This document outlines technical specifications for the reconstruction of the Silver Lake Campground in the Eldorado National Forest. The project involves reconstructing multiple campsite spurs and living areas, repairing damage to the driveway entrance, and demolishing 42 unimproved spurs. Key specifications include reconstructing 32 campsite spurs and living areas, reconstructing 105 feet of asphalt driveway entrance, and constructing 4 speed bumps. The project is located in Amador County, California and will involve clearing and grubbing, excavation and embankment work, aggregate base installation, asphalt paving, and grading according to the provided specifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_12970223R0028_Amd_0002.pdf | ||
| Sol_12970223R0028_Amd_0001.pdf | ||
| A1 Fire Plan.pdf | ||
| A1 SILVER LAKE CG RECON PHASE II_FINAL DWGs.pdf | ||
| Solicitation 12970223R0028.pdf | ||
| Davis Bacon CA20230007 06_30_2023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
SILVER LAKE CAMPGROUND RECONSTRUCTION PHASE II
(FINAL – 04/17/2023)
1.1 SCOPE OF CONTRACT
A. This project consists of reconstructing multiple campsite spurs and living areas of Silver Lake Campground East, as well as repairing damage to the driveway entrance.
1. The existing restrooms, potable water, and utilities are to remain, as designated.
Contractor is responsible for repairs if damage occurs as a result of fault or negligence.
B. Demolition work includes the following:
1. Demolition of 42 unimproved spurs, including obliteration of the existing asphalt.
C. New construction work includes the following:
1. Reconstruction of 32 unimproved camping spurs and living areas.
2. Reconstruction of approximately 105 feet of asphalt driveway entrance.
3. Construction of 4 speed bumps (Option bid item #1).
1.2 PROJECT LOCATION
The project is located in the Amador Ranger District of the Eldorado National Forest, Amador County, California, in Section T10 N R17 E. It is located approximately 36 miles Northeast of Pioneer, California. The project may be accessed from Highway 88.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction site will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access. The Contractor shall construct a temporary fence with appropriate signing around site during construction to prevent public access.
2. Contractor will provide all materials and labor necessary to protect streams and lakes, wet or dry, during construction activities. The Contractor will be required to submit an erosion control plan and receive approval from the COR, in writing, prior to the beginning of construction.
3. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
4. Dust Abatement: The contractor shall take precautions to prevent unnecessary wind-blown dust. It is especially important to prevent dust from blowing into areas that are in use by the public. Cover or water stockpiles. To the extent possible, construct road subgrades during off-peak recreation periods. Keep all exposed subgrades watered or use other approved method to prevent dust from becoming airborne.
5. Water is available at the site for construction purposes.
6. Toilet facilities are available at the site.
7. Contractor shall comply with all terms and conditions of any camping permit issued to allow use of premises. Any non-compliance will result in suspension of work until compliance is achieved.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Caltrans. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work or housing) on site.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 START DATE
A. September 15, 2023
1.8 CONTRACT TIME
A. Base Bid: 140 days
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3
1.9 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
Section 010250 – Construction Staking Section 011250 – Measure and Payment with Asphalt Section 011900 – Mobilization Section 013300 – Submittal Procedures Section 014100 – Quality Control Section 020000 – Environmental Concerns Section 020900 – Construction Area Traffic Control Devices Section 023701 – Sediment and Erosion Control Devices Section 024100 – Waste Material Disposal Section 026210 – Paths and Trails Section 033020 – Concrete from Packaged Dry Mix for Minor Structures Section 061000 – Carpentry and Lumber Section 101400 – Signs Section 311000 – Clearing and Grubbing Section 312000 – Earthwork Section 312010 – Select Borrow Section 312100 – Project Site Preparation and Grading Section 312225 – Excavation and Embankment Section 321200 – Warm Mix Asphalt Paving Section 321204 – Crushed Aggregate Base or Surface Course Section 322205 – Barrier Rocks Section 322640 – Pavement Marking Section 322706 – Asphalt Pavement Pulverizing
END OF SECTION C
May 2023
CONSTRUCTION STAKING 010250-1
USDA FOREST SERVICE, ELDORADO NATIONAL FOREST
SILVER LAKE CAMPGROUND RECONSTRUCTION PHASE II
SECTION 010250 - CONSTRUCTION STAKING
PART 1 - GENERAL
1.1 SUMMARY
A. This work shall consist of the construction staking of camping spurs, living areas, paths and road entrance in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.
1.2 QUALITY CONTROL
A. Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.
1.3 MEASUREMENT AND PAYMENT
A. Measurement shall be lump sum for surveying and staking the project through all phases of construction.
PART 2 - PRODUCTS
2.1 GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS
A. The Government will provide the contractor with a set of survey control sheets showing horizontal and vertical control for site to be staked. The Government will provide the Contractor with layout information that will include the Northing, Easting, and Elevations for centerline of roads, spurs and parking areas, edge of parking areas, and corners of buildings and other structures.
2.2 STAKES
A. Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:
1. Roads, parking lots, and parking spurs -Orange
2. Waterlines and utilities -Blue
3. Group units and paths -Red
CONSTRUCTION STAKING 010250-2
4. Buildings, excavation and grading -Yellow
2.3 SURVEY NOTE PAPER AND BOOKS
A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.
PART 3 - EXECUTION
3.1 GENERAL
A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract.
The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.
B. Accuracy requirements:
1. Minimum position close; 1/1000
2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)
3. Cross section and slope stake precision:
C. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.
D. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross section points will not exceed: 1.0 ft.
E. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%.
Clearing limits: 1.0 ft.
3.2 ESTABLISING AND REFERENCING IMPROVEMENT LOCATIONS
A. Access Roads, Parking Spurs, and Parking lots:
1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles as shown on the drawings.
2. Slope stakes shall be set at 50-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points. Slope stakes shall be set at 25 foot intervals around curves having a radius less than 100 feet.
B. Paths and Trails
CONSTRUCTION STAKING 010250-3
1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles as shown on the drawings.
2. Slope stakes shall be set at 10-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points.
3.3 DISCREPANCIES
A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.
3.4 VERTICAL CONTROL
A. Vertical control for construction shall be as referenced on the Drawings.
3.5 MARKING STAKES
A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;
PI Point of Intersection of tangents
PC Point of curvature
POC Point on curve
Pt Point of tangency
POT Point on tangent
RP Reference point
P P-line (preliminary location line)
L L-line (final location line)
BM Bench mark
TBM Temporary bench mark
BT Begin taper (any)
ET End taper (any)
C Cut
CONSTRUCTION STAKING 010250-4
F Fill
L Centerline
D Ditch
W Width
3.6 SURVEY NOTES
A. All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.
B. Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey was performed, and survey data or sketched that cannot be electronically recorded. The party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.
END OF SECTION 010250
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-1
SILVER LAKE CAMPGROUND RECONSTRUCTION PHASE II
SECTION 011250 - MEASUREMENT AND PAYMENT WITH ASPHALT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
7. For bituminous material, volumes will be measured at 60°F or will be corrected to the volume at 60°F by using ASTM D1250 for asphalts. Emulsified asphalt will be
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-2
measured at 60°F, or measured by converting the gallonage at another temperature to gallonage at 60°F by means of the following formula:
Gallons at 60°F = Gallons at A°F
1+0.00025 (A°F - 60°F)
* A°F is the temperature of the material at the time the gallonage is measured.
a. For vehicular shipments, net certified scale weights or weights based on certified volumes will be used as a basis of measurement. Measurements will be adjusted when bituminous material has been lost from the vehicle or the distributor, has been wasted, or has otherwise not been incorporated into this work. Determining true weights of hauling vehicles shall be made by weighing the empty vehicles at least once a day at the times the CO directs.
Each vehicle shall bear a plainly legible identification mark.
b. When bituminous materials are shipped, net certified weights, or volume corrected for loss of foaming, can be used for computing quantities.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-3
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-4
1.5 PRICE ADJUSTMENT (for Out-of-Specification Bituminous Materials)
A. Bituminous materials are defined as all types and grades of asphalt cement, liquid asphalt, emulsified asphalt, and dust oil.
B. If bituminous material fails one or more test requirements, and the Contracting Officer determines it is in the public interest to accept the material at a reduced price, the price reduction shall be based on the test results giving the largest percent price adjustment.
The contractor may remove and replace the defective material or accept the adjustment.
C. The price reduction shall apply to all pay items affected.
D. Price adjustment will be based on samples taken in duplicate in accordance with AASHTO T40 under the supervision of the Contracting Officer. Samples shall be sent to an authorized laboratory. The laboratory shall test one of each duplicate sample and retain the other. When any test result is not within the specification limits, the laboratory shall immediately notify the Contractor, the supplier, and the Contracting Officer. The Contractor, after notifying the Contracting Officer, may check test the retained sample.
E. If the retained sample tests satisfactorily, the material will be accepted. If the retained sample also fails, the following schedule of price adjustments shall apply. The average of test values for the two samples will determine the basis for price adjustment, except when test results on the samples differ by more than the applicable AASHTO or ASTM Repeatability Unit; then, the test result numerically nearest the specification requirement will be used. (A repeatability unit is defined as D2S or D2S% limit for single operator precision described in ASTM C670.)
F. The schedule of price adjustments shall not apply to the following tests:
Test AASHTO Test Method
Spot Test T102
Particle Charge T59
Ductility T51
G. Bituminous materials failing to meet specifications for these tests shall be removed and replaced.
H. See Table 011250-1 for the schedule of price adjustments for bituminous materials that do not meet specifications.
MEASUREMENT AND PAYMENT WITH ASPHALT 011250-5
Table 011250-1
Schedule of Price Adjustments for Out-of-Specification Bituminous Materials.
Application
Deviation from Specification Limit Measured in Reproducibility Units*.
Less than 1 1 but less than 2
2 but less than 3
3 or more
Price reduction applicable to bituminous base course and pavement mixture or to seal coat and bituminous material paid for as a separate item.
0% 5% 25% Remove & Replace
Price reduction applicable to bituminous material paid for as a separate item.
0% 10% 25% Remove & Replace
* A reproducibility unit is defined as D2S or D2S% limit for multi-laboratory precision described in ASTM recommended practice C670.
The Sieve Test (AASHTO T59) results may be exempt from the Schedule of Price Adjustments provided the contractor's quality assurance program includes checking the uniformity of bituminous spread rates in increments no greater than 1 foot over the width of the spray bar and variation between increments is no greater than 5 percent.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
MOBILIZATION 011900-1
SILVER LAKE CAMPGROUND RECONSTRUCTION PHASE II
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
April 2023
SUBMITTAL PROCEDURES 013300-1
SILVER LAKE CAMPGROUND RECONSTRUCTION PHASE II
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification sections within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
SUBMITTAL PROCEDURES 013300-2
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. Where appropriate, electronic submission is acceptable. CO will return two copies or electronic copy. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
SUBMITTAL PROCEDURES 013300-3
g. Compliance with recognized testing agency standards.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
SUBMITTAL PROCEDURES 013300-4
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, Contractor shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
SUBMITTAL PROCEDURES 013300-5
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section
Section Title Subsec tion Required Submittal
010250 Construction Staking 3.6 A Survey Notes
014130 Quality Control 1.3A Contractor quality control plan
014130 Quality Control 1.3B Permits, Licenses and Certificates
014130 Quality Control 1.3C Test and Inspection Reports
014130 Quality Control 1.2D As-Built Drawings
020900 Traffic Control 3.1A Traffic Control Plan
023701 Sediment & Erosion Control Measures 1.2A Sediment & Erosion Control Plan
101400 Signs 1.2A Sign List Submittal
033020 Concrete for Minor Structures 2.1 Materials
312000 Earthwork 1.3A Bedding and Backfill Certification
312225 Excavation and Embankment 1.3A Density Test Results
321200 Hot Mix Asphalt Paving 1.2A Product Data
321200 Hot Mix Asphalt Paving 1.3B Job Mix Design
321200 Hot Mix Asphalt Paving 1.3C Material Certificate
321204 Crushed Aggregate Base or Surface Course
1.2A Aggregate Base – Source, Gradation, Material Properties
321204 Crushed Aggregate Base or Surface Course
1.2B Compaction Test Results and Proctor
321204 Crushed Aggregate Base or Surface Course
1.2C Material Properties
322640 Pavement Markings 1.3A Product Data
END OF SECTION 013300
SUBMITTAL PROCEDURES 013300-6
QUALITY CONTROL 014100-1
SILVER LAKE CAMPGROUND RECONSTRUCTION PHASE II
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
D. As-Built Drawings
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
QUALITY CONTROL 014100-2
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit three copies of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
QUALITY CONTROL 014100-3
6. Reference Specification Section(s).
7. Complete test or inspection data.
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and reinspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency
312225 3.11B Moisture-Density Relationship One Test for Each Soil Type Encountered
312225 3.11B Compaction – Subgrade One test every 1000
sq. yd. of subgrade
321200 3.9B Gradation and Asphalt Content One per 700 tons or Min. of 1 per Project
QUALITY CONTROL 014100-4
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency
321200 3.9C Field Density Tests – Asphalt One test for every 300
sq. yd. of pavement
321204 3.4A Compaction Tests – Road Base and Surface Course
One test for every 300
sq. yd. of aggregate
329310 1.4B Topsoil Analysis One test per planting strip
332228 3.7C Compaction Tests One test for every 12 inches of lift placed
END OF SECTION 014100
ENVIRONMENTAL CONDITIONS 020000-1
SILVER LAKE CAMPGROUND RECONSTRUCTION PHASE II
SECTION 020000 – ENVIRONMENTAL CONCERNS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Seismic Conditions
2. Weather Conditions
3. Elevation
1.2 APPROXIMATE COORDINATES
A. Silver Lake East Campground: N 38.672° W120.120°
1.3 WEATHER CONDITIONS
A. Freezing conditions exist during the winter months.
B. 100 degree plus temperatures exist during the summer months.
C. Ground Snow Load: 300 psf
1.4 ELEVATION
A. Silver Lake East Campground: 7,250 +/- ft
1.5 DESIGN WIND SPEED
A. Per CBC requirements.
END OF SECTION 020000
CONSTRUCTION AREA TRAFFIC CONTROL DEVICES 020900-1
SILVER LAKE CAMPGROUND RECONSTRUCTION PHASE II
SECTION 020900 – CONSTRUCTION AREA TRAFFIC CONTROL DEVICES
PART 1 - GENERAL
1.1 This section sets forth requirements concerning possible flagging (if traffic volume dictates) and traffic handling equipment and devices used in carrying out the Contractor’s responsibilities for public convenience and public safety. This section applies to all work associated within each project site and hauling of materials & equipment into and out of each site, waste area, and borrow site.
1.2 Attention is directed to the Manual on Uniform Traffic Control Devices (MUTCD) for Streets and Highways, latest edition, published by the U.S. Department of Transportation, Federal Highway Administration. The contents of this manual are incorporated by reference in its entirety into this specification.
PART 2 - PRODUCTS
2.1 BARRICADES
1. Appropriate barricades and construction area signs shall be furnished, installed, maintained, and removed when no longer required.
PART 3 - EXECUTION
3.1 TRAFFIC CONTROL PLAN
A. The Contractor shall develop a Traffic Control Plan. The plan shall be developed, submitted to the Contracting Officer, and approved by the Contracting Officer before commencing construction activities. The plan shall show and describe how traffic will be provided for during the construction activities. The Traffic Control Plan shall include necessary and required construction area signs and conform to the provisions of the latest edition of the MUTCD. The Contractor shall be responsible for coordination with the onsite inspector.
B. During any blasting, hauling, and excavation operations, the highway may be closed and public traffic stopped for periods not to exceed ½ hours. After each closure, all accumulated traffic shall be allowed to pass through the work before another closure.
C. Should the Contractor decide to use the provisions in the previous paragraph they shall place signs advising the public of the possible delays. The signs shall be commercial quality and of sufficient size to be easily read by passing motorists.
END OF SECTION 026210
SEDIMENT AND EROSION CONTROL MEASURES 023701-1
SILVER LAKE CAMPGROUND RECONSTRUCTION PHASE II
SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES
PART 1 - GENERAL
1.1 The work under this section consists of furnishing all necessary labor, equipment, materials, and performing all operations in connection with construction sediment and control measures.
A. General
1. All erosion and sediment control measures are to be placed prior to any disturbance caused by grading and or excavation and shall conform to the requirements of the appropriate regulatory agency for the State.
2. The Contractor shall be solely responsible for ensuring that erosion and sediment control measures are implemented and maintained at the site.
3. Soil disturbing activities include but are not limited to: Clearing and grubbing, roadway and parking area construction, construction or modification of site drainage, and grading.
4. The Contractor shall remove temporary sediment and erosion control measures prior to contract closeout, unless determined otherwise.
1.2 SUBMITTALS
A. The Contractor shall be required to submit a sediment and erosion control plan in accordance with this specification for approval by the Contracting Officer 2 weeks prior to start of work.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Synthetic Filter Fabric for silt fences.
1. Pervious sheet of polypropylene, nylon, or polyethylene fabric conforming to the following physical and hydraulic characteristics:
• Physical Properties (Min.) Requirement Test Method
• Grab Tensile, lbs. W120/F100 ASTM-D-4632
SEDIMENT AND EROSION CONTROL MEASURES 023701-2
• Grab Elongation, % 15 ASTM-D-4632
• Mullen Burst, psi 275 ASTM-D-3786
• Puncture, lbs. 65 ASTM-D-4833
• Trapezoidal Tear, lbs. 50 ASTM-D-4533
• UV Resistance, % 80 ASTM-D-4355
• AOS, US Sieve # 30/40 ASTM-D-4751
• Permittivity gal/min-sq. ft. 90 ASTM-D-4491
2. Filter fabric should contain ultraviolet ray inhibitors and stabilizers to provide a minimum of 6 months of expected usable construction life at a temperature range of 0 to 120 F.
3. Support Posts: 4 foot - 2 x 2 wood.
B. Straw Bales.
1. Oat or wheat straw, free from weeds, viable weed seeds, foreign matter detrimental to plant life, and dry.
a. Grass hay bales are not acceptable.
b. In order to prevent deterioration of the bindings, all bales shall be either wire-bound or string-tied so that bindings are oriented around the sides rather than along the tops and bottoms of the bales.
PART 3 - EXECUTION
3.1 CONSTRUCTION
A. Install straw bales at local drainage ways to prevent silt intrusion upon adjacent drainage courses. Remove straw bales following establishment of vegetation cover and utilize as mulch at swales or on steep slopes.
B. Prior to construction, install silt fence along the downhill construction limits to prevent silt intrusion upon adjacent land.
C. Install sediment and erosion control measures on the down slope toe of all top soil stock piles.
D. Maintain and remove all erosion controls as specified.
3.2 DUST CONTROL
A. In areas subject to surface and air movement of dust, where on-site or off-site damage is likely to occur, one or more of the following preventive measures shall be taken for dust control:
SEDIMENT AND EROSION CONTROL MEASURES 023701-3
1. Minimize the period of soil exposure through the use of temporary ground cover and other temporary stabilization practices.
2. Sprinkle the site with water until surface is wet. Repeat as needed.
3.3 SILT FENCE
A. Silt fences are appropriate for the following general locations:
1. Immediately upstream of the point(s) of runoff discharge from a site before flow becomes concentrated. Below disturbed areas where runoff may occur in the form of overland flow.
2. Along the down slope toe of all top soil stock piles.
B. Materials.
1. Utilize standard strength synthetic filter fabric for sediment barriers. The filter fabric shall be purchased in a continuous roll cut to the length of the barrier to avoid the use of joints. When joints are necessary, filter cloth shall be spliced together only at a support post, with a minimum 6 inch overlap, and securely sealed.
2. The standard strength filter fabric shall be stapled or wired to the fence and 6 inches of the fabric shall be extended into the ground. Filter fabric shall not be stapled to existing trees.
3. Support posts shall be spaced at a maximum 6 feet and driven securely into the ground a minimum of 24 inches.
4. Filter fabric shall be buried a minimum of 12 inches.
5. The height of a silt fence shall not exceed 36…