation Area, Lake Shelbyville Project, Illinois.
1.9 SCHEDULE OF WORK. The Contractor shall perform all work between the hours of 7 a.m. and 5 p.m. CST Monday through Friday. No work shall be performed on weekends or holidays. All work shall be completed no later than 120 days after contract award.
1.10 ACCESS. The Contractor shall be responsible for access to, into and through all locations.
Access into and through Government property shall be by routes approved by the Contracting Officer in advance prior to entry. Access through Government locked barricades or gates will be provided by the Government to the Contractor provided that notification is given a minimum of twenty-four (24) hours in advance.
1.11 UNUSUAL CONDITIONS. The Contractor shall inform the Contracting Officer of any unusual conditions observed such as dumping or vandalism. NOTICE: The Contractor shall be required to cooperate with, and coordinate with the Government any operations in and around any other Contractors, work crews, Government employees or the public which may be working or entering the area within the contract limits.
1.12 QUALITY CONTROL. The Contractor shall establish and maintain quality control for all operations to assure compliance with contract requirements and maintain records of his quality control for all construction operations.
1.13 WARRANTY. All items furnished under this section shall be warranted to be free from defect in workmanship and materials for a minimum period of one (1) year after date of start-up assistance.
1.14 REFERENCE PUBLICATIONS. These specifications, standards and descriptions are not available from Government sources. They may be obtained from the publishers listed below:
American National Standards Institute (ANSI) 11 West 42ND Street New York, NY 10036 www.ansi.org
American Society of Testing and Materials (ASTM) 100 Barr Harbor Drive West Conshohocken, PA 19428 www.astm.org
American Water Works Association (AWWA) 666 West Quincy Denver, CO 80235 www.awwa.org
Underwriters Laboratories Inc.
333 Pfingsten Road Northbrook, IL 60062-2096 www.ul.com
American Society of Mechanical Engineers ASME International Three Park Avenue
New York, NY 10016-5990 www.asme.org
American Iron and Steel Institute 1140 Connecticut Ave. NW Suite 705 Washington D.C. 20036 www.steel.org
2. DESCRIPTION OF WORK. Components to be furnished and installed shall conform to the following requirements.
2.1 Lithia Springs Wastewater Treatment Area. The Contractor shall remove and replace two (2) vertical line shaft pumps complete with electric motors, discharge bases, discharge piping, check valves and gate valves at the irrigation station. In the operator building the duplex motor control panel shall be replaced and connected to the pumps. Contractor shall replace the motor feeder cables, safety disconnect switches and junction box including stand, and flexible conduit connections to new pump motors. All necessary electrical fittings, wire and hardware required to connect the system shall be the contractor’s responsibility.
Basic details of pump system components and valves are shown in Appendix C.
2.1.1 GENERAL. The existing pre-cast concrete wet well is approximately 6-feet in diameter and approximately 24-feet deep. Note: This is a “Confined Space Entry Permit” required space.
2.1.2 DEMOLITION AND REPAIR. The existing pumps, related bases, valves, electric conductors, duplex motor control panel, disconnect switches and junction box including stand shall be removed.
Electrical conduits may be reused except for the flexible conduit connections to new motors, these shall be replaced. The Contractor shall be responsible for repairing any physical damage caused to the existing wet-well during demolition and for the removal and disposal of waste water and debris. Deterioration of the wet-well discovered after dewatering shall be documented and submitted to the Contracting Officer. All demolished equipment and material become property of the contractor and shall be removed from Government property.
2.1.3 PUMPS. Furnish and replace vertical line shaft pumps as described herein. The motor shall be connected for operation on a 230 volt, 60 HZ, single phase service and shall be separable from rest of pumping unit. Manufacturer shall have installations of like or similar application with a minimum of 5 years service for this pump size.
Flow, GPM 90 TDH, Feet 155 Motor HP, rated 7.5 HP Max.
Speed RPM, rated 3550 RPM Max.
Power 230V-60hz-1ph
2.1.4 PUMP CONSTRUCTION.
2.1.4.1 Impeller. The impeller shall be of bronze construction conforming to ASTM B584, C83600. It shall be of one-piece construction, single suction. The waterways through the impeller shall have smooth contours devoid of sharp corners. The impeller is to be balanced and secured to the shaft by means of a stainless steel drive collet or a combination of a thrust washer, key and/or snap rings.
2.1.4.2 Bowls. The bowls shall be made of close-grained cast iron conforming to ASTM A48
CL30. Castings shall be free from blowholes, sand holes and shall be accurately machined and fitted to close dimensions. Bowls shall be flange connected. The casing shall be hydrostatically tested to 1.5 times the design head or 1.25 times the shutoff head whichever is greater.
2.1.4.3 Impeller Shaft. Impeller shaft shall be of stainless steel construction conforming to
ASTM A582 type 416 stainless steel. The shaft shall be supported by bronze or neoprene bearings located on both sides of each impeller. Impeller shaft coupling shall be of stainless steel construction conforming to ASTM A582 type 416 stainless steel.
2.1.4.4 Wear Rings. Impeller wear rings shall be of the radial-type. Bowl wear rings shall be of the radial-type. Wear rings shall be attached to the impellers and bowls using an interference fit. Wear rings shall be bronze conforming to ASTM, B505 C93200.
2.1.4.5 Pump Column. Pump column shall be of sufficient length to use existing structural supports inside wet-well and suspend bottom impeller off the floor of wet-well a suitable amount as determined by pump manufacturer. Column pipe shall be furnished in sections connected with threaded, sleeve-type couplings or flanged.
2.1.4.6 Lineshafts. Lineshafting shall be of ample size to transmit the torque and operate the pump without distortion or vibration. Shafting shall be of stainless steel construction conforming to ASTM A582 type 416 stainless steel. Lineshafting shall be water lubricated.
2.1.4.7 Discharge Head Assembly. The pump discharge head shall be of the above ground type of either cast iron or fabricated steel construction with an ANSI 125# discharge flange. The discharge head shall be of sufficient design to support the entire weight of the pump and driver. A drive shaft of the same material as the lineshaft shall extend through the sealing assembly of the discharge head and be coupled to a vertical hollow shaft driver. Discharge head openings shall be fitted with guards to prevent access to the rotating shaft and/or coupling.
2.1.4.8 Field Test Vibration Limitations. The limits of vibration as set forth in the standards of the Hydraulic Institute shall govern.
2.1.4.9 Testing. A certified factory hydrostatic and performance test shall be performed on each bowl assembly in accordance with Hydraulic Institute Standards, latest edition. Tests shall be sufficient to determine the curves of head, input horsepower, and efficiency relative to capacity from shutoff to 150% of design flow. A minimum of six points, including shutoff, shall be taken for each test. At least one point of the six shall be taken as near as possible to each specified condition.
2.1.5 ELECTRICAL. Furnish and replace two (2) new electrical motors as part of a complete pump system, two (2) new electrical disconnect switches and junction box including stand, new motor feeder conductors, one (1) new duplex motor control panel and all necessary conduit/fittings/hardware. Contractor responsible for integration of existing timer controller model Rain Bird ESP-LXME. All electrical equipment and workmanship shall meet the requirements of NFPA 70 National Electrical Code.
2.1.5.1 Electric Motor. Each electric pump motor shall be rated at no more than 7.5 hp/230 V/1-phase/60 Hz and shall be as recommended by the pump manufacturer. Motors shall have Class ‘F’ insulation. The rotor and stator shall be enclosed in a cast iron outer housing. Bi-metallic thermal switches shall be imbedded in each phase of the winding to sense high temperature. The rating of the switch shall be 130C +/- 5C. The control circuit shall be connected through the bi-metallic switches so the motor is shut down should a high temperature condition exist. The switches shall be self-resetting when the motor cools.
Single phase motors shall be of the capacitor start, capacitor run type for high starting torque
2.1.5.2 Disconnect Safety Switch. Switches shall be Heavy Duty Safety Switch type rated 60
A/600 V/3-pole. Two switching poles shall be utilized for 1-phase AC. Switches shall be housed in new NEMA 4X enclosures and installed in-place of existing disconnect enclosures using all new stainless steel mounting channel/hardware.
2.1.5.3 Motor Feeder Conductors. Conductors shall be copper (CU) #6AWG with XLPE insulation meeting requirements of NEMA WC 70. PVC jackets not permitted. Conductors shall be installed between output terminals of contactors located in new duplex control panel in pump house and new disconnect safety switches. Contractor may reuse existing conduit between new duplex control panel and disconnect switches. New CU #6AWG conductors shall be installed between new disconnect switches and new pump motor terminals. Contractor shall replace existing liquid-tight flexible metal conduit LFMC to each new pump motor.
2.1.5.5 Duplex Motor Control Panel. The motor control panel shall be sufficient to operate the new motors, pumps, and be compatible with the existing Rain Bird ESP-LXME timer.
http://www.rainbird.com/landscape/products/controllers/ESP-LXME.htm. Control panel shall be powered from existing 100A circuit breaker (ckt 10, 12) located in existing 120/240V Power Panel. Duplex control panel shall include but not be limited to the following:
□ 100A Main Circuit Breaker
□ (2) 80A Motor Branch Circuit Breakers
□ (2) NEMA size 2 Motor Starters including electronic overload protection
□ Alternating Relay and necessary components
□ (2) RED Pump Running Pilot Lights
□ (2) GREEN Pump Off Pilot Lights
□ Pump Select selector switch
□ Hand-Off-Auto selector switch
□ (2) Pump Elapsed Time Meters steel.
2.1.9 HARDWARE. All hardware, fabricated hangers, supports and brackets shall be 304 stainless
2.1.10 PIPE AND VALVES. New piping, valves, and related accessories shall be provided inside the wet-well.
2.1.10.1 Station Piping. Replace flanged fittings within wet well, and provide new piping as needed to adapt new components to use existing 3” ductile iron discharge pipe leaving the wet-well. All new piping inside the wet–well shall be 3” schedule 40 stainless steel.
2.1.10.2 Ball Check Valves/Gate Valves. Each pump shall have a horizontal pipe with a flanged ball check valve and flanged gate valve. Valves shall be of materials and coatings suitable for the intended environment, and be provided with galvanic isolation from the rest of the piping if furnished in a material other than stainless steel.
2.3 DEWATERING AND GRAY WATER BYPASS. The Contractor shall be responsible for preventing sewage from entering the wet-well during the rehabilitation process, a shut off valve adjacent to the wet-well is available for use to facilitate this. The Contractor shall take measures to prevent and/or remove weather related flooding or damage to work in progress. Under no circumstances shall the Contractor permit bypassed sewage, combined sewage or storm-water to discharge into open gutters, onto or into the ground, or into sanitary sewers. The Government shall maintain water levels in adjacent lagoon so as to prevent overflow and preclude the need for bypass pumping; the Contractor is responsible for initial dewatering of pump wet-well.
2.4 SITE WORK. Prior to final acceptance of the work, the sites shall be restored to original grade and condition. Work includes restoration of soil to original grade, seeding and mulching. The Contractor shall furnish additional top-soil as necessary to bring the grade of the surrounding ground elevation to within two inches of existing or to fill voids left over from equipment rutting.
2.5 FIELD SERVICE REQUIREMENTS. The supplier of the pumps and valves shall provide one (1) day of start-up service and operator training. The manufacturer’s representative shall provide written certification that the installation has been successfully started and pump stations can be put into service.
2.6 OPERATION AND MAINTENANCE MANUALS. Prior to final acceptance of the work, four
(4) complete system manuals with operation and maintenance manuals for all the equipment provided shall be provided prior to final acceptance.
3. CONTRACTOR FURNISHED EQUIPMENT AND MATERIALS.
3.1 GENERAL. All Contractor-furnished equipment and materials used in the performance of this contract shall be of suitable size and type and/or quality for the intended use. Except as otherwise provided herein, the Contractor shall provide all equipment necessary to perform the work described herein. Any materials found to be unsafe or not in conformity with the contract specifications shall not be used.
3.2 EQUIPMENT STORAGE. The Contractor will not be allowed to store any equipment on
Government property unless approved in advance by the Contracting Officer. If approval is given for equipment storage, the Government assumes no responsibility for the safety or security of equipment left on Government property. Equipment shall be removed from the work site as soon as possible after the completion of the work described herein.
3.3 MATERIALS DELIVERY AND STORAGE. Materials shall be delivered to the site in a dry and undamaged condition and stored out of contact with the ground at a location approved by the Contracting Officer. Materials may be stored at the work site during continuous working days if notification is given to the Contracting Officer in advance. The Government assumes no responsibility for the safety or security of materials left on Government property.
3.4 MATERIALS TO BE FURNISHED BY THE CONTRACTOR. Except as otherwise provided herein, the Contractor shall furnish all materials necessary to perform the work described herein, including, but not limited to; pumps, discharge bases, discharge pipe, valves, lids and hatches, float switches, lifting chains, guide rail systems, control panel, cable holder, top soil, seed, mulch and other related materials.
3.5 SUBMITTALS. Within Five (5) days following award, and prior to commencement of work, the
Contractor shall provide the following submittals as required by the specifications to the Contracting Officer. Submittals may be requested in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Submittals shall include items such as: Contractor’s, manufacturer’s or fabricator’s drawings; descriptive literature including catalog cuts, diagrams, operating charts or curves; test reports; samples; parts lists; certificates; and other such required submittals.
Submittals requiring Government approval shall be Scheduled and made prior to the acquisition of the material or equipment covered thereby. Submittals required shall be for Government approval (GA) or for information only (FIO) and shall be submitted as listed below. Three copies of data for Government approval (GA) and two copies of data for information only (FIO) shall be submitted.
3.5.1 SD-03, Product Data
a. Pump performance curves and tests procedures, (GA)
b. Complete pump technical data showing materials of construction, weight, type, and length of cable, (GA)
c. Pump shop drawings, (GA)
d. Complete motor data including input kW, shaft BHP, full load amps, locked rotor amps, NEMA code letter, motor efficiency, and power factor, (GA)
e. Manufacturers data for check valve and gate valve, (GA)
f. Electrical Cable Data for Motor Feeder Conductors (GA)
g. Electrical Disconnect Safety Switches including mounting stand/hardware, (GA)
e. Duplex Motor Control Panel including single line diagram, (GA)
3.5.2 SD-07, Certificates
a. Confined space program, (FIO)
3.5.3 SD-10, Operation and Maintenance Data
a. Operation and maintenance manuals for pumps, (GA)
b. Operation and maintenance manuals for valves, (GA)
3.5.4 TRANSMITTAL FORM (ENG 4025-R). The sample transmittal form (ENG Form 4025-R) shown in Appendix B shall be used for submitting the above data to the Contracting Officer in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. This form shall be properly completed by filling out all the heading blank spaces and identifying each item submitted. The form shall be submitted in original and one copy, and shall be numbered sequentially.
4. GOVERNMENT FURNISHED MATERIALS.
4.1 MATERIALS. The Government will supply to the Contractor, for use only in connection with this contract, the following described materials in amounts and at times necessary for the use by the Contractor to provide the necessary work described herein. The Contractor will receive Government-furnished materials at the Shelbyville Lake Project Office, 1989 State Highway 16, Shelbyville, Illinois. The Contractor shall evidence receipt of such materials by signing ENG Form 3059, Requisition on Warehouseman.
4.1.1 KEYS. The Government will furnish the necessary keys for access to the work site. NOTE:
DUPLICATION OF GOVERNMENT-FURNISHED KEYS IS NOT PERMITTED. The Contractor shall immediately report the loss of keys to the Contracting Officer. In the event that a Government-furnished key is lost, the Contractor is responsible for reimbursement of all costs incurred by the Government for replacement of entire lock systems throughout the lake project which are affected by the lost key.
Contractor costs shall include, but not be limited to, Government labor, replacement lock costs, replacement key costs, tumbler reworking and all contracted labor costs required to replace lock systems.
All lock systems required to be replaced will be equal quality to lock systems presently in place. The Government will determine the specific replacement lock system.
5. PERSONNEL.
5.1 LABOR REQUIRED. All employees including a state licensed plumber required to satisfactorily perform the work described herein shall be furnished by the Contractor.
5.2 SUPERVISION. The Contractor shall provide adequate supervision of his employees to insure compliance with the contract specifications. The Contractor shall furnish a telephone number and mailing address through which he can normally be contacted on a daily basis and must supply in writing the name(s) of his designated supervisor(s) who can be contacted on a daily basis.
6. PROTECTION OF RESOURCES.
6.1 PROTECTION OF THE ENVIRONMENT. This paragraph prescribes actions required for the prevention of environmental pollution during and as the result of operations under this contract. For the purpose of this specification, environmental pollution is defined as the presence of chemicals, physical or biological elements, or other agents which adversely affect human health or welfare; unfavorably alter ecological balances; affect other species or degrade the utility of the environment for aesthetic and recreational purposes. The control of environmental pollution requires consideration of air, water and land;
and involves noise, solid waste management of radiant energy and radioactive materials as well as other pollutants.
6.2 PROTECTION OF LAND RESOURCES. The contract areas on which the work is to be performed under this contract and the land resources adjacent thereto shall be preserved in their present condition.
6.3 PROTECTION OF WATER RESOURCES. Lakes, ditches, rivers, canals, waterways or reservoirs shall not be polluted with fuels, oils, bitumens, calcium chloride, insecticides, herbicides, or other similar materials harmful to fish, shellfish, or wildlife or materials which may be a detriment to outdoor recreation.
6.4 PROTECTION OF GOVERNMENT FACILITIES AND STRUCTURES. The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of his operations.
Reasonable care shall be used to avoid damage. Any such damage shall be repaired or the items replaced as directed by the Contracting Officer at no cost to the Government. If the Contractor does not make such repair or replacement, the cost thereof will be deducted from payments to be made to him. The Contractor shall advise the Contracting Officer of any damage to the facilities due to vandalism or other causes on the day he first notices such damage.
6.5 REMOVAL OF MATERIALS AND RUBBISH. Before final payment is made, the Contractor shall remove from the site of work, all his equipment and unused materials provided by him, any waste materials and rubbish resulting from the operations performed herein. The methods and locations of disposal of materials, wastes, effluents, trash, garbage, oil, grease, chemicals, etc., shall be in accordance with all local, state and federal laws and regulations and will not enter project lands, lakes, ditches, rivers, canals, waterways, or reservoirs.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Lithia Springs Wastewater Treatment Reha
FFP
The contactor shall furnish all labor, equipment, and materials necessary to replace the motors, pumps, valves, motor control panel, and electrical components, in accordance with all sections listed within the contact specifications.
FOB: Destination
PSC CD: S222
NET AMT
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 01-SEP-2022 TO
01-MAR-2023
N/A LAKE SHELBYVILLE PROJECT OFC
REBECCA WHEELER
US ARMY ENGR DIST ST LOUIS
1989 STATE HIGHWAY 16
SHELBYVILLE IL 62565-4631
217 774-3951 FOB: Destination
965116
CLAUSES INCORPORATED BY REFERENCE
52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.204-21 Basic Safeguarding of Covered Contractor Information Systems
NOV 2021
52.222-41 Service Contract Labor Standards AUG 2018 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-1 Disputes MAY 2014 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
APR 2012
52.249-8 Default (Fixed-Price Supply & Service) APR 1984 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General AUG 2019 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
DEC 2019
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.225-7036 Buy American--Free Trade Agreements--Balance of Payments Program--Basic
MAR 2022
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports
DEC 2018
CLAUSES INCORPORATED BY FULL TEXT
52.212-4 CONTRACT TERMS AND CONDITIONS--COMMERCIAL PRODUCTS AND COMMERCIAL
SERVICES (NOV 2021)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights-
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include--
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer--Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.--
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C.
3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall--
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the--
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C.
7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if--
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on--
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b.
destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m)…