This document is a Schedule of Items related to the Little Bear Campground Reconstruction solicitation. It details the various demolition, construction, and improvement tasks required for the campground and day use area, including site preparation, utility work, restroom and site furnishing installations, parking and walkway upgrades, and electrical service enhancements. The solicitation number is 1282B124R0046, and it is being issued by the U.S. Department of Agriculture Forest Service. A mandatory site visit is scheduled for August 23, 2024. The Schedule of Items lists the specific bid items, quantities, units, unit prices, and total prices for the base bid and several alternates, with a total project budget of approximately $3 million.

View the file

Other files

File Type Posted
A10_Amd_0003.pdf PDF
Amd_0002_Atch_3- Electrical Requirements Explanation.docx DOCX document
A10_Amd_0002_SF30.pdf PDF
Copy of A9_RFQ_Ques_Ans_Little_Bear.xlsx XLSX spreadsheet
Amd_0002_Atch-2_Schedule_of_Items_Little Bear.xlsx XLSX spreadsheet
A10_Amd_0001.pdf PDF
A10_1282B124R0046_RFP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule of Items Little Bear

SCHEDULE OF ITEMS
Location: Little Bear CG
Bid ItemDescriptionLocationQTYUnitUnit PriceTOTAL PRICE
1GENERAL REQUIREMENTS AND MOBILIZATION
AMobilization/DemobilizationDay Use + CG1LS
BConstruction Signing and Barricades for Public ClosureDay Use + CG1LS
CFencing for Tree Protection from Construction ActivityDay Use + CG1LS
DLayout Erosion Control MaterialsDay Use + CG1LS
MOBILIZATION TotalMethod of MeasureLSQ
2CONSTRUCTION SURVEYING AND STAKING
AConstruction Surveying and StakingDay Use + CG1LS
CONSTRUCTION SURVEYING AND STAKING TotalMethod of MeasureLSQ
3CLEARING AND GRUBBING
AClearing and GrubbingDay Use + CG1LS
CLEARING AND GRUBBING TotalMethod of MeasureLSQ
4DEMOLITION AND REMOVAL OF EXISTING INFRASTRUCTURE
ADemolition of existing vault toilets and associated concrete workDay Use + CG4EA
BDemolition of existing site furnishings - Day Use Area (boulder barriers, bulletin boards, signs, fish cleaning station)Day Use Area1LS
CDemolition of existing site furnishings - CG Area commons (boulder barriers, bulletin boards, signs)Campground1LS
DDemolition of existing site furnishings - CG Area individual sites (fire rings, picnic tables, grills, tent pads, signs)Campground36EA
EDemolition of existing asphalt path between fishing pier and bathroom and misc flatworkCampground2500SF
DEMOLITION AND REMOVAL OF EXISTING INFRASTRUCTURE TotalMethod of MeasureLSQ
5DEMOLITION AND REMOVAL OF EXISTING TREES
ADemolition and Removal of Existing TreesDay Use + CG151EA
DEMOLITION AND REMOVAL OF EXISTING TREES TotalMethod of MeasureAQ
6ROAD IMPROVEMENTS - ROAD GRADING AND DRAINAGE
ARoad Improvements (Widening and reshaping of road, construction of ditches and swales, construction of culverts, resurfacing of dayuse parking w/ gravel)Day Use + CG1LS
ROAD IMPROVEMENTS - ROAD GRADING AND DRAINAGE TotalMethod of MeasureLSQ
7CAMPGROUND WATER DISTRIBUTION SYSTEM REPLACEMENT
AWater line w/ rock excavation (WATER)Day Use + CG1LS
BAppurtenances: Valves, water fill stations, air relief, etc (WATER)Day Use + CG1LS
CHost site sewage holding tank includes connections & piping (SEWER)Day Use + CG1LS
CAMPGROUND WATER DISTRIBUTION SYSTEM REPLACEMENT TotalMethod of MeasureLSQ
8ELECTRICAL SERVICE - BASE BID
AAdditional excavation (not shared with water line)Entire Site100LF
B50 Amp PedestalsEntire Site1EA
C30 Amp PedestalsEntire Site0EA
DMain distribution panelEntire Site1EA
EMetering EquipmentEntire Site1EA
FWire and conduitEntire Site1LS
GTrenching Per DMEA Specs for Primary Power (excavate and backfill)Entire Site2300LF
HPrimary Wire, conduit and Elec Vaults (2) - DMEA Equipment CostEntire Site1LS
ELECTRICAL SERVICE - BASE BID Total
9CAMPGROUND IMPROVEMENTS
CAMPGROUND COMMON AREAS
APit Toilet Replacement & 5' Concrete apron (Includes structure, delivery and site preperation)Campground3EA
BFee Station Bulletin BoardCampground1EA
CFee Station Tube ReplacementCampground1EA
DOverall Campground Wayfinding SignageCampground1LS
EOverall Campground Walkways (Access to Existing fishing pier and Island Lake hiking trail)Campground283LF
FOverall Campground Boulder Barrier RocksCampground70EA
GOverall Campground ORAR Path to restrooms (4' width)Campground150LF
HDumpster PadCampground3EA
I6' Three-sided Fence Enclosure for Dumpster PadCampground3EA
J3-Panel Fee Station KioskCampground1EA
CAMPGROUND COMMON AREAS Total
CAMPSITES
KStone Retaining Walls within campsites (maximum 2.5' retaining per boulder course)Campground189LF
LTimber Stairs within campsites (5 - risers / approx. 30" grade change)Campground16EA
MWalkways connecting parking spurs and campsites (3' width typ)Campground754LF
NCampsite Improvements - Site Type 1 (New Construction, Back-In)
1Site Grading and LevelingCG Site6EA
2Parking Spur - Aggregate Base CourseCG Site6EA
3Metal WheelstopCG Site6EA
4Picnic TableCG Site6EA
2Fire RingCG Site6EA
3Tent PadCG Site6EA
4Facility PadCG Site6EA
5Bear BoxCG Site6EA
9Site Signage - Campground ID MarkerCG Site6EA
OCampsite Improvements - Site Type 2A (New Construction, Pull-Through)
2Site Grading and LevelingCG Site2EA
1Parking Spur - Aggregate Base CourseCG Site2EA
3Picnic TableCG Site2EA
4Fire RingCG Site2EA
5Tent PadCG Site2EA
6Facility PadCG Site2EA
7Bear BoxCG Site2EA
8Site Signage - Campground ID MarkerCG Site2EA
PCampsite Improvements - Site Type 2B (New Construction, Pull-Through, no tent pad)
1Site Grading and LevelingCG Site1EA
2Parking Spur - Aggregate Base CourseCG Site1EA
3Picnic TableCG Site1EA
4Fire RingCG Site1EA
5Facility PadCG Site1EA
6Bear BoxCG Site1EA
7Site Signage - Campground ID MarkerCG Site1EA
QCampsite Improvements - Site Type 3 (Reconstruction, Back-In)
1Site Grading and LevelingCG Site19EA
2Parking Spur - Aggregate Base CourseCG Site19EA
3Metal WheelstopCG Site19EA
4Picnic TableCG Site19EA
5Fire RingCG Site19EA
6Tent PadCG Site19EA
7Facility PadCG Site19EA
8Bear BoxCG Site19EA
9Site Signage - Campground ID MarkerCG Site19EA
RCampsite Improvements - Site Type 4 (Reconstruction, Pull-Through)
1Site Grading and LevelingCG Site6EA
2Parking Spur - Aggregate Base CourseCG Site6EA
3Picnic TableCG Site6EA
4Fire RingCG Site6EA
5Tent PadCG Site6EA
6Facility PadCG Site6EA
7Bear BoxCG Site6EA
8Site Signage - Campground ID MarkerCG Site6EA
CAMPSITES Total
CAMPGROUND IMPROVEMENTS Total
10DAY USE AREA IMPROVEMENTS
ASteel Wheel StopsDay Use Area2EA
BPit Toilet Replacement & Concrete apron (Includes structure, delivery and site preperation)Day Use Area1EA
CAccessible Concrete Path to Pit ToiletDay Use Area423SF
DAccessible Concrete Path to Pit ToiletDay Use Area2EA
EInterpretive Signage and InfrastructureDay Use Area1LS
FBoulder Barrier RocksDay Use Area45EA
GShore Path to Kayak AreaDay Use Area95LF
HShore Path to Kayak Area Stone StepsDay Use Area2EA
INew Paths to Existing Shoreline PathsDay Use Area280LF
DAY USE IMPROVEMENTS Total
11AS-BUILT DRAWINGS
AAll materials, equipment, labor and incidentals to produce electronic and hard copy as-built drawings.Entire Site1LS
AS-BUILT DRAWINGS Total

PROJECT BASE BID TOTAL

12ALTERNATES
ALT 1Campsite Improvements - Site Type 5 (New Construction Tent Walk-In)
1Clearing and GrubbingCG Site4EA
2Site Grading and LevelingCG Site4EA
3Parking Space - Aggregate Base CourseGroup Parking1932SF
4Metal Wheel StopGroup Parking5EA
5Site Signage - Group Parking ADA SignageGroup Parking1EA
6Site Signage - Walk In Site Directional SignageGroup Parking1EA
7Picnic TableCG Site4EA
8Fire RingCG Site4EA
9Tent PadCG Site4EA
10Facility PadCG Site4EA
11Bear BoxCG Site4EA
12Site Signage - Campground ID MarkerCG Site4EA
13Improved Path (Native Soil)CG Site336LF
14Improved Path Stone StepsCG Site3EA

ALT 2 Accessible Fishing Platform Improvements - Re-level and form existing platforms, better accessibility and safer edges. As Shown 2 EA

ALT 3 Day Use Gravel Parking Area Improvement (Grading and refresh of aggregate base course surface, decommissioning and revegetation of existing gravel areas) Day Use Area 1 LS

ALT 4 Day Use Parking Area Asphalt Paving and Striping (requires inclusion of ALT 3 scope) Day Use Area 1 LS

ALT 5 Existing Boat Ramp Improvements (improved asphalt vehicular access, expanded concrete boat ramp slab, improved walkways/retaining) As Shown 1 LS

ALT 6Electrical Service - Alternate 6
AAdditional excavation (not shared with water line)Entire Site130LF
B50 Amp PedestalsEntire Site1EA
C30 Amp PedestalsEntire Site3EA
DWire and ConduitEntire Site1LS
ELECTRICAL SERVICE - Alternate 6 Total
ALT 7Electrical Service - Alternate 7 (requires inclusion of ALT 6 scope)
AAdditional excavation (not shared with water line)Entire Site120LF
B50 Amp PedestalsEntire Site3EA
C30 Amp PedestalsEntire Site0EA
DWire and ConduitEntire Site1LS
ELECTRICAL SERVICE - Alternate 7 Total
ALT 8Electrical Service - Alternate 8 (requires inclusion of ALT 6 and ALT 7 scopes)
AAdditional excavation (not shared with water line)Entire Site150LF
B50 Amp PedestalsEntire Site1EA
C30 Amp PedestalsEntire Site3EA
DWire and ConduitEntire Site1LS
ELECTRICAL SERVICE - Alternate 8 Total
ALT 9Electrical Service - Alternate 9 (requires inclusion of ALT 6, ALT 7, and ALT 8 scopes)
AAdditional excavation (not shared with water line)Entire Site0LF
B50 Amp PedestalsEntire Site0EA
C30 Amp PedestalsEntire Site0EA
DWire and ConduitEntire Site1LS
ELECTRICAL SERVICE - Alternate 9 Total

PROJECT ALTERNATES TOTAL

PROJECT BASE BID TOTAL
PROJECT ALTERNATES TOTAL
GRAND TOTAL
Unit: LS (Lump Sum), EA (Each), LF (Linear Feet), SF (Square Feet)
DO NOT PRINT LINE!!! - Budget - 3 MILLION