This document contains a projected submittal list for a pond liner engineering project at Valley City National Fish Hatchery. The project will replace the liners in fish pond 4 and asbestos-cement drain lines with a new drain line from existing kettles to the termination point.
The submittal list requires the contractor to provide a construction schedule, drainpipe materials, warranty, reinforced plastic pond liner and materials, miscellaneous materials, and certifications. Shop drawings must be submitted for the pond liners as well as physical liner samples, certificates of conformance, shipping and handling instructions, installation procedures, and delivery tickets. The submittals will be reviewed and marked as approved, approved with notes and no resubmission required, approved with notes and resubmission required, no action taken with resubmission required, or disapproved with resubmission required.
The related federal contract opportunity is solicitation number 140F0122R0073 to replace the pond liner at the Valley City National Fish Hatchery. The project will replace the liner in fish pond 4 and asbestos drain lines, accounting for existing pipes and a kettle. The Department of the Interior Fish and Wildlife Service is the contracting agency.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHEET 1 OF 1
PROJECT NAME: POND LINER ENGR. PROJECT NO.: 21-039
LOCATION: VALLEY CITY NFH CONTRACT NO.:
CONTRACTOR:
Spec.
Section
Number
Spec.
Paragraph
No. Comments
013200 1.4
221116 2.3.E
221116 2.10.A Linkseal
313215 3.5.C Compaction Test Results
321500.1 2.1 Gravel
334713 1.2.B Shop Drawings for Liners
334713 1.2.C Pond Liner Physical Samples
334713 1.2.D Certificate of Conformance
334713 1.2.E Shipping and Handling and Storage Instructions
334713 1.2.F Installation Procedures
334713 1.2.G Delivery Tickets
334713 1.2.H
334713 1.3
334713 2.2
334713 2.3
PROJECTED SUBMITTAL LIST
Description of item and submittal type (i.e. shop drawings, manufacture cut sheets, tests required, certifications, samples, operating and maintenance manuals, etc.)
Construction schedule
Drainpipe Materials
Warranty
RPP Liner and Materials
Miscellaneous Materials
Certification
A - Approved as Submitted.
B - Approved, Except as Noted. No Resubmission Required.
C - Approved, Except as Noted. Resubmission Required.
D - No Action Taken. See Comments. Resubmission Required.
E - disapproved. See Comments. Resubmission Required.