This is a Statement of Work (SOW) for annual inspection and 5-year recertification Engineering Design Review (EDR) of fall arrest systems at two facilities: Newlon Building 1 and Fuel Cell Hangar Building 18, operated by the Department of the Army National Guard. The contractor must perform comprehensive physical inspections and engineering reviews to ensure all fall protection systems, including beam and trolley systems, Self-Retracting Lifelines (SRLs), railings, support structures, trolleys, and associated hardware comply with current OSHA regulations and ANSI Z359 standards. The inspection scope covers systems manufactured by Lee Grover/Flexible Lifeline Systems, LICO Steel Inc. (Building 1), and Fall Protection Systems (Building 18). A competent person must conduct visual and physical examinations of all components, verify manufacturer requirements and ANSI Z359.2-2017 compliance, and immediately red-tag any equipment failing inspection for removal, disposal, repair, or replacement.

The EDR must be performed by a Qualified Professional Engineer and shall include a thorough review of original system design, consultation with on-site personnel, evaluation of risk and hazard changes, and assessment of regulatory or standard changes since installation. All work must comply with OSHA General Duty Clause, ANSI Z359.2-2017 (inspection requirements), and ANSI Z359.6-2016 (5-year EDR requirements). Deliverables include proof of inspection certificates, complete drawings and reports detailing compliance status, identified deficiencies, and recommended remediation actions, as well as Qualified Professional Engineer-stamped drawings and 5-year EDR certification. The related solicitation amendment indicates a due date of September 17, 2026 at 1:00 PM CST.

View the file

Other files

File Type Posted
B7-Sign in Sheet.pdf PDF
Solicitation Amendment - W50S7G26QA0240001.pdf PDF
Solicitation Amendment W50S7G26QA0240001 SF 30.pdf PDF
A2-SOW-VM (002).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work: Newlon (Bldg 1) & Fuel Cell Hangar (Bldg 18)

1.0 Objective

This Statement of Work details the annual inspection and 5-year recertification Engineering Design Review (EDR) to be performed by the contractor. The objective is to ensure the fall arrest systems are in compliance with current OSHA and ANSI Z359 standards, identify any deficiencies, and accomplish the required 5-year recertification.

2.0 Scope of Work

The contractor will perform a comprehensive inspection and an Engineering Design Review (EDR) for the following systems located in the Newlon & Fuel Cell Hangars:

· Beam & Trolley FP Systems and SRLs identified in attached drawings.

· Bldg 1 Systems Manufactured By:

· Lee Grover/Flexible Lifeline Systems

· LICO Steel Inc.

· Bldg 18 System Manufactured By:

· Fall Protection Systems

2.1 Inspection

A competent person from the contractor will conduct a physical, on-site inspection of the systems including railing, support structure, trolleys, Self-retracting lifeline, and all associated hardware. The inspection will include:

· Visual and physical examination of all system components to ensure good working order.

· Verification that the systems meet the manufacturer's requirements and ANSI Z359.2-2017 standards.

· Any equipment or system that fails inspection will be immediately red-tagged and designated "out of service." The contractor will then review options for removal, disposal, repair, or replacement.

2.2 Engineering Design Review (EDR)

A Qualified Professional Engineer will perform a thorough EDR to bring the systems into compliance with the latest version of ANSI Z359. The review will include:

· A thorough review of the original system design and a consultation with on-site competent persons and authorized users.

· An evaluation of any changes in risks, hazards, or tasks since the system's original installation.

· An assessment of changes in regulations, standards, or other factors affecting the fall protection system.

· Qualified describes a person who, by possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training, and experience has successfully demonstrated the ability to solve or resolve problems relating to the subject matter, the work, or the project.

3.0 Compliance Standards

All work performed will be in accordance with the following standards to ensure the systems are recertified and safe for use:

· OSHA: General Duty Clause (Section 5(a)(1) of the Occupational Safety and Health Act of 1970)

· ANSI:

· ANSI Z359.2-2017 (Inspection requirements)

· ANSI Z359.6-2016 (5-Year EDR requirements)

4.0 Deliverables

Upon completion of the work, the contractor shall provide:

1. Proof of Inspection Certificate.

2. A full set of drawings and a report detailing the following outcomes:

· Confirmation of systems that are in compliance with current OSHA and ANSI standards.

· A list of any deficiencies found in non-compliant systems.

· Recommended repairs or remediation required to bring all systems back into compliance.

3. Qualified Professional Engineer stamped drawings/specifications and a 5-Year EDR Certification.