This is a revised feature work list attachment for the PKAA Querida Phase 2 Project in Colorado, detailing mine opening closure specifications and requirements. The document provides comprehensive information on eleven guaranteed closure projects and two contingent projects involving various mine features including prospect shafts, adits, and other excavations requiring remediation. The work encompasses multiple closure methods including machine backfill, corrugated steel pipe installations with bat ladders, bat grate sections, polyurethane foam closures, and steel grated shaft closures. Features range in size from small prospect shafts to large openings exceeding 29 feet by 31 feet, with depths varying from 7 feet to over 100 feet. All features include specific locations identified by UTM coordinates in NAD83 format, with detailed work descriptions and material requirements specified for each closure method.

The scope includes extensive stormwater sediment control measures requiring excelsior waddles installation on the downstream side of working areas, with quantities ranging from 25 to 50 linear feet per feature. Specific projects require additional materials such as 23 cubic yards of imported rockfill for feature Q02, concrete footers and W6x20 steel beams for the steel grated shaft closure at TH01, and 50 cubic yards of polyurethane foam for feature Q07. Road grading totaling 176 linear yards is necessary to access features TH01 and TH02. The document distinguishes between guaranteed work items presented in Table 1 and two not-guaranteed contingent features in Table 2, allowing for flexible project scope based on final site conditions and assessment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1

Table 1: Item 4.0 Querida - Querida Phase 2 – Feature Work List REVISED

Feature ID Type Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

KH02 Prospect Shaft

Excavated:

Eroded:12ft by 14ft

Present:12ft by 14ft

Depth:14 ft Lining:N/A

Drainage:No

Machine Backfill SWS 2 470342.96199972, 4220059.09132914

Machine Backfill with onsite material. No Rockfill is required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five (25) linear feet of excelsior waddles shall be installed on the downstream side of the working area under the direction of the PROJECT

MANAGER.

KH03

Prospect Shaft

Excavated:8ft by 4ft

Eroded:9ft by 5ft Present:9ft by 5ft

Depth:7 ft Lining:N/A

Drainage:No

Machine Backfill

SWS 2

470350.029071669

4220060.91476284

Machine Backfill with onsite material. No Rockfill is required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five (25) linear feet of excelsior waddles shall be installed on the downstream side of the working area under the direction of the PROJECT

MANAGER.

MT01 Adit

Excavated:4ft by 3ft

Eroded:7ft by 3ft Depth:100 ft Lining:Rock Drainage:No

Grated Corrugated Steel Pipe w/ Bat Ladder

SWS 10, 13

Drawing(s) 5, 6.2

470828.940524799 4220270.92483496

Excavate to determine extents. Install a 36-inch diameter twenty-foot (20 ft) length of twelve-gauge (12 ga.) corrugated steel pipe (CSP) with bat ladder in accordance with Corrugated Steel Pipe Specifications and Bat Grate Alternative. Approximately 5 feet of CSP will be set inside the opening.

Access door is required. The front 3 feet of backfill of the space between the Corrugated Steel Pipe and adit walls requires concreted durable rock that is a minimum of 4 inches in diameter. Drain pipe is NOT required.

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

MT02 Adit

Excavated:8ft by 5ft

Eroded:6ft by 3ft Present:6ft by 3ft

Depth:20 ft Lining:Rock Drainage:No

Grated Corrugated Steel Pipe w/ Bat Ladder

SWS 10, 13

Drawing(s) 5, 6.2

470752.95985247, 4220196.9185069

Excavate to determine extents. Install a 36-inch diameter ten foot (10 ft) length of twelve-gauge (12 ga.) corrugated steel pipe (CSP) with bat ladder in accordance with Corrugated Steel Pipe Specifications and Bat Grate Alternative. Approximately 5 feet of CSP will be set inside the opening.

Access door is required. The front 3 feet of backfill of the space between the Corrugated Steel Pipe and adit walls requires concreted durable rock that is a minimum of 4 inches in diameter. Drain pipe is NOT required.

Q01 Prospect Shaft

Excavated:

Eroded:17ft by 18ft

Present:17ft by 18ft

Depth:8 ft Lining:Rock Drainage:No

Machine Backfill SWS 2

471020.376756398

4219746.89630656

Machine Backfill with onsite material. No Rockfill is required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five (25) linear feet of excelsior waddles shall be installed on the downstream side of the working area under the direction of the PROJECT

MANAGER.

Q02 Shaft

Excavated:

Eroded:29ft by 31ft

Present:29ft by 31ft

Depth:12 ft Lining:Rock Drainage:No

Machine Backfill SWS 2

471194.101324968

4219646.11034739

Machine Backfill with onsite material.

Twenty-three (23) cubic yards of imported rock fill required then topped with on-site material.

Storm water sediment control measures shall be implemented prior to work on the closure. Fifty (50) linear feet of excelsior waddles shall be installed on the downstream side of the working area

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

Q03 Prospect Shaft

Excavated:

Eroded:21ft by 20ft

Present:21ft by 20ft

Depth:12 ft Lining:Rock +

Timber Drainage:No

Machine Backfill SWS 2 470531, 4219595

Remove branches and set aside. Machine Backfill with onsite material. No Rockfill is required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five (25) linear feet of excelsior waddles shall be installed on the downstream side of the working area under the direction of the PROJECT

MANAGER.

Q05 Adit

Excavated:

Eroded:16ft by 40ft

Present:16ft by 40ft

Depth:10 ft Lining:Rock Drainage:No

Machine Backfill SWS 2

470477.025762403

4219693.98857082

Trim surrounding tree branches to remove and potential fire danger.

Machine Backfill with onsite material. No Rockfill is required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five (25) linear feet of excelsior waddles shall be installed on the downstream side of the working area under the direction of the PROJECT

MANAGER.

Q06 Adit

Excavated:

Eroded:3ft by 5ft Present:3ft by 5ft

Depth:Unk ft Lining:Rock Drainage:No

Bat Grate

Section 11.0, Standard Drawing #6, Section 13.0, Standard Drawing

#6-2

470271.098682744

4219647.89025095

Remove door and set aside.

Construct a grated adit closure with a full-length bat ladder in accordance with Grate Adit Closure Specifications. An access door is not required. Drainpipes are not required.

Q07 Shaft

Excavated:8ft by 4ft

Eroded:20ft by 12ft Present:14ft by

10ft Depth:30+ ft Lining: Rock Drainage:No

Polyurethane Foam

Section 9.0 – Polyurethane Foam

Closure.

470252.940980377

4219676.00396547

Install a closure using Polyurethane Foam (PUF). Bottom form is NOT required. Fifty cubic yards (50CY) of PUF will be needed to plug the feature. The PUF will be allowed to cure for four (4) days prior to backfill. Hand backfill over PUF using on-site material.

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

TH01 Prospect Shaft

Excavated:13ft by 13ft

Eroded:18ft by 21ft Present:18ft by

21ft Depth:17 ft Lining:Rock Drainage:No

Steel Grated Shaft

Closure

Section 8.0 and Standard Drawing

#4

470199.94715346, 4219898.11075867

One hundred and seventy-six (176) linear yards of road grading is necessary to reach features TH01 and TH02. No imported fill is required.

Install a twenty-foot (20ft) by twenty-foot (20ft) steel grated shaft closure with concrete footers. Poor rock condition at the collar will require concrete footers. Three

(3) W6x20 steel beams are required. A bat cupola is NOT required.

Table 2: Item 5.0 Querida - Querida Phase 2 – Feature Work List REVISED – NOT GUARANTEED

Description of Mine Opening

Closure Method

General Bid Specifications and

Drawings

UTM

(X,Y) NAD83 Work Description / Notes

Q04 Prospect Shaft

Excavated:

Eroded:25ft by 27ft

Present:25ft by 27ft

Depth:10 ft Lining:Rock Drainage:No

Machine Backfill SWS 2

470441.615768645

4219805.38166667

Machine Backfill with onsite material. No Rockfill is required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five (25) linear feet of excelsior waddles shall be installed on the downstream side of the working area under the direction of the PROJECT

MANAGER.

TH02 Prospect Shaft

Excavated:

Eroded:26ft by 21ft

Present:26ft by 21ft

Depth:10 ft Lining:Rock Drainage:No

Machine Backfill SWS 2

470187.042494516

4219897.84981193

One hundred and seventy-six (176) linear yards of road grading is necessary to reach features TH01 and TH02. No imported fill is required.

Machine Backfill with onsite material. No Rockfill is required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five (25) linear feet of excelsior waddles shall be installed on the downstream side of the working area