This document is a detailed Statement of Work (SOW) for maintenance services on Ships Service Diesel Generators (SSDG) for the USNS Robert F. Kennedy (TAO 208). The maintenance requires an Original Equipment Manufacturer (OEM) authorized Rolls-Royce Bergen Diesel Engine representative to perform comprehensive technical services, including troubleshooting start-up faults, engine inspection, performance testing, and crew familiarization for two diesel engines (serial numbers 16501 & 16502) located in the Main Machinery Room. The work is part of a Navy Military Sealift Command contract, with a performance period from 11 September to 5 October 2025 in Norfolk, VA, involving specific maintenance tasks such as temporary disassembly, component inspection, repairs, and detailed reporting requirements.
Key technical requirements include using only OEM parts, conducting cylinder temperature and pressure recordings, completing a minimum four-hour performance test, and submitting comprehensive reports detailing engine conditions, measurements, and any defects discovered. The contractor must provide daily written reports to the vessel's Chief Engineer, use authorized field service representatives, and comply with specific quality assurance and safety protocols. All maintenance must adhere to the reference technical manual and meet IMO certification standards for critical shipboard safety items, with potential for contract modification if additional work is required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USNS Robert F. Kennedy
( TAO 208 )
| AUXILIARY MACHINERY |
| CONTRACT NO. N00000-00-X-0000 |
| ITEM NO. 0502 |
| CATEGORY "A" |
| 2025-08-21 |
| TAO205-CSI-SSDG ENGINE SERVICE |
| Cipolla, Michael, P |
ABSTRACT
This item describes the requirement to provide the technical services and industrial support to accomplish maintenance of SSDG diesel engines.
REFERENCE/ENCLOSURE
Reference Tech Manual T9311-CL-MMC-020, Generator, Diesel, Ship's Service, Model: TAO205-B3240L8/B1207_99/B0104117, Volume 2 Enclosure Diesel Engine Maintenance Start-up And Dormant Start-up Readiness Assessment
ITEM LOCATION/DESCRIPTION
Location/Quantity Locations Main Machinery Room (5-193-0), 3rd Platform FR 216
1.1.1 Quantity: Two (Port and Starboard)
Item Description/Manufacturer’s Data Manufacturer: Rolls-Royce Engine Type: Bergen Diesel Engine Model Number: B32:40L8A Serial Numbers: 16501 & 16502 Cylinders: 8 Rated Speed: 720 RPM
GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICE
Government Furnished Equipment (GFE): None Government Furnished Material (GFM) Lube oil as required Engine coolant additive as required Government Furnished Service (GFS): None Government Furnished Information (GFI): None
NOTES
The contractor and all subcontractors, regardless of tier must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs including but not limited to GTRs 1 through 7, 22, 23, 24, 28, and 29.
QUALITY ASSURANCE REQUIREMENTS
At least one member of ship's force will be assigned to assist with quality assurance efforts whenever diesel work is being accomplished.
Make known to all personal working on the engine that electrical and electronic controls and devices are present and may require necessary precautions and isolations that must be protected from damage during the overhaul period.
STATEMENT OF WORK REQUIRED
Tagout all required systems and equipment. Drain and dispose of any liquid in accordance with all federal, state and local regulations.
Only OEM authorized or qualified representatives will be permitted to temporarily remove, inspect, refurbish, and reinstall SSDG diesel components.
The lead Original Equipment Manufacturer (OEM) representative is to remain on-site from the beginning of work until completion of work with satisfactory dock trials. If there is a need to change the lead OEM representative during this scheduled maintenance action, the shipyard quality assurance department is to schedule a turnover meeting with the departing and arriving lead OEM representatives, shipyard quality assurance personnel and OMT REPs in attendance to ensure a proper turnover is accomplished.
Provide all tools and material required, including, but not limited to special tools, rags, degreaser, lubricant and loctite for accomplishment of all elements of this work item.
Only OEM parts are to be used in the accomplishment of work under this work item.
The shipyard quality assurance department is to schedule and provide a representative to attend a daily meeting onboard the vessel with MSC port engineers, ship's force representatives, shipyard personnel, and OEM representatives to review data collected and the work planned for the next 24-hour period.
Provide all labor, material, equipment and services required to perform maintenance using Reference 2.1.1 as guidance. Perform temporary disassembly of engines and accomplish the following;
SSDG 1:
Troubleshoot start-up faults Troubleshoot lube oil priming pump failure. Provide CFR of repair plan.
Provide crew familiarization and training
SSDG 2:
Troubleshoot start-up faults Provide crew familiarization and training All parts that are required to be IMO certified for IAPP shall be procured directly from the OEM to meet IMO requirements. These parts shall be noted and included in the “as released” condition report.
Provide labor and material to temporarily install valves, fittings, and hoses to assist ship's force in filling the engine with GFM lube oil identified in Paragraph 4.2.1 and shipyard provided deionized water.
NOTE: SHIP'S FORCE WILL TREAT ENGINE WATER WITH GFM ADDITIVE IDENTIFIED IN 4.2.2
Inspection/Test Prior to engine start-up the checklist in Enclosure 2.2.1 is to be completed. This evolution is to be accounted for in the scheduling of work under this item and related items.
Notify the OMT REP when the overhauled engine is ready to be tested under ship's electrical load for an approximate period of two hours. The Chief Engineer will be responsible for engaging the unit on the vessel’s main bus. Record cylinder operating temperatures, fluid operating temperatures and pressures during load test. Submit an “as found” condition report.
Complete a performance test on each serviced engine for a minimum of four hours. Record all operating temperatures, pressures and maximum firing pressures and submit to OMT REP.
1.2 Reports
1.2.1 Provide a daily written report to the vessel’s Chief Engineer detailing actions and progress.
When inspection, service and testing reveal any deficiency a condition report is to be submitted to the OMT REP with recommended repairs and parts required. Submit one electronic copy in Portable Document Format (PDF).
Provide the OMT REP with a report for each engine no more than seven days after the completion of all work. Provide one electronic copy in Portable Document Format (PDF). The report will contain the following, at minimum:
Engine operating hours and serial number.
Photographs of the engine condition at disassembly and any unusual conditions.
Description of any abnormal or unusual conditions found during maintenance Measurements taken and recorded and critical clearances and adjustments. "As-found", "As-released" and acceptable ranges for measurements are to be listed in the report.
Include comments on any defects found in arrangements for removals and lifting of engine components.
Include a listing of any additional special tools found to be needed for successful maintenance on engine.
Include a listing of all parts used during maintenance. Identify all parts rebuilt, renewed or exchanged. The parts list to include the Sub-Assembly drawing number and Bergen part number.
Include a listing of all parts included in the parts kits or ordered and not used as well as items turned over to Ship’s Force.
Engine to generator alignment readings.
Valve lash measurements with OEM acceptable limits.
All reports and checklists are to be completed and signed by the person who carried out the inspection and maintenance work and countersigned by the OEM representative.
Painting/Lagging Prepare, prime, paint and restore all new, soiled, and disturbed surfaces to match surrounding surfaces.
Renew lagging where damaged or disturbed.
Manufacturer’s Representative Provide the services of an OEM authorized field service representative to accomplish all work and testing on the ships service diesel generators identified in section 3.0 ensuring compliance with the manufacturer’s standards and performance specifications.
This work item requires maintenance and repair actions to be performed on a MSC ship critical safety item. Only original equipment manufacturer (OEM) authorized technical field service providers or MSC qualified non-OEM technical field service providers and OEM authorized or MSC qualified non-OEM parts shall be used to accomplish the requirements of this work item for this ship critical safety item including oversight and guidance on all aspects of equipment as-found condition inspection, removal, disassembly, reassembly, repairs, modifications, reinstallation, and testing as applicable. The technical service provider is to attend dock and sea trials.
Contractors interested in gaining MSC qualification as a non-OEM parts and/or service provider should visit this website for qualification and submittal requirements: https://www.msc.usff.navy.mil/Business-Opportunities/Contracts/Qualification-for-Items-Critical-to-Shipboard-Safety-on-MSC-Vessels/.
Possible Sources Provide the OMT REP with a signed letter of qualification from the Original Equipment Manufacturer and certificate of training for the field service representative for the equipment listed in section 3.0 prior to the start of any work.
Preparation of Drawings: None additional Period of Performance:
Period of performance (POP)is to be within the window of opportunity (WOO) 11 SEP – 05 OCT.
POP may be extended and ship location may change should additional work be required to address any CFR. Any change will be addressed via task order modification.
GENERAL REQUIREMENTS: None additional ENCLOSURE 2.2.1 DIESEL ENGINE MAINTENANCE START-UP AND DORMANT START-UP READINESS ASSESSMENT (ONE CHECKLIST PER DIESEL ENGINE)
USNS/USS ________________________ Hull No: _______ Diesel Engine Examined for Start-up: ____________________________________ Port / Shipyard: __________________________ Date: ________
72 Hours (notional) Prior to Dock Trial (Machinery Space Turnover)
| |_| | Verification received from Contractor / Tech Rep that all work is complete, and Engine is ready and safe to start. |
| |_| | Verify machinery space fire and smoke detection systems are fully operational. |
| |_| | Verify all Lockout / Tag out locks / tags are cleared IAW SMS 2.1-004-ALL “Lockout / Tag out.” |
| |_| | Verify that diesel exhaust systems are intact, and no fire hazards exist in the uptake spaces. |
| |_| | Verify all tanks are closed. |
| |_| | Verify all machinery space doors are operating correctly including any installed door closers. |
| |_| | Verify fixed, semi-portable and portable firefighting systems are fully certified and operational. |
| |_| | Verify Damage Control Locker and equipment are available. |
| |_| | Verify that all machinery space reach rods and remote pull stations are fully functional where fitted. |
| |_| | Verify all hoses, staging, covers, rigging, etc., temporarily installed in support of ship maintenance and repair, are removed from the machinery spaces. |
| |_| | Verify machinery space bilges are clean with no accumulations of liquids or debris. |
| |_| | Verify that machinery space supply and exhaust ventilation and fire dampers are functioning properly. |
| |_| | Verify that all installed engine hoses have been checked for wear and compliance with the COMSC 5-year replacement mandate. |
48 Hours (notional) Prior to Startup
| |_| | Check engine oil level in sump. |
| |_| | Check governor oil level. |
| |_| | Check cooling water level. |
| |_| | Check central freshwater treatment and level. |
| |_| | Check oil levels in reduction gear, lineshaft bearings and auxiliary sumps. |
| |_| | Verify fuel oil lines on engine are secure. |
| |_| | Transfer fuel oil from storage tanks to settler. |
| |_| | Check fuel oil service tanks for water or contamination. Conduct fuel oil analysis. |
| |_| | Check lube oil service tanks and sumps for water or contamination. Conduct lube oil analysis. |
| |_| | Verify all engine filters cleaned or renewed. |
ENCLOSURE 2.2.1 DIESEL ENGINE MAINTENANCE START-UP AND DORMANT START-UP READINESS ASSESSMENT (ONE CHECKLIST PER DIESEL ENGINE)
24 Hours (notional) Prior to Startup
| |_| | Remove stack covers. |
| |_| | Walk around the engine and check for leaks on and under the engine. |
| |_| | Verify 115V / 24VDC control voltage available. |
| |_| | Perform lamp test locally and at EOS console. |
| |_| | Run the lube oil and fuel oil purifiers on sumps and service tanks. |
| |_| | Run auxiliary systems; check pressures and temperatures. |
| |_| | Verify auto start of standby pumps. |
| |_| | Verify machinery space bilges are clean with no accumulations of liquids or debris. |
Pre-Start
| |_| | Check oil level in sump. |
| |_| | Check head tank levels. |
| |_| | Disengage barring gear. |
| |_| | Review USCG Periodic Safety Test Plan (PSTP) and verify that all engine related safety and alarm features are functioning properly. |
| |_| | Verify that saltwater cooling / freshwater cooling systems and heat exchangers are on-line and fully operational. |
| |_| | Verify that lube oil service pumps / lube oil service system is fully functional. |
| |_| | Verify that lube oil purifiers are operating properly. |
| |_| | Verify that fuel oil service pumps / fuel oil service system is fully functional. |
| |_| | Verify that fuel oil purifiers are operating properly. |
| |_| | Verify that compressed air / start air systems are fully functional. |
| |_| | Verify shafts and props are clear to spin. |
| |_| | Stop all fuel transfers. |
| |_| | Test sliding watertight doors. |
| |_| | Verify EDG is available and ready; test run off line. |
| |_| | Open all Engine cocks and roll the engine. |
| |_| | Check local emergency stop. |
| |_| | Check remote emergency stop. |
| |_| | Chief Engineer to notify Master and Port Engineer that start-up readiness assessment has been completed for all prime movers, and associated support systems and that machinery is ready / not ready for start-up. |
| |_| | Master to provide concurrence for start-up or not and conveys same to Type Desk and PM for information. |
Chief Engineer Port Engineer 0502 - 12