A1_Scope_of_Work_6_pages.docx
DOCX document 28 KB Posted
- Attached to
- August Roads (CA2023-1) 27N02/29N30
- Solicitation number
- 12970224R0022
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Scope of Work (SOW) for the reconstruction of multiple forest roads on the Mad River Ranger District of the Six Rivers National Forest. The work consists of reconstructing roadway, embankments, and fill-slopes using reinforced soil slopes, biaxial geogrid, underdrains, erosion control, and new culvert installations. The project location and access details are provided, along with the operating season, equipment requirements, and submittal items. The applicable Federal Highway Administration's Standard Specifications for Construction of Roads and Bridges (FP-14) and associated Forest Service Supplemental Specifications are incorporated. The related federal contract opportunity is for the August Roads (CA2023-1) 27N02/29N30 project, solicitation number 12970224R0022, issued by the USDA Forest Service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_12970224R0022_Amd_0001.pdf | ||
| A11_Q_and_A_0001.docx | DOCX document | |
| A1_PAL_Fire_Plan__6_pages.docx | DOCX document | |
| A1_FS_Supplemental_Specfications_to_FP14_31_pages.docx | DOCX document | |
| A1_Photo_Gallery_2024_MAD_RIVER_ERFO_PROJECT_7_pages.pdf | ||
| A1_Maps_ALL_2_pages.pdf | ||
| A10_Davis_Bacon_Act_WD_CA20240007_44_pages.pdf | ||
| A1_Drawings_ERFO_ALL_CAD_26_pages.pdf | ||
| Sol_12970224R0022.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
SIX RIVERS NATIONAL FOREST
MAD RIVER RANGER DISTRICT
2024 MAD RIVER ERFO PROJECT
SCOPE OF WORK
The intent for this contract is to secure services for the reconstruction of FS road 27N02, 29N30 and its embankments which have multiple fill-slope failures on the Mad River Ranger District of Six Rivers National Forest.
Reconstruct the roadway, embankment, and fill-slope to match its existing width and profile. Work consists of reconstructing embankmments and fill-slopes with reinforced soil slopes, biaxial geogrid, geocomposite underdrains, rolled erosion control mat, and seeding. Additionally, selected sites require the removal and installation of corrugated steel culverts. This consists of disposing the existing culvert and replacing it with a new, upsized culvert along with the placement of surface aggregate, seeding, and mulching areas of exposed soil with straw. The roadway surface will consist of aggregate base course, asphalt concrete, and permanent pavement markings (aka fogline).
The contractor shall carefully examine the existing conditions and information, shall become familiar with the nature and location of the work, site constraints related to ground slopes and terrain. The contractor shall examine the nature of the soil and subsoil conditions, and the nature and extent of the materials that will be encountered during the construction operations and any existing site conditions that may affect the project, prior to the beginning of work.
The contractor is responsible for any road reconditioning and brushing necessary to access project sites and complete project work and is incidental to other items of work.
Unless otherwise provided, the Contractor shall furnish all labor, transportation, equipment, tools, supervision, materials and any incidentals necessary to accomplish work.
PROJECT LOCATION AND ACCESS
The project area is on the Mad River Ranger District of Six Rivers National Forest.
Mad River: From Eureka take Highway 101 South to Highway 36 near Fortuna, California. Take Highway 36 east past the town of Dinsmore, continue east to the Mad River Ranger District Office.The estimated time of travel is approximately 1 hour and 30 minutes.
29N30: From Highway 36 east, make a right onto Lower Mad River Road (County Road 504). Approximately 40 minutes will pass by until you come upon Barry Creek Bridge on the left fork onto Wildwood Mad River Road (aka 29N30).
27N02: From Highway 36 east, make a right onto Lower Mad River Road (County Road 504). Approximately 40 minutes will pass until you reach Barry Creek Rd/Wildwood Road. Turn left onto Upper Mad River Road County Road 501), crossing over the bridge, and drive approximately 10 minutes until you reach FS road 27N02.
OPERATING SEASON
Operating season shall be year-round except where prohibited by snow or wet weather. Between October 15th and May 15th wet weather operating restrictions shall apply and work will be tightly controlled and monitored for erosion control and preventive measures. At the discretion of the Forest Service, work may be suspended for wet weather before startup or during operations when conditions warrant.
Some roads also have limited operating periods (LOPs) due to wildlife protection measures. Limited operating periods, if any, are shown in the road logs.
Northern Spotted Owl LOP for Road 29N30 is from February 1 to July 9 and 27N02 will not require LOPs. COR will notify contractor if these requirements are lifted early.
EQUIPMENT
All equipment shall be suitable for the purpose intended and shall meet all requirements of the Occupational Safety and Health Act. The Contracting Officer may order the removal or require the replacement of any unsatisfactory equipment.
All vehicles and machinery operating on or from the traveled way or road shoulder shall have flashing lights or rotary beacons operated continuously while work is in progress. All equipment shall be equipped with a standard slow moving vehicle emblem. Truck headlights shall be on while operated. Backup warning devices shall be required on self-propelled equipment in excess of 8,000 pounds gross vehicular weight.
Vehicles and machinery not currently used in decommissioning operations shall be parked off the traveled way at a location that minimizes interference with normal use of the road.
Equipment Cleaning
The contractor shall clean all vehicles and equipment before entry into the Mad River Ranger District unless the cleaning requirement is waived in writing by the Forest Service. Thereafter, all vehicles and equipment that leave the Mad River Ranger District or enter infested portions of the district must be cleaned prior to their reentry, unless waived in writing by the Forest Service. All cleaning of vehicles or equipment shall be done at sites agreed to by the Forest Service and the Contractor. The water used for washing will be from a source in a non-infested drainage. The Forest Service shall inspect all vehicles and equipment prior to entry, as appropriate and determined necessary. Infested and uninfested areas will be determined by the Forest Service. Cleaning shall include the removal of soil by steam cleaning or use of high pressure water spray.
SUBMITTALS
SUBMITTAL REQUIREMENTS
SUBMITTALS
The following submittals are required for this project:
Construction Schedule
Safety Plan
Traffic Control Plan (Ref FP-14 156)
MATERIAL CERTIFICATIONS AND TESTING REPORTS
| The following material certifications and/or testing reports shall be submitted on this project: Title |
| Referenced by Specification No |
| Weed-Free Mulch Certification |
| 713.05 |
SPECIAL CONTRACT REQUIREMENTS
Use of Premises
(a) Forest Service Regulations for Use of Campground prohibits occupancy of developed recreation sites for other than primarily recreation purposes. One camp unit will be allowed at the project site for use by a watchman.
(b) A storage site will be permitted at a designated site within the project area. The Forest Service assumes no liability for materials stored within the storage site. The Contractor will be allowed to erect a temporary fence to secure materials and equipment; however, the fence shall be removed, and the site restored prior to final acceptance of the contract.
(c) When the Contractor’s operations require a temporary electrical power distribution system, the system shall comply with the National Electrical Code, applicable local codes, and utility regulations. The Contractor shall make all arrangements with the serving utility for temporary power and shall pay the serving utility for all applicable fees and power consumed.
(d) Potable water and sanitary facilities are NOT available for use during construction.
(e) The Contractor is authorized to use roads that are part of the construction project and those Forest Service Roads designated below for performance of work under this contract.
(f) The Contractor is responsible for all road maintenance and repair work caused by their operations.
| Road No. |
| Road Termini |
| Authorizations, Restrictions or Requirements |
| Maintenance Required |
| 27N02 |
| Site 1-MP0.7 |
| None |
| Construction |
| 27N02 |
| Site 2-MP1.1 |
| None |
| Construction |
| 27N02 |
| Site 3-MP1.2 |
| None |
| Construction |
29N30
| Site 1-MP3.2 |
| None |
| Construction |
| 29N30 |
| Site 2-MP3.8 |
| None |
| Construction |
| 29N30 |
| Site 3-MP3.94 |
| None |
| Construction |
| 29N30 |
| Site 4-MP4.9 |
| None |
| Construction |
Load Limits - All vehicles and equipment shall not exceed State legal highway loads and widths or posted limits without valid State and Forest Service overload, over-width permits. Forest Service overload permits for this project may be obtained from the Mad River District Ranger.
Heritage/Archeology
(a) In the event that cultural resources are discovered during implementation, all work in the area shall cease and the Forest Heritage Program Manager shall be notified immediately. Any inadvertent discoveries within the project boundary shall be protected utilizing Standard Protection Measures as stipulated in the First Amended Region 5 Programmatic Agreement (2018 R5 PA).
(b) Should inadvertent effects to or unanticipated discoveries of human remains be made on Region 5 lands, the County Coroner (California Health and Safety Code 7050.5(b)) shall be notified immediately. If the remains are determined to be Native American or if Native American cultural items pursuant to NAGPRA are uncovered, the provisions of NAGPRA and its regulations at 43 CFR 10 and ARPA at 43 CFR 7 shall be followed on federal lands (R5 PA Stipulation 7.9 (a)).
Special Project Specifications are physically incorporated within this solicitation, beginning after the list of applicable Standard Project Specifications.
The following Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects issued in 2014 (FP-14) are applicable to this contract:
| APPLICABLE FP-14 STANDARD SPECIFICATIONS |
| DATE |
| Section 101. — TERMS, FORMAT, AND DEFINITIONS |
| 2014 |
| Section 102. — BID, AWARD, AND EXECUTION OF CONTRACT |
| 2014 |
| Section 103. — SCOPE OF WORK |
| 2014 |
| Section 104. — CONTROL OF WORK |
| 2014 |
| Section 106. — ACCEPTANCE OF WORK |
| 2014 |
| Section 107. — LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC |
| 2014 |
| Section 108. — PROSECUTION AND PROGRESS |
| 2014 |
| Section 109. — MEASUREMENT AND PAYMENT |
| 2014 |
| Section 151. — MOBILIZATION |
| 2014 |
| Section 152. — CONSTRUCTION SURVEY AND STAKING |
| 2014 |
| Section 153. — CONTRACTOR QUALITY CONTROL |
| 2014 |
| Section 154. — CONTRACTOR SAMPLING AND TESTING |
| 2014 |
| Section 155. — SCHEDULES FOR CONSTRUCTION CONTRACTS |
| 2014 |
| Section 156. — PUBLIC TRAFFIC |
| 2014 |
| Section 204. — EXCAVATION AND EMBANKMENT |
| 2014 |
| Section 207. — EARTHWORK GEOSYNTHETICS |
| 2014 |
| Section 302. — MINOR CRUSHED AGGREGATE |
| 2014 |
| Section 403. — ASPHALT CONCRETE |
| 2014 |
| Section 602. — CULVERTS AND DRAINS |
| 2014 |
| Section 605. — UNDERDRAINS, SHEET DRAINS, AND PAVEMENT EDGE DRAINS |
| 2014 |
| Section 625. — TURF ESTABLISHMENT |
| 2014 |
| Section 629. — ROLLED EROSION CONTROL PRODUCTS & CELLULAR CONFINEMENT SYSTEMS |
| 2014 |
| Section 634. — PERMANENT PAVEMENT MARKINGS |
| 2014 |
The following Forest Service Supplemental Specifications (FSSS) to the FP-14 are applicable to this contract:
| Description |
| Revision Date |
| Preface |
| 5/14/2020 |
| 101 - Terms, Format, and Definitions |
| 11/9/2016 |
| 101.01 Meaning of Terms |
| 11/9/2016 |
| 101.03 Abbreviations. |
| 11/9/2016 |
| 101.04 Definitions. |
| 1/22/2020 |
| 102 - Bid, Award, and Execution of Contract |
| 11/9/2016 |
| 103 - Scope of Work |
| 11/9/2016 |
| 104 - Control of Work |
| 11/9/2016 |
| 104.06 Use of Roads by Contractor |
| 11/9/2016 |
106 - Acceptance of Work
| 106.01 Conformity with Contract Requirements. |
| 7/18/2017 |
| 106.02 Visual Inspection |
| 11/9/2016 |
| 106.07 Partial and Final Acceptance |
| 11/1/2016 |
107 - Legal Relations and Responsibility to the Public
| 107.05 Responsibility for Damage Claims. |
| 7/18/2017 |
| 108 - Prosecution and Progress |
| 11/9/2016 |
| 109 - Measurement and Payment |
| 11/9/2026 |
| 109.01 Measurement of Work |
| 2/22/2019 |
| 109.02 Measurement Terms and Definitions |
| 11/9/2016 |
| 155 - Schedules for Construction Contracts |
| 11/9/2016 |
203 - Removal of Structures and Obstructions
| 203.04 (b) General. |
| 11/2/2016 |
| 203.05 Disposing of Material. |
| 9/10/2018 |
| 209.-Structure Excavation and Backfill |
| 7/18/2017 |
209.9 (a)-General
209.10 (c)-Compaction Method 3
| 704-Soil |
| 7/18/2017 |
File details come from the government source that posted it. Updated .