This document is Appendix A: Technical Specifications for Service Work Items for the Bald Mountain Stewardship project on the Shasta-Trinity National Forest, McCloud Ranger District. The project objective is to create a 600-foot-wide ridgeline fuelbreak down Bald Mountain ridge via mechanical mastication and to construct two helispots for emergency access. The work encompasses 509 acres across Units 1-10 and includes four mandatory service items: (1) mechanical mastication of all brush and conifers less than 10 inches diameter breast height (DBH), with oaks, dogwood, and hardwood trees retained; (2) falling all dead standing trees within the project area and masticating tops and branches less than 10 inches, with exceptions for marked wildlife trees, trees with nests, and specific boundary conditions; (3) creation of two helispots by clearing all trees within 160-foot diameter circles (0.46 acres each) with material either piled or dispersed; and (4) maintenance of the existing Bald Mountain Jeep Trail and 38N36 road, including repairs to any damage caused by operations and installation of waterbars where needed for erosion control.

The contract establishes minimum acceptable quality levels (AQL) of 90 percent for Items 1-3 and 100 percent for Item 4, with work evaluated through informal visual inspections and formal verification plot inspections. Payment is calculated based on work quality percentages, with a 5 percent statistical variation adjustment applied to work quality at or above 85 percent. Work quality below 85 percent results in no payment and requires rework; quality between 85-94 percent receives reduced payment equal to the actual percentage plus 5 percent adjustment. Work is restricted during Northern Spotted Owl nesting season (February 1 through September 15), during periods of elevated fire risk, and in areas with protected botanical resources or discovered cultural/archaeological sites. The Contractor must notify the Contracting Officer's Representative (COR) when units begin, when problems arise, and when requesting inspections, with government inspection responses required within 5 working days.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bald Mountain Stewardship SSC Shasta-Trinity National Forest Page 1 of 8 McCloud Ranger District

Revised 01.06.2022

APPENDIX A

TECHNICAL SPECIFICATIONS FOR SERVICE WORK ITEMS

SECTION I – DESCRIPTION OF WORK:

The objective of this project is to create a linear ridgeline fuelbreak that can be used in the event of a wildfire or to facilitate prescribed burning. The project will create a 600-foot-wide ridgeline fuelbreak down Bald Mountain ridge via mastication. The project also creates two helispots that can be used in either situation. Objectives will be accomplished by the following:

1. Mechanically masticate brush and small trees.

2. Fall all dead standing trees within the fuel break. Masticate tops and branches less than 10” Diameter.

3. Create two helispots by falling all trees within a 160 foot diameter circle. Masticate tops and either disperse or consolidate boles depending on amount of material.

SECTION II – WORK ITEMS

Mandatory Item 1: Masticate brush and small trees:

Units 1-10 (509 Acres)

1. Mechanical mastication of all brush and conifers less than 10 inches DBH.

a. Oaks, dogwood, and other hardwood trees may be retained.

2. Tethering is required on slopes greater than 35%, or when excessive rutting occurs.

a. Excessive rutting is defined as ruts greater than 8” deep and longer than 12 feet.

3. Masticated brush and small conifers shall be cut as close to ground as possible without ground disturbance, but no taller than 6 inches.

4. Conifers up to 14” DBH may be cut/masticated to facilitate tether operations where needed.

5. Up to 10% of brush may be left in “retention clumps”

a. In areas difficult to access, rock outcrops, drainages, etc.

b. “Retention clumps” will not be left within 100 feet of road, ridgeline, or centerline of project.

c. “Retention clumps” will be as small as possible.

Mandatory Item 2: Fall dead standing trees:

Units 1-10 (509 Acres)

1. Fall all dead standing trees within the project area, unless:

a. It is marked as a “Wildlife Tree”.

b. It has a nest in it.

c. Is within 50 feet of the edge of project and is leaning away.

d. Has “wildlife tree characteristics” and is approved to leave by COR

2. Masticate tops and branches less than 10” diameter

3. Buck boles to ensure ground contact

4. No hung up trees will be left

5. Stump heights are not to exceed 6 inches

Mandatory Item 3: Create 2 Helispots:

Helispots are shown on Project Map

1. Fall all trees within a 160-foot diameter circle for each Helispot (.46 ac for each spot)

Page 2 of 8 McCloud Ranger District

2. Masticate tops and branches less than 10” diameter

3. Boles will be either piled or dispersed depending on amount of material

4. Helispot locations on map are approximate, actual locations will be selected to:

a. Minimize number of trees felled

b. Ensure Helispot is on ridgeline, with minimal slope.

c. Locations will be approved by COR

Mandatory Item 4: Maintain Access

1. Fix any damage caused to the existing “Bald Mountain Jeep Trail”, or 38N36 road, within project boundary.

a. Maintain existing level of drivability.

2. Waterbars may be required in high traffic areas, such as ridgeline “access path”

a. If excessive rutting occurs and will direct water flow along ridgeline “access path”

SECTION III – CONTROL OF WORK

The Contractor agrees to conduct its operations under this contract and other related business activities in compliance with Federal, State, and local statutes, standards, orders, permits and other regulations.

The Contractor shall meet all State and local environmental quality laws applicable to National Forest system lands.

Work may be done any time during the term of the contract, except under the following conditions:

(1) When conditions are such that operations shall be restricted or ceased due to increased fire risk.

a. See Fire Plan for PAL Area and restrictions

(2) When seasonal operating restrictions for Northern Spotted Owl are in effect

a. Between February 1 and September 15

(3) The government reserves the right to prioritize the order in which Units are treated.

(4) If any cultural or archeological sites are discovered during operations of this contract, work will be suspended in the immediate vicinity of the site until a reconnaissance survey is completed by the Forest Archeologist.

(5) There may be areas with protected botanical resources. These areas will be flagged by FS botanists and avoided.

SECTION IV – INSPECTION AND ACCEPTANCE

For All Work Items:

At any point during the project, the Contractor and/or Project Manager may request (documented through email, text, or hand-written request) an in the field consultation with the Forest Service to inspect work progress, review contract specifications, or clarify issues. The Forest Service shall respond to Contractor’s request within 5 working days, excluding weekends and federal holidays.

GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN

Government Inspection Procedures - The COR, or a designated inspector (GTM), will make periodic inspections while work is in progress, usually daily at first, as needed to assure work is proceeding satisfactorily. The Contractor shall notify the COR when units are started, when problems are encountered and when contract work needs government oversight.

Page 3 of 8 McCloud Ranger District

1. Each unit will be inspected as a separate unit. Unit will not be averaged with other units for acceptance or payment.

2. When units are completed and ready for government inspection, Contractor’s designated Project manager shall request unit inspection in writing, prior to moving out of the general area.

3. The COR, or designated inspector, will determine compliance with contract specifications through informal visual inspections. In the event visual inspection indicates work to be in non-compliance with specifications, prompt corrective action and/or rework shall be required.

Government Inspection Procedures – Formal (Plots)

1. In the event visual inspection indicates work and / or rework to be in non-compliance with contract specifications, a series of verification plots shall be installed by the Government to determine compliance with specifications and percent of satisfactory work for treatment of each unit not meeting specification as observed with visual inspection.

2. Government verification plots will consist of a series of fixed area plots along transects to record whether requirements are being met and to what extent.

3. Plots and grid will be distributed so that a representative sample is obtained.

4. The COR or designated inspector will mark the center of each plot on the ground using flagging, stakes, or pin flags. Additional flagging will be hung near the plot center so that it may be seen from a distance. The inspector will include the plot number, their initials and date on the flagging.

5. Plots will be numbered to correlate with the inspection form and transects on a unit map.

6. The minimum number of verification plots, per treatment unit, shall be as follows:

Unit Acreage Minimum No. of Plots 1 – 9 1 plot per 2 acres 10 – 29 10 plots 30 – 59 1 plot per 4 acres 60 – 99 20 plots 100 1 plot per 5 acres

7. Determination of acceptability of the work performed will be based on Government verification inspections and will be considered conclusive.

8. At each plot, the Government will examine the plot area and record findings on the items listed below:

a. Plot number

b. Number of trees to be left on plot.

c. Number of trees left on plot.

d. Number of satisfactory trees.

e. Number of deficient trees.

f. Number of excess trees.

- Stumps containing live limbs which are not in accordance with specifications herein will be counted as excess trees.

- Cut trees which are still attached at the stump will be counted as excess trees

- Trees meeting cut specifications will be counted as excess trees

Page 4 of 8 McCloud Ranger District

- Trees in excess of trees to be left will be counted as excess

9. Work quality will be calculated on the form as follows:

No. Trees Deficient + No. Excess Trees -------------------------------------------------- = % Unsatisfactory work No. Trees to be left

100% – % Unsatisfactory work = % Work Quality

Unsatisfactory Cutting

1. If the work quality falls below 85 percent, the COR will immediately notify the Contractor, in writing, and order him to improve the quality of subsequent tree cutting. If the quality of subsequent tree cutting is not raised above the 85 percent minimum acceptable standard within 24 business hours after receipt of such written notice, the Contractor’s right to proceed may be terminated and the contract considered in default.

2. When the work quality falls below 90 percent as a result of excess trees, the Government may elect to do one of the following:

(a) Order rework to be performed and withhold payment until excess trees are cut and the results of a post-rework Government inspection show work quality to be at least 85 percent or more. No rework shall be performed unless ordered or authorized by the COR.

(b) Order that no rework be performed and payment will either be made at a reduced rate, or not at all, as determined from the Thinning Inspection Report.

3. Repeated failure to produce work quality at or above the 85 percent minimum acceptable standard will be considered reason for contract termination and default action.

Reinspection Upon Contractor Request

1. If Government inspection results are unacceptable to the Contractor, a reinspection may be requested, in writing, within 5 business days after receipt of notice of said inspection results. The same inspection procedure will be used; however, the inspection pattern will be shifted so that new inspection plots will not overlap previously inspected plots.

2. If reinspection results – rounded up to the nearest whole percent – indicate a variance of more than 5 percent from the first inspection, the results of the second inspection will be used to calculate work quality and payment, and the Government will bear the cost of reinspection.

3. If reinspection results – rounded up to the nearest whole percent – are within 5 percent of the first inspection, plots from the initial inspection and the reinspection will be combined and used to calculate work quality and payment, and the Contractor shall bear the cost of reinspection.

Government Inspection Procedures – Items 1-4

Table 1 – Minimum Acceptable Quality Levels (AQL) of Work

ITEM DESCRIPTION SCHEDULE UNIT Min AQL

1 Masticate brush and small trees MANDATORY ACRE 90% 2 Fall dead standing trees MANDATORY ACRE 90% 3 Create 2 Helispots MANDATORY SPOT 90% 4 Maintain Access MANDATORY MILE 100%

Page 5 of 8 McCloud Ranger District

SECTION V – PAYMENT METHODS

Method of Measurement for Acreages Acreages were determined by using Global Positioning Systems (GPS). The acreage for each work item will be rounded to the nearest acre and is final unless:

a. The contract is modified or,

b. The Government makes a determination to remeasure or,

c. The Contractor exercises his/her option under the following Remeasurement provisions:

Remeasurement

1. The Contractor may request, in writing, remeasurement of any units under this contract if he/she feels that acreage stated on the project maps is incorrect. The remeasurement must be within the existing perimeter of the respective unit. No variance of the unit perimeters as laid out on the ground for this contract will be allowed.

All requests for remeasurement must be made prior to payment for each completed unit. Remeasurement will be performed by the Government.

2. If remeasurement indicates that a variance of ten percent or less exists on units of 1 to 5 acres, five percent or less exists on units of more than five but less than 20 acres, or if three percent or less exists on units of 20 acres or larger, the Contractor shall pay for the actual costs of the remeasurement. Under this condition, payment will be made on the acreage stated on the project maps. If the remeasurement indicates the actual acreage varies by more than the above factors from that stated on the project maps, the payment will be made on the remeasured acreage and the Forest Service will pay for the cost of the remeasurement.

Acceptance and Payment

1. Percentages as calculated herein shall be rounded to the nearest whole percent.

2. No allowance for variation or portion of a variation will be added which will create a percentage greater than 100 percent.

Acceptance and Payment – Item 1 Masticate brush and small trees

1. If informal visual inspection indicates acceptable work quality, the Contractor will be paid 100 percent of their bid rate.

2. In the event that formal inspections are used, the rate of payment to the Contractor will be calculated as follows:

(a) For work quality of 95 percent or higher, 5 percent (adjustment for statistical variation) will be added and the Contractor will be paid 100 percent of their bid rate.

(b) For work quality from 85 to 94 percent, the 5 percent will be added to the work quality percent and the Contractor will be paid the total multiplied by the bid rate.

(c) For work quality 84 percent and less, the 5 percent will not be added and there will be no payment made to the Contractor.

(d) If, after rework, the percentage of satisfactory work is between 85% and 94%, payment will be made by the actual percentage. If the percentage is less than 85%, the work is unacceptable, and no payment will be made.

Acceptance and Payment – Item 2 Fall dead standing trees

1. If informal visual inspection indicates acceptable work quality, the Contractor will be paid 100 percent of their bid rate.

2. In the event that formal inspections are used, the rate of payment to the Contractor will be calculated as follows:

(a) For work quality of 95 percent or higher, 5 percent (adjustment for statistical variation) will be added and the

Contractor will be paid 100 percent of their bid rate.

Page 6 of 8 McCloud Ranger District

(b) For work quality from 85 to 94 percent, the 5 percent will be added to the work quality percent and the Contractor will be paid the total multiplied by the bid rate.

(c) For work quality 84 percent and less, the 5 percent will not be added and there will be no payment made to the Contractor.

(d) If, after rework, the percentage of satisfactory work is between 85% and 94%, payment will be made by the actual percentage. If the percentage is less than 85%, the work is unacceptable, and no payment will be made.

Acceptance and Payment – Item 3 Create 2 Helispots

1. If informal visual inspection indicates acceptable work quality, the Contractor will be paid 100 percent of their bid rate.

Acceptance and Payment – Item 4 Maintain Access

1. Full payment will be made when visual inspection indicates specifications have been met and the roads are sufficiently maintained.

Acceptance and Payment

1. Percentages as calculated herein shall be rounded to the nearest whole percent.

2. No allowance for variation or portion of a variation will be added which will create a percentage greater than 100 percent.

3. Payment rate for work quality at or above 85% will be calculated as follows:

% Work Quality + 5 % Statistical Variation (SV) = % Payment rate

4. Examples:

(a) 2 Trees Deficient + 4 Trees Excess 6 ------------------------------------------- = --------- = 5.22% = 5% Unsatisfactory work 115 Trees to be left 115

100% – 5% = 95% Work Quality 95% + 5% (SV) = 100% Payment rate

(b) 2 Trees Deficient + 9 Trees Excess 11 ------------------------------------------- = --------- = 11.96% = 12% Unsatisfactory work 92 Trees to be left 92

100% – 12% = 88% Work Quality 88% + 5% (SV) = 93% Payment rate

2 Trees Deficient + 14 Trees Excess 16 -------------------------------------------- = --------- = 16.84% = 17% Unsatisfactory work 95 Trees to be left 95

100% – 17% = 83% Work Quality - - No payment made

Page 7 of 8 McCloud Ranger District

SECTION VI – DEFINITIONS

ACCEPTABLE QUALITY LEVEL (AQL): Acceptance of work will be based on compliance with all specifications corresponding to the appropriate task(s). A minimum AQL is required for all service work – hand or mechanical. The minimum AQL will receive a satisfactory performance rating.

BOLE SPACING: The horizontal distance in feet from the edge of one leave tree bole to another leave tree bole, measured from the outside bark of each tree.

CIRCULAR PLOT: A sample plot within a thinning unit that is used to determine the number of desirable trees and other contract specifications.

COARSE WOODY DEBRIS: Woody material left on the ground to meet wildlife habitat requirements.

CUT TREES: Trees that do not possess the characteristics of desirable leave trees and are required to be cut. As described by the contract or otherwise marked to be cut.

CUTTING UNIT: See Treatment Unit definition

DAMAGED TREES: Trees damaged beyond recovery. A tree that is larger than 2 feet in height, and has the top knocked out, is leaning more than 10 degrees, has less than one half of its original limbs, or has approximately 50% of bark removed from the circumference of the bole.

DBH: Diameter at breast height, measured at a point of 4.5 feet above the ground level on the uphill side of the tree.

DECKING: Stockpiling of trees in a designated area.

DEAD/DYING TREES: Trees with the crown foliage changing from green to red, yellow, or needleless. Any tree that has pitch tubes indicating Mountain Pine Beetle infestation.

HANG-UP TREE: Any cut tree suspended above ground level.

HELISPOT: A place cleared of trees and tall brush to land a helicopter. Usually a 20 foot radius landing pad with an additional 60 foot safety radius. Total radius is 80 feet, total diameter is 160 feet.

LEAVE TREE: Trees that possess desirable characteristics and that serve to create the basis for designated spacing requirements or are otherwise designated to be left.

PAYMENT UNIT: See Treatment Unit.

PERFORMANCE REQUIREMENTS SUMMARY (PRS): Identifies the key service outputs of the contract that will be evaluated by the Government to assure contract performance standards are met by the Contractor.

PILING: Material moved to an agreed upon location shall be piled for future treatment by Forest Service.

PROGRESSION OF WORK: Work conducted in a progressive, workmanlike and orderly manner by the Contractor.

SLASH: Woody material existing or created that has accumulated on the forest floor. Woody material includes logs, pieces of logs, tops, and branches.

UNIT: See Treatment Unit.

TEMPORARY ROADS: Non-permanent roads that are constructed by Contractor for the purpose of treatment unit access.

TREATMENT UNIT: An individual area on the ground in which activities will be performed and which may appear as a separate pay item in the Schedule of Items.

UNSATISFACTORY WORK: If work quality falls below the AQL, the COR will issue a work order or notice of noncompliance to the Contractor in writing. Untreated or unsatisfactory treated areas shall be reworked to obtain satisfactory work quality.

Page 8 of 8 McCloud Ranger District

WILDLIFE TREE: Standing tree marked to be reserved as a wildlife tree. Used by birds and small mammals for shelter, nesting, perching, etc.

SECTION I – DESCRIPTION OF WORK:
SECTION II – WORK ITEMS
Mandatory Item 1: Masticate brush and small trees:
Mandatory Item 2: Fall dead standing trees:
Mandatory Item 3: Create 2 Helispots:
Mandatory Item 4: Maintain Access
SECTION III – CONTROL OF WORK
SECTION IV – INSPECTION AND ACCEPTANCE
GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN
Government Inspection Procedures - The COR, or a designated inspector (GTM), will make periodic inspections while work is in progress, usually daily at first, as needed to assure work is proceeding satisfactorily. The Contractor shall notify the COR w...
Government Inspection Procedures – Formal (Plots)
Unsatisfactory Cutting
Government Inspection Procedures – Items 1-4
SECTION V – PAYMENT METHODS
Method of Measurement for Acreages
Remeasurement
Acceptance and Payment
Acceptance and Payment – Item 1 Masticate brush and small trees
Acceptance and Payment – Item 2 Fall dead standing trees
Acceptance and Payment – Item 3 Create 2 Helispots
Acceptance and Payment – Item 4 Maintain Access
Acceptance and Payment

SECTION VI – DEFINITIONS