A#1 PreBid Agenda & Discussion.pdf
PDF 4 MB Posted
- Solicitation number
- RFP PMAA 20260000000000000020 2
- Issued by
- Grand County, Colorado
About this file
This is a pre-bid agenda and discussion document for the Spring Creek Dam Rehabilitation project, a Construction Manager/General Contractor (CM/GC) procurement issued by Colorado Parks and Wildlife (CPW) in partnership with the Colorado Department of Natural Resources (DNR). The project involves rehabilitation services for a high-hazard dam located at approximately 10,000 feet elevation in the GMUG National Forest, with primary scope including removal and replacement of the spillway, extensive filter blanket installation on the downstream face, possible access road improvements, riprap placement, site clearing and revegetation, and instrumentation. The estimated construction cost is $8-10 million. The mandatory pre-proposal on-site meeting is scheduled for May 20, 2026 at 1:00 PM (MDT). Written clarification requests are due by May 25, 2026 at 5:00 PM (MDT), with responses posted May 29, 2026. Proposals must be submitted by June 10, 2026 at 10:00 PM (MDT), followed by a public proposal opening at 12:00 PM the same day. Shortlist notifications occur July 6, 2026, with interviews scheduled for July 9-10, 2026. The notice of award recommendation is targeted for July 14, 2026, with contract execution anticipated in mid-August 2026. The preconstruction phase is scheduled from September 2026 through May 2027, followed by the construction phase from May/June 2027 through October 2028.
The CM/GC delivery method was selected to manage project challenges including the remote and confined site, short construction season (typically mid-May through late October/early November), difficult water control due to natural springs, and heavy recreational use on narrow mountainous access roads. The contractor will serve in an advisory capacity during preconstruction, providing expertise in cost estimating, risk assessment and mitigation, value engineering, constructability reviews, and construction phasing. Separate contracts exist for preconstruction and construction phases. Following 90% design completion, the contractor submits a Construction Agreed Price (CAP) proposal for CPW negotiation, with up to three attempts possible. If the CAP is accepted, the contractor proceeds as general contractor during construction; if rejected, CPW may rebid the project to the public, excluding the original CM/GC firm from prime bidding. The integrated project team includes CPW Capital Development, HDR Inc. as design consultant, an independent cost estimator (upcoming procurement), and the State Engineer's Office as regulatory authority. Stakeholder coordination includes the GMUG National Forest and CPW's Southwest Region and various internal sections.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A#1 Prebid Sign In Sheet.pdf | ||
| A#1 RFP PMAA 2026_0020 Spring Creek CMGC.docx | DOCX document | |
| RFP PMAA 2026_0020 Spring Creek CMGC (1).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Laura Clellan, Director, Colorado Parks and Wildlife
Parks and Wildlife Commission: Richard Reading, Chair · James 'Jay' Tutchton, Vice-Chair · Eden Vardy, Secretary · Jessica Beaulieu · Frances Silva Blayney · Tai Jacober · Dallas May · Jack Murphy · Gabriel Otero
Capital Development 6060 Broadway • Denver, CO 80216
PH: (720) 456.0283
Spring Creek Dam Rehabilitation
CM/GC RFP 2026*0020
Date: 05.20.2026
Mandatory Site Visit
AGENDA:
Introductions
Site Safety
Integrated Project Team Introduction
CMGC 101
o What is it?
o Why did CPW select CM/GC delivery method for the project
Project Challenges o Estimated Pre-construction phase
Dam Overview o History
Project Overview o Project Goals and Challenges
Schedule
Questions
Introductions:
CPW (OWNER) REPRESENTATIVES:
CPW Local Staff
• Wildlife Technician – Jeremiah Rummel
• Area Wildlife Manage – Brandon Diamond
CPW Capital Development
Dam Safety Program Manager – Eric Eisinger, P.E.
Dam Safety Project Manager – Jenna Svoboda, P.E.
CPW Procurement
• CPW Contracts Manager – Joe Small
DNR Procurement
• DNR Purchasing Lead – Jeanette Stroud
Site Safety
Integrated Project Team
CPW Capital Development
• Project Manager – Eric Eisinger, P.E.
Design Consultant – HDR, Inc.
• Project Manager – Korey Kadrmas, P.E.
• Project Engineer – Adam Toothman, P.E.
CM/GC Services Firm – In Procurement
• TBD
Independent Cost Estimator (ICE) – Upcoming Procurement
• TBD
Regulatory Authority - State Engineer’s Office (SEO)
• Water Division 4 Dam Safety Engineer – Jason Ward, P.E.
Stakeholders include –
• Grand Mesa, Uncompahgre, & Gunnison (GMUG) National Forest
• CPW Southwest Region
• CPW Water Resources, Aquatics, and Terrestrial Sections
• Spring Creek Residents & businesses
CMGC 101
• What is it?: Contracting method that involves a contractor in both the design and construction phases o Partnership with Owner (CPW), Stakeholders, the Design Consultant (HDR, Inc), Independent Cost Estimator, and the Contractor - IPT
• Why did CPW select CM/GC delivery method for the project o To best handle Spring Creek Dam Rehab challenges (ie. remote and confined site, short construction season, impacts to residents & recreation) o Early contractor involvement to facilitate:
Safety of public and staff Fiscal responsibility Schedule optimization Constructability evaluation Continuous, progressive Value Engineering o Minimize risk and impacts to CPW and all stakeholders
• Value to Project (Project First) o CPW sees value in having a Well-Qualified Contractor sitting at the table with the Design Engineer, Independent Cost Estimator, and the Owner to:
Provide input on constructability, value engineering, materials, scheduling, and phasing Improves the construction schedule (through careful planning), o Streamline the design process and produces a project that adheres to the budget Have “open” discussion about costs and schedules (Open Cost Model).
o Provide input on Target Risk areas and minimize, eliminate or transfer risk to the appropriate entity, and maintain a Risk Register o Develop a strong relationship and focus on partnering with the entire project team, including external stakeholders, and maintaining a consistent team between preconstruction and construction phases.
• CPW Procurement o Pre-Construction Phase
The Contractor acts as an advisory or subject matter expert in the areas of construction, constructability, construction estimating, risk assessment/mitigation, and construction phasing in the design phase.
Separate contracts for the pre-construction and construction phases.
o Construction Phase
The Contractor, if a Construction Agreed Price (CAP) is accepted, then serves as the General Contractor during the construction phase.
If CAP proposal is not accepted, CPW may choose to release the project to public bidding for the Construction Phase. The CM/GC firm would not be allowed to bid the project as prime general contractor.
• Process for Project w/ CMGC o Design Consultant develops a design for project while collaborating with the Contractor, Independent Cost Estimator, and CPW (the IPT) o Contractor (with IPT collaboration) develops Risk Register, Open Cost Model, and tracks
Value Engineering Innovations (Starting 30%) o Independent Cost Estimator to independently develop all quantity and cost estimates;
then openly compare with contractor (Open Cost Model);
o After the 90% design completion milestone, the Contractor submits a CAP (Construction Agreed Price). CPW negotiates with the Contractor and either accepts or rejects the CAP.
There can be up to 3 total attempts at reaching the CAP.
Multiple CAP packages for phased construction or long lead time items are possible o Each CAP package must be a completed bid package that could be advertised. Well defined beginning and ending All construction bid packages must be severable and biddable.
• Contractor Services – Pre-Construction Phase o Attend regular project progress meetings, risk workshops, and review milestones (30, 60
& 90%) o Anticipated services (see added details in RFP):
Cost estimating Risk development and tracking Value engineering Constructability reviews Construction expertise o Examples of responsibilities (see added details in RFP):
Provide input on schedule, phasing, constructability, material availability, and cost Identify Project risk; provide OPCCs that help guide any changes to the design and establish Project risk pools Evaluate Project risk and develop a Risk Register and Risk Management Plan (in conjunction with CPW) Develop alternatives and innovations that improve the Project design, operations, schedule, and cost
• Summary of General Process for Spring Creek CMGC o RFP solicitation is released No contact with PM, written questions due to Jeanette Stroud o Mandatory Pre-Proposal Meeting o Submission of Proposals
Evaluation of proposals will be based on qualifications only (details in RFP.
o Shortlist selection for Interview phase
Interview Phase with approximately 3 shortlisted contractors Evaluation of shortlisted contractors based on qualifications AND cost
(details in RFP) Consists of short presentation, Team Challenge Component, and Q&A CM/GC Management Price Percentage is submitted and opened only after all qualifications (qualitative) scoring is complete and fixed.
o Selected contractor enters into pre-construction phase o Integrated Project Team kickoff meeting, includes Stakeholders o Pre-construction phase ends with final construction CAP o Construction Contract Starts – Target Construction Start in May/June 2027
Dam Overview:
• Operated and maintained by CPW under a Special Use Permit with the GMUG
• High Hazard Dam
• Zoned (?) embankment dam
• Concrete lined service spillway w/ an RCC emergency overflow spillway
• 24” RCP outlet pipe.
• Dam is currently un-instrumented o Will be conducting a geotechnical investigation in 2026 which would produce (+/-)2 permanent piezometers.
• Normal Water Surface Elevation: 9942
• Normal Storage: +/-1,000 ac-ft
Dam History:
Dam Safety Concerns:
Spillway Condition
Seepage
Project Description
• Primary Scope Items o Removal and replacement of spillway o Extensive filter blanket on the downstream face (combination - blanket drain, toe drain & filter diaphragm)
• Other Scope Items o Possible access road improvements (structural sections) for FSR 744 and 748 o Construction access o Riprap placement o Site Clearing grubbing / Cleanup & revegetation o Instrumentation
• Estimated Construction Cost 8-10Million
Project Goals
• Maintain public safety during and after construction
• Restore dam to safe operating condition at full storage
• Reinstate maximum life cycle of dam
• Minimize long-term maintenance and monitoring requirements
• Minimize disruption to CPW, recreational users, and Stakeholders o Logging in area will likely be occurring during construction
• Provide transparency and consideration to Project Stakeholders
• Minimize aquatic and terrestrial disruptions
• Complete an economical project that meets all dam safety and budgetary constraints.
Construction Challenges
• High elevation site at almost 10,000ft, short field and/or construction window
• Water shed has the potential to fill the reservoir from empty to spilling with outlet 100% open.
• Typical year, drivable access to the site opens around mid-May
• Runoff peaks around beginning-middle of June
• Snow/winter shutdown “typically” occurs around end of October to the beginning of November.
• Control of water could be difficult as there are natural springs in the area
• Narrow mountainous access roads that are heavily used for recreation during the spring/summer/fall.
• Relatively confined site
• Heavy recreational use: ATVs, motorcycles, mountain bikers, camping, fishing, rafting, etc.
• Limited areas for vehicle pull-off, turnaround & staging
• Will need to work with USFS for access and environmental requirements
Schedule:
1. Mandatory Pre-proposal On-Site Meeting
a. May 20, 2026; 1:00 PM (MDT)
2. Deadline for Written Requests for Clarifications (See Section 4.3)
a. May 25, 2026; 5:00 PM (MDT)
3. Responses Posted for Written Requests for Clarifications
a. May 29, 2026
4. Proposal Submission Deadline
a. June 10, 2026; 10:00 PM (MDT)
5. Public Proposal Opening
a. June 10, 2026; 12:00 PM (MDT)
6. Interview Shortlist Notification
a. July 6, 2026
7. Interviews with Shortlisted Proposers
a. July 9, 2026 - July 10, 2026
8. Notice of Award Recommendation
a. July 14, 2026
9. Contract Execution
a. Mid-August 2026
10. Preconstruction Phase (Phase 2)*
a. September 2026 through May 2027
11. Construction Phase (Phase 3)*
a. May/June 2027 through October 2028