This document is a justification for other than full and open competition for simplified acquisitions over the micro-purchase threshold up to the simplified acquisition threshold. The National Park Service Pacific West Region requires the urgent rental of emergency heavy equipment to open park roads in Death Valley National Park for administrative and emergency access after roads were flooded by Hurricane Hillary. Brief market research found most equipment in the area was already rented by other agencies and businesses responding to the storm. Without urgent action to access critical infrastructure like water and sewage systems, the park faces risk of further damages that could endanger human health. The contracting officer approved the justification on August 29, 2023.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 2

JUSTIFICATION & APPROVAL FOR OTHER THAN FULL AND OPEN COMPETITION

for SIMPLIFIED ACQUISITIONS OVER THE MICROPURCHASE THRESHOLD (See FAR

Part 2) UP TO SAT

(See FAR 13.106-1)

Last updated 6/2/2016

Date: ___08/24/2023_____________________

PR Number: ____40637334_____________________

1. Nature and/or description of the item/service being procured and its intended use (include the anticipated cost):

Emergency Heavy Equipment Rental for opening park roads for administrative and emergency traffic after Hurricane Hillary Flood events August 2023.. Anticipated cost is $30K

2. Sole Source Justification rationale (Check one and explain below):

______ Only one responsible source.

___X___ Urgent and compelling circumstances exist. Include critical delivery or performance dates, and when you became aware of the requirement. Provide a specific statement of the impact on

Government operations, financial or otherwise, if the required delivery or performance dates are not met.

______ Other _____________________________________________________

Explain: The DEVA roads were inundated with flood waters from the remanence of Hurricane Hillary.

Nearly all critical NPS systems such as Cow Creek Water System, Furnace Creek Water system, Stovepipe wells Sewer Treatment plan, Grapevine water system, Wild Rose Water System, etc. are not accessible on NPS roads. DEVA does not have enough functional heavy equipment to open these roads both for administrative access to maintain the systems and assess damage after the storm, but also for emergency vehicles to be able to leave the park.

Without urgent action, the park is at eminent risk of more catastrophic and unknown damages to critical infrastructure by not being able to access the areas; such as losing potable water to the housing areas and sewage overflows, which would pose a hazard to human health.

3. Market Research. Please explain the results or why one was not performed. State whether any other offers were received, or anyone expressed interest:

Brief market research was performed by performing searches on the SBA Dynamic Small Business

Search engine, reviewing past contracts for emergency equipment rentals and identifying business within a 300 mile radius from the remote area of Death Valley that have access to this type of equipment. The storm has left many business with empty rental lots as other agencies and private businesses have rented what little equipment was in the area already.

ATTACHMENT 2

JUSTIFICATION & APPROVAL FOR OTHER THAN FULL AND OPEN COMPETITION

for SIMPLIFIED ACQUISITIONS OVER THE MICROPURCHASE THRESHOLD (See FAR

Part 2) UP TO SAT

(See FAR 13.106-1)

Last updated 6/2/2016

(Signature) _______________________________________ (Date)__________________________

Type or Print Name: Charles Thompson

Title: Chief of Maintenance

(Signature) _______________________________________ (Date) ___________________________

Type or Print Name: Cris Stubitz

Title: Contracting Officer

2023-08-29T07:08:51-0700