A06_Specs_CombinedSpecs_WattStreetHouse190.pdf
PDF 368 KB Posted
- Attached to
- BATHROOM RENOVATIONS - WATT STREET HOUSING, #190
- Solicitation number
- 140L3923Q0118
About this file
This solicitation package includes specifications for bathroom renovations at housing unit #190 located at the Bureau of Land Management's Watt Street facility in Battle Mountain, Nevada. The solicitation seeks bids from contractors to provide all necessary labor, materials, equipment, and supervision to complete bathroom fixture replacements including a new glass shower door, toilet, lavatory, and accessories. The specifications also cover ceramic tile installation, painting, and plumbing work. The deadline for bid submission is February 15, 2023, with an anticipated award date in early March.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
House #190 Bathroom Renovation
BUREAU OF LAND MANAGEMENT
BATTLE MOUNTAIN DISTRICT OFFICE
Battle Mountain, Nevada
GENERAL REQUIREMENTS 010000 - 1
SECTION 010000 – GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2
SUMMARY
A. This Section includes general requirements that are to apply to all Work throughout the Project. Requirements included in this Section are to apply to all other specification Sections.
B. Refer to Construction Agreement for other requirements by the General Contractor, Subcontractors, suppliers, etc.
1.3
DEFINITIONS
A. General: Basic Contract definitions are included in the Conditions of the Contract.
B. "Approved": When used to convey COR’s or CO's action on Contractor's submittals, applications, and requests, "approved" is limited to COR’s and CO’s duties and responsibilities as stated in the Conditions of the Contract.
C. “Center of...”: Indicates a specific single point at the exact center of the tile, panel, or other surface indicated.
D. “Contractor”: The General Contractor unless otherwise stated.
E. "Directed": A command or instruction by COR or CO. Other terms including "requested,"
"authorized," "selected," "approved," "required," and "permitted" have the same meaning as "directed."
F. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.
G. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as "indicated."
H. "Install": Operations at Project site including unloading, temporarily storing, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.
BATTLE MOUNTAIN DISTRICT OFFICE
GENERAL REQUIREMENTS 010000 - 2
I. “Project Manager”: The Contractor’s project manager.
J. “Project Representative”: The BLM’s project representatives (COR and CO).
K. "Project Site": Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built.
L. "Provide": Furnish and install, complete and ready for the intended use.
M. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.
N. “Related Sections”: Related Sections articles are included herein as a courtesy to assist in the locating of items in the specifications that the reader might expect to find in the Section but that are specified elsewhere. The list of sections may or may not be complete.
‘Related Sections’ articles do not relieve the Contractor of the contractual obligation to perform to all the Contract Documents or to coordinate who does what amongst the team of subcontractors.
1.4 SITE INSPECTION
A. Examine the premises and site and compare them with the drawings and specifications.
B. Become familiar with existing conditions such as obstructive areas, excavating or filling, and any problems related to construction. No allowances will subsequently be made by reason of failure to examine the site.
1.5 SCOPE OF THE WORK
A. Unless otherwise provided, all materials, labor, equipment, tools, transportation, and utilities necessary for the successful completion of the Project shall be provided at the expense of the Contractor.
B. Requirements of the Work are contained in the Contract Documents, and include cross-references herein to published information, which is not necessarily bound therewith.
C. Provide, as part of the Bid and without additional charge, all incidental items required for completion of the Work, even if not specifically indicated.
1. Install all Work so that its several component parts function together as a complete and workable system, and with all equipment properly adjusted and in working order.
BATTLE MOUNTAIN DISTRICT OFFICE
GENERAL REQUIREMENTS 010000 - 3
D. Conform to highest quality standards for materials and workmanship to execute Work that is indicated or specified and that is necessary to fully satisfy the Contract Document requirements for a complete, finished, acceptable installation regardless of whether indicated or specified or not.
E. Responsibilities of the Contractor includes the responsibility to verify all field measurements of actual building conditions so that all Work fits properly in the locations indicated and specified. Protect existing structures, improvements, trees, and other items from physical damage, unless identified to be removed.
F. Any existing surfaces, furniture or equipment that are damaged by the Contractor are to be restored to their original condition, or better, to the satisfaction of the Owner.
G. Contractor is to restore any roads, utilities, walks, curbs, gutters or other existing conditions that are used for construction and are damaged, to the same condition as they existed prior to commencement of construction. Where existing conditions are damaged, they shall be replaced by new Work to match existing adjacent Work, or repaired, if acceptable to Project Representative, at no cost to BLM.
1.6 WORKERS
A. The Contractor is to enforce strict discipline and good order among his/her employees at all times and shall not employ on the Project any unfit person or anyone not skilled in the Work assigned to him/her.
B. Consumption of alcohol, smoking or any other controlled, non-medically prescribed substance will not be allowed on the Project.
C. Contractor shall rectify behavior unacceptable to the BLM or BLM’s Project Representative by strict enforcement of discipline. BLM reserves the right to request dismissal of individual workers for failure to comply with standards of behavior communicated to the Contractor.
1.7 MANUFACTURER’S DIRECTIONS
A. Manufactured articles, materials, or equipment shall be applied, installed, connected, erected, used, cleaned, and conditioned in accordance with the Manufacturer’s printed directions unless otherwise indicated in the Contract Documents.
1.8 FASTENERS
A. Unless noted otherwise, the trade requiring the fastening of its Work to any substrate or support is responsible for provision and installation of requisite fasteners.
1.9 PENETRATIONS
A. The sealing of all penetrations in fire-rated, acoustically-rated or structural partitions and separations is the responsibility of the trade making or requiring the penetration.
BATTLE MOUNTAIN DISTRICT OFFICE
GENERAL REQUIREMENTS 010000 - 4
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01100
House # 190 Bathroom Renovation
BATTLE MOUNTAIN DISTRICT OFFICE
Battle Mountain, NEVADA
JOINT SEALANTS 079200 - 1
SECTION 079200 - JOINT SEALANTS
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Silicone joint sealants.
2. Urethane joint sealants.
3. Mildew-resistant joint sealants.
4. Latex joint sealants.
B. Related Requirements:
1. Section 092900 "Gypsum Board" for sealing perimeter joints.
2. Section 093013 “Ceramic Tiling”.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.4 ACTION SUBMITTALS
A. Product Data: For each joint-sealant product.
B. Samples for Initial Selection: Manufacturer's color charts consisting of strips of cured sealants showing the full range of colors available for each product exposed to view.
C. Samples for Verification: For each kind and color of joint sealant required, provide
Samples with joint sealants in 1/2-inch-wide joints formed between two 6-inch-long strips of material matching the appearance of exposed surfaces adjacent to joint sealants.
D. Joint-Sealant Schedule: Include the following information:
1. Joint-sealant application, joint location, and designation.
2. Joint-sealant manufacturer and product name.
BATTLE MOUNTAIN DISTRICT OFFICE
JOINT SEALANTS 079200 - 2
3. Joint-sealant formulation.
4. Joint-sealant color.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: When requested, for qualified testing agency.
B. Product Test Reports: When requested, for each kind of joint sealant, for tests performed by a qualified testing agency.
C. Preconstruction Laboratory Test Schedule: When requested, include the following information for each joint sealant and substrate material to be tested:
1. Joint-sealant location and designation.
2. Manufacturer and product name.
3. Type of substrate material.
4. Proposed test.
5. Number of samples required.
D. Preconstruction Laboratory Test Reports: When Requested, from sealant manufacturer, indicating the following:
1. Materials forming joint substrates and joint-sealant backings have been tested for compatibility and adhesion with joint sealants.
2. Interpretation of test results and written recommendations for primers and substrate preparation are needed for adhesion.
E. Preconstruction Field-Adhesion-Test Reports: When requested, indicate which sealants and joint preparation methods resulted in optimum adhesion to joint substrates based on testing specified in "Preconstruction Testing" Article.
F. Field-Adhesion-Test Reports: When requested, for each sealant application tested.
G. Sample Warranties: For special warranties.
1.6 QUALITY ASSURANCE
A. Installer Qualifications: When applicable/requested, an authorized representative who is trained and approved by manufacturer.
B. Product Testing: When applicable/requested, test joint sealants using a qualified testing agency.
1. Testing Agency Qualifications: Qualified according to ASTM C1021 to conduct the testing indicated.
C. Mockups: When requested, install sealant in mockups of assemblies specified in other
Sections that are indicated to receive joint sealants specified in this Section. Use materials and installation methods specified in this Section.
BATTLE MOUNTAIN DISTRICT OFFICE
JOINT SEALANTS 079200 - 3
1.7 PRECONSTRUCTION TESTING
A. Preconstruction Laboratory Testing: When applicable/requested, submit to joint-sealant manufacturers, for testing indicated below, samples of materials that will contact or affect joint sealants.
1. Adhesion Testing: Use ASTM C794 to determine whether priming and other specific joint preparation techniques are required to obtain rapid, optimum adhesion of joint sealants to joint substrates.
2. Compatibility Testing: Use ASTM C1087 to determine sealant compatibility when in contact with glazing and gasket materials.
3. Stain Testing: Use ASTM C1248 to determine stain potential of sealant when in contact with masonry substrates.
4. Submit manufacturer's recommended number of pieces of each type of material, including joint substrates, joint-sealant backings, and miscellaneous materials.
5. Schedule sufficient time for testing and analyzing results to prevent delaying the Work.
6. For materials failing tests, obtain joint-sealant manufacturer's written instructions for corrective measures, including use of specially formulated primers.
7. Testing will not be required if joint-sealant manufacturers submit data that are based on previous testing, not older than 24 months, of sealant products for adhesion to, staining of, and compatibility with joint substrates and other materials matching those submitted.
B. Preconstruction Field-Adhesion Testing: When applicable/requested, before installing sealants, field test their adhesion to Project joint substrates as follows:
1. Locate test joints where indicated on Project or, if not indicated, as directed by
COR.
2. Conduct field tests for each kind of sealant and joint substrate.
3. Notify COR seven days in advance of dates and times when test joints will be erected.
4. Arrange for tests to take place with joint-sealant manufacturer's technical representative present.
a. Test Method: Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1.1 in ASTM C1193 or Method A, Tail Procedure, in ASTM C1521.
1) For joints with dissimilar substrates, verify adhesion to each substrate separately; extend cut along one side, verifying adhesion to opposite side. Repeat procedure for opposite side.
5. Report whether sealant failed to adhere to joint substrates or tore cohesively.
Include data on pull distance used to test each kind of product and joint substrate.
For sealants that fail adhesively, retest until satisfactory adhesion is obtained.
6. Evaluation of Preconstruction Field-Adhesion-Test Results: Sealants not evidencing adhesive failure from testing, in absence of other indications of noncompliance
BATTLE MOUNTAIN DISTRICT OFFICE
JOINT SEALANTS 079200 - 4
with requirements, will be considered satisfactory. Do not use sealants that fail to adhere to joint substrates during testing.
1.8 FIELD CONDITIONS
A. Do not proceed with installation of joint sealants under the following conditions:
1. When ambient and substrate temperature conditions are outside limits permitted by joint-sealant manufacturer or are below 40 deg F.
2. When joint substrates are wet.
3. Where joint widths are less than those allowed by joint-sealant manufacturer for applications indicated.
4. Where contaminants capable of interfering with adhesion have not yet been removed from joint substrates.
1.9 WARRANTY
A. Special Installer's Warranty: Installer agrees to repair or replace joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.
1. Warranty Period: Two years from date of Substantial Completion.
B. Special Manufacturer's Warranty: Manufacturer agrees to furnish joint sealants to repair or replace those joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.
1. Warranty Period: Five years from date of Substantial Completion.
C. Special warranties specified in this article exclude deterioration or failure of joint sealants from the following:
1. Movement of the structure caused by stresses on the sealant exceeding sealant manufacturer's written specifications for sealant elongation and compression.
2. Disintegration of joint substrates from causes exceeding design specifications.
3. Mechanical damage caused by individuals, tools, or other outside agents.
4. Changes in sealant appearance caused by accumulation of dirt or other atmospheric contaminants.
PART 2 - PRODUCTS
2.1 JOINT SEALANTS, GENERAL
A. Compatibility: Provide joint sealants, backings, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by joint-sealant manufacturer, based on testing and field experience.
BATTLE MOUNTAIN DISTRICT OFFICE
JOINT SEALANTS 079200 - 5
B. Colors of Exposed Joint Sealants: As selected by COR from manufacturer's full range.
2.2 SILICONE JOINT SEALANTS
A. Silicone, S, NS, 25, T, NT: Single-component, nonsag, plus 25 percent and minus 25 percent movement capability, traffic- and nontraffic-use, neutral-curing silicone joint sealant;
ASTM C920, Type S, Grade NS, Class 25, Uses T and NT.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following (or approved equal in strength, quality, and durability):
a. May National Associates, Inc.; a subsidiary of Sika Corporation.
b. Pecora Corporation.
c. Sika Corporation; Joint Sealants.
2.3 URETHANE JOINT SEALANTS
A. Urethane, S, NS, 25, NT: Single-component, nonsag, nontraffic-use, plus 25 percent and minus 25 percent movement capability, urethane joint sealant; ASTM C920, Type S, Grade NS, Class 25, Use NT.
a. BASF Corporation.
b. Bostik, Inc.
c. Pecora Corporation.
d. Sherwin-Williams Company (The).
e. Sika Corporation; Joint Sealants.
f. Tremco Incorporated.
B. Urethane, S, P, 25, T, NT: Single-component, pourable, plus 25 percent and minus 25 percent movement capability, traffic- and nontraffic-use, urethane joint sealant; ASTM C920, Type S, Grade P, Class 25, Uses T and NT.
a. BASF Corporation.
c. Polymeric Systems, Inc.
d. Sherwin-Williams Company (The).
2.4 MILDEW-RESISTANT JOINT SEALANTS
A. Mildew-Resistant Joint Sealants: Formulated for prolonged exposure to humidity with fungicide to prevent mold and mildew growth.
http://www.specagent.com/Lookup?ulid=9406 http://www.specagent.com/Lookup?uid=123457013393 http://www.specagent.com/Lookup?uid=123457079798 http://www.specagent.com/Lookup?uid=123457057842 http://www.specagent.com/Lookup?ulid=9414 http://www.specagent.com/Lookup?uid=123457013416 http://www.specagent.com/Lookup?uid=123457013417 http://www.specagent.com/Lookup?uid=123457013418 http://www.specagent.com/Lookup?uid=123457013421 http://www.specagent.com/Lookup?uid=123457058203 http://www.specagent.com/Lookup?uid=123457013423 http://www.specagent.com/Lookup?ulid=9418 http://www.specagent.com/Lookup?uid=123457013430 http://www.specagent.com/Lookup?uid=123457013431 http://www.specagent.com/Lookup?uid=123457013432 http://www.specagent.com/Lookup?uid=123457013434
BATTLE MOUNTAIN DISTRICT OFFICE
JOINT SEALANTS 079200 - 6
B. Silicone, Mildew Resistant, Acid Curing, S, NS, 25, NT: Mildew-resistant, single- component, nonsag, plus 25 percent and minus 25 percent movement capability, nontraffic-use, acid-curing silicone joint sealant; ASTM C920, Type S, Grade NS, Class 25, Use NT.
a. GE Construction Sealants; Momentive Performance Materials Inc.
c. The Dow Chemical Company.
d. Tremco Incorporated.
2.5 LATEX JOINT SEALANTS
A. Acrylic Latex: Acrylic latex or siliconized acrylic latex, ASTM C834, Type OP, Grade NF.
a. May National Associates, Inc.; a subsidiary of Sika Corporation.
c. Sherwin-Williams Company (The).
d. Tremco Incorporated.
2.6 JOINT-SEALANT BACKING
A. Sealant Backing Material, General: Nonstaining; compatible with joint substrates, sealants, primers, and other joint fillers; and approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.
a. Adfast.
b. Alcot Plastics Ltd.
c. BASF Corporation.
d. Construction Foam Products; a division of Nomaco, Inc.
B. Cylindrical Sealant Backings: ASTM C1330, Type C (closed-cell material with a surface skin), Type B (bicellular material with a surface skin) or any of the preceding types, as approved in writing by joint-sealant manufacturer for joint application indicated, and of size and density to control sealant depth and otherwise contribute to producing optimum sealant performance.
C. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer for preventing sealant from adhering to rigid, inflexible joint-filler materials or joint surfaces at back of joint. Provide self-adhesive tape where applicable.
http://www.specagent.com/Lookup?ulid=9448 http://www.specagent.com/Lookup?uid=123457013476 http://www.specagent.com/Lookup?uid=123457099583 http://www.specagent.com/Lookup?uid=123457013475 http://www.specagent.com/Lookup?uid=123457013479 http://www.specagent.com/Lookup?ulid=9454 http://www.specagent.com/Lookup?uid=123457013357 http://www.specagent.com/Lookup?uid=123457013358 http://www.specagent.com/Lookup?uid=123457013359 http://www.specagent.com/Lookup?uid=123457013360 http://www.specagent.com/Lookup?ulid=9455 http://www.specagent.com/Lookup?uid=123457104788 http://www.specagent.com/Lookup?uid=123457064684 http://www.specagent.com/Lookup?uid=123457013490 http://www.specagent.com/Lookup?uid=123457013491
BATTLE MOUNTAIN DISTRICT OFFICE
JOINT SEALANTS 079200 - 7
2.7 MISCELLANEOUS MATERIALS
A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.
B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials, free of oily residues or other substances capable of staining or harming joint substrates and adjacent nonporous surfaces in any way, and formulated to promote optimum adhesion of sealants to joint substrates.
C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with requirements for joint configuration, installation tolerances, and other conditions affecting performance of the Work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions and the following requirements:
1. Remove all foreign material from joint substrates that could interfere with adhesion of joint sealant, including dust, paints (except for permanent, protective coatings tested and approved for sealant adhesion and compatibility by sealant manufacturer), old joint sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.
2. Clean porous joint substrate surfaces by brushing, grinding, mechanical abrading, or a combination of these methods to produce a clean, sound substrate capable of developing optimum bond with joint sealants. Remove loose particles remaining after cleaning operations above by vacuuming or blowing out joints with oil-free compressed air. Porous joint substrates include the following:
a. Unglazed surfaces of ceramic tile.
3. Clean nonporous joint substrate surfaces with chemical cleaners or other means that do not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants. Nonporous joint substrates include the following:
a. Metal.
BATTLE MOUNTAIN DISTRICT OFFICE
JOINT SEALANTS 079200 - 8
b. Glass.
c. Porcelain enamel.
d. Glazed surfaces of ceramic tile.
B. Joint Priming: Prime joint substrates where recommended by joint-sealant manufacturer or as indicated by preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.
C. Masking Tape: Use masking tape where required to prevent contact of sealant or primer with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.
3.3 INSTALLATION OF JOINT SEALANTS
A. General: Comply with joint-sealant manufacturer's written installation instructions for products and applications indicated, unless more stringent requirements apply.
B. Sealant Installation Standard: Comply with recommendations in ASTM C1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.
C. Install sealant backings (where applicable) of kind indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.
1. Do not leave gaps between ends of sealant backings.
2. Do not stretch, twist, puncture, or tear sealant backings.
3. Remove absorbent sealant backings that have become wet before sealant application and replace them with dry materials.
D. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and backs of joints.
E. Install sealants using proven techniques that comply with the following and at the same time backings are installed:
1. Place sealants so they directly contact and fully wet joint substrates.
2. Completely fill recesses in each joint configuration.
3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow optimum sealant movement capability.
F. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified in subparagraphs
BATTLE MOUNTAIN DISTRICT OFFICE
JOINT SEALANTS 079200 - 9
below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.
1. Remove excess sealant from surfaces adjacent to joints.
2. Use tooling agents that are approved in writing by sealant manufacturer and that do not discolor sealants or adjacent surfaces.
3. Provide concave joint profile per Figure 8A in ASTM C1193 unless otherwise indicated.
4. Provide flush joint profile at waterfall edges of solid surfacing according to Figure 8B in ASTM C1193.
5. Provide recessed joint configuration of recess depth and at aluminum storefront systems according to Figure 8C in ASTM C1193.
a. Use masking tape to protect surfaces adjacent to recessed tooled joints.
3.4 CLEANING
A. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.
3.5 PROTECTION
A. Protect joint sealants during and after curing period from contact with contaminating substances and from damage resulting from construction operations or other causes so sealants are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out, remove, and repair damaged or deteriorated joint sealants immediately so installations with repaired areas are indistinguishable from original work.
3.6 JOINT-SEALANT SCHEDULE
A. Joint-Sealant Application: Interior joints in horizontal traffic surfaces.
1. Joint Locations:
a. Isolation joints in cast-in-place concrete slabs.
b. Control and expansion joints in tile flooring.
c. Other joints as indicated on Drawings.
2. Joint Sealant: Urethane, S, P, 25, T, NT.
3. Joint-Sealant Color: As selected by COR from manufacturer's full range of colors.
B. Joint-Sealant Application: Interior joints in vertical surfaces and horizontal nontraffic surfaces.
BATTLE MOUNTAIN DISTRICT OFFICE
JOINT SEALANTS 079200 - 10
a. Control and expansion joints on exposed interior surfaces of exterior walls.
b. Tile control and expansion joints.
c. Vertical joints on exposed surfaces of unit masonry walls and partitions.
d. Other joints as indicated on Drawings.
2. Joint Sealant: Urethane, S, NS, 25, NT.
3. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.
C. Joint-Sealant Application: Interior joints in vertical surfaces and horizontal nontraffic surfaces not subject to significant movement.
a. Control joints on exposed interior surfaces of exterior walls.
b. Perimeter joints between interior wall surfaces and frames of interior doors.
2. Joint Sealant: Acrylic latex.
3. Joint-Sealant Color: As selected by COR from manufacturer's full range of colors.
D. Joint-Sealant Application: Mildew-resistant interior joints in vertical surfaces and horizontal nontraffic surfaces.
a. Joints between plumbing fixtures and adjoining walls, floors, and counters.
b. Tile control and expansion joints where indicated.
2. Joint Sealant: Silicone, mildew resistant, acid curing, S, NS, 25, NT.
3. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.
END OF SECTION 079200
BATTLE MOUNTAIN DISTRICT OFFICE
INTERIOR PAINTING 099123 - 1
SECTION 099123 - INTERIOR PAINTING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes surface preparation and the application of paint systems on interior substrates.
B. Related Requirements:
1. Section 081113 “Hollow Metal Doors and Frames”
2. Section 092900 “Gypsum Board” surface preparation.
1.3 DEFINITIONS
A. MPI Gloss Level 1: Not more than five units at 60 degrees and 10 units at 85 degrees, according to ASTM D523.
B. MPI Gloss Level 2: Not more than 10 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D523.
C. MPI Gloss Level 3: 10 to 25 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D523.
D. MPI Gloss Level 4: 20 to 35 units at 60 degrees and not less than 35 units at 85 degrees, according to ASTM D523.
E. MPI Gloss Level 5: 35 to 70 units at 60 degrees, according to ASTM D523.
F. MPI Gloss Level 6: 70 to 85 units at 60 degrees, according to ASTM D523.
G. MPI Gloss Level 7: More than 85 units at 60 degrees, according to ASTM D523.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product. Include preparation requirements and application instructions.
1. Include Printout of current "MPI Approved Products List" for each product category specified, with the proposed product highlighted.
INTERIOR PAINTING 099123 - 2
2. Indicate VOC content.
B. Samples for Initial Selection: For each type of topcoat product.
C. Samples for Verification: For each type of paint system and in each color and gloss of topcoat.
1. Submit Samples on rigid backing, 8 inches square.
2. Apply coats on Samples in steps to show each coat required for system.
3. Label each coat of each Sample.
4. Label each Sample for location and application area.
D. Product List: Cross-reference to paint system and locations of application areas. Use same designations indicated on Drawings and in schedules. Include color designations.
1.5 MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials, from the same product run, that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.
1. Paint: 5 percent, but not less than 1 gal. of each material and color applied.
1.6 QUALITY ASSURANCE
A. Mockups if requested by COR: Apply mockups of each paint system indicated and each color and finish selected to verify preliminary selections made under Sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution.
1. COR will select one surface to represent surfaces and conditions for application of each paint system.
a. Vertical and Horizontal Surfaces: Provide samples of at least 100 sq. ft..
b. Other Items: COR will designate items or areas required.
2. Final approval of color selections will be based on mockups.
a. If preliminary color selections are not approved, apply additional mockups of additional colors selected by Architect at no added cost to Owner.
3. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless COR specifically approves such deviations in writing.
4. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.
INTERIOR PAINTING 099123 - 3
1.7 DELIVERY, STORAGE, AND HANDLING
A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45 deg F.
1. Maintain containers in clean condition, free of foreign materials and residue.
2. Remove rags and waste from storage areas daily.
1.8 FIELD CONDITIONS
A. Apply paints only when temperature of surfaces to be painted and ambient air temperatures are between 50 and 95 deg F.
B. Do not apply paints when relative humidity exceeds 85 percent; at temperatures less than 5 deg F above the dew point; or to damp or wet surfaces.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements, provide products by one of the following or approved equal in quality and durability:
1. Benjamin Moore & Co.
2. PPG Paints.
3. Sherwin-Williams Company (The).
B. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include but are not limited to products listed in the Interior Painting Schedule for the paint category indicated.
2.2 PAINT, GENERAL
A. MPI Standards: Products shall comply with MPI standards indicated and shall be listed in its "MPI Approved Products Lists."
B. Material Compatibility:
1. Materials for use within each paint system shall be compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.
2. For each coat in a paint system, products shall be recommended in writing by topcoat manufacturers for use in paint system and on substrate indicated.
C. Colors: As selected by COR from manufacturer's full range.
http://www.specagent.com/Lookup?ulid=11642 http://www.specagent.com/Lookup?uid=123457105283 http://www.specagent.com/Lookup?uid=123457105297 http://www.specagent.com/Lookup?uid=123457105301
INTERIOR PAINTING 099123 - 4
2.3 SOURCE QUALITY CONTROL
A. Testing of Paint Materials: BLM reserves the right to invoke the following procedure:
1. BLM will engage the services of a qualified testing agency (or a qualified laboratory) to sample paint materials. Contractor will be notified in advance and may be present when samples are taken. If paint materials have already been delivered to Project site, samples may be taken at Project site. Samples will be identified, sealed, and certified by testing agency (or a qualified laboratory).
2. Testing agency (or a qualified laboratory) will perform tests for compliance with product requirements.
3. BLM may direct Contractor to stop applying paints if test results show materials being used do not comply with product requirements. Contractor shall remove noncomplying paint materials from Project site, pay for testing, and repaint surfaces painted with rejected materials. Contractor will be required to remove rejected materials from previously painted surfaces if, on repainting with complying materials, the two paints are incompatible.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.
B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:
1. Wood: 15 percent.
2. Gypsum Board: 12 percent.
C. Gypsum Board Substrates: Verify that finishing compound is sanded smooth.
D. Spray-Textured Ceiling/Wall Substrates: Verify that surfaces are dry.
E. Verify suitability of substrates, including surface conditions and compatibility, with existing finishes and primers.
F. Proceed with coating application only after unsatisfactory conditions have been corrected.
1. Application of coating indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Comply with manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual" applicable to substrates and paint systems indicated.
INTERIOR PAINTING 099123 - 5
B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.
1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection if any.
C. Clean substrates of substances that could impair bond of paints, including dust, dirt, oi l, grease, and incompatible paints and encapsulants.
1. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce paint systems indicated.
D. Wood Substrates:
1. Scrape and clean knots and apply coat of knot sealer before applying primer.
2. Sand surfaces that will be exposed to view and dust off.
3. Prime edges, ends, faces, undersides, and backsides of wood.
4. After priming, fill holes and imperfections in the finish surfaces with putty or plastic wood filler. Sand smooth when dried.
E. Cotton or Canvas Insulation Covering Substrates: Remove dust, dirt, and other foreign material that might impair bond of paints to substrates.
3.3 APPLICATION
A. Apply paints according to manufacturer's written instructions and to recommendations in "MPI Manual."
1. Use applicators and techniques suited for paint and substrate indicated.
2. Paint surfaces behind movable equipment and furniture same as similar exposed surfaces. Before final installation, paint surfaces behind permanently fixed equipment or furniture with prime coat only.
3. Paint front and backsides of access panels, removable or hinged covers, and similar hinged items to match exposed surfaces.
4. Do not paint over labels of independent testing agencies or equipment name, identification, performance rating, or nomenclature plates.
5. Primers specified in painting schedules may be omitted on items that are factory primed or factory finished if acceptable to topcoat manufacturers.
B. Tint each undercoat a lighter shade to facilitate identification of each coat i f multiple coats of same material are to be applied. Tint undercoats to match color of topcoat but provide sufficient difference in shade of undercoats to distinguish each separate coat.
C. If undercoats or other conditions show through topcoat, apply additional coats until cured film has a uniform paint finish, color, and appearance.
INTERIOR PAINTING 099123 - 6
D. Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks, roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color breaks.
3.4 FIELD QUALITY CONTROL
A. Dry Film Thickness Testing: BLM may engage the services of a qualified testing and inspecting agency (or a qualified Laboratory) to inspect and test paint for dry film thickness.
1. Contractor shall touch up and restore painted surfaces damaged by testing.
2. If test results show that dry film thickness of applied paint does not comply with paint manufacturer's written recommendations, Contractor shall pay for testing and apply additional coats as needed to provide dry film thickness that complies with paint manufacturer's written recommendations.
3.5 CLEANING AND PROTECTION
A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from Project site.
B. After completing paint application, clean spattered surfaces. Remove spattered paints by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces.
C. Protect work of other trades against damage from paint application. Correct damage to work of other trades by cleaning, repairing, replacing, and refinishing, as approved by COR, and leave in an undamaged condition.
D. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces.
3.6 INTERIOR PAINTING SCHEDULE
A. Gypsum Board Substrates:
1. Latex over Latex Sealer System MPI INT 9.2A:
a. Prime Coat: Primer sealer, latex, interior, MPI #50.
1) Benjamin Moore: Ultra Spec 500; Waterborne Interior Primer Sealer.
2) PPG Architectural: Speedhide Zero Interior Zero VOC Latex Sealer.
3) Sherwin Williams: ProMar 200 Zero; Interior Latex Primer.
4) Or approved equal in quality and durability.
b. Prime Coat: Latex, interior, matching topcoat.
c. Intermediate Coat: Latex, interior, matching topcoat.
d. Topcoat: Latex, interior (MPI Gloss Level 2), MPI #44.
INTERIOR PAINTING 099123 - 7
1) Benjamin Moore: Ultra Spec 500; Interior Low Sheen Finish.
2) PPG Architectural: Speedhide Zero Interior Zero VOC Latex Eggshell.
3) Sherwin Williams: ProMar 200 Zero VOC; Interior Latex Low Sheen.
4) Or approved equal in quality and durability.
e. Topcoat: Latex, interior (MPI Gloss Level 3), MPI #52.
1) Benjamin Moore: Ultra Spec 500; Waterborne Interior Eggshell.
2) PPG Architectural: Speedhide Zero Interior Zero VOC Latex Satin.
3) Sherwin Williams: ProMar 200 Zero VOC; Interior Latex Eg-Shel.
4) Or approved equal in quality and durability.
f. Topcoat: Latex, interior, semi-gloss (MPI Gloss Level 5), MPI #54.
1) Benjamin Moore: Ultra Spec 500; Waterborne Interior Gloss.
2) PPG Architectural: Ultra-Hide 250 Interior Semi-Gloss Paint.
3) Sherwin Williams: ProMar 200 Zero VOC; Interior Latex Gloss.
4) Or approved equal in quality and durability.
g. Topcoat: Latex, interior (MPI Gloss Level 3), MPI #155. (Ceilings and Exposed Structure)
1) Benjamin Moore: Dry Fall; Latex Dry Fall Eggshell.
2) PPG Architectural: Speedhide Super Tech WB Int. Eggshell 100%
Acrylic Dry-Fog.
3) Sherwin Williams: Dryfall; Waterborne Acrylic Dryfall Eg-Shel.
4) Or approved equal in quality and durability.
2. Epoxy High Build Latex System MPI INT 9.2N:
a. Prime Coat: Primer sealer, latex, interior, MPI #50.
1) Benjamin Moore: Ultra Spec 500; Waterborne Interior Primer Sealer.
2) PPG Architectural: Speedhide Zero Interior Zero VOC Latex Sealer.
3) Sherwin Williams: ProMar 200 Zero; Interior Latex Primer.
4) Or approved equal in quality and durability.
b. Intermediate Coat: Latex, interior, high performance architectural, matching topcoat.
c. Topcoat: Latex, interior, high performance architectural (MPI Gloss Level 4), MPI #108.
1) Benjamin Moore: Corotech; Polyamide Epoxy Semi-Gloss.
2) PPG Architectural: Protective and Marine Coatings; Aquapon High
Build Epoxy.
3) Sherwin Williams: Protective & Marine; Macropoxy 646 Fast Cure
Epoxy.
4) Or approved equal in quality and durability.
INTERIOR PAINTING 099123 - 8
END OF SECTION 099123
THIS PAGE INTENTIONALLY LEFT BLANK
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 1
TOILET, AND BATH
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Private-Use bathroom accessories.
2. Underlavatory guards.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes.
2. Include anchoring and mounting requirements, including requirements for cutouts in other work and substrate preparation.
3. Include electrical characteristics.
B. Samples: For each exposed product and for each finish specified, full size.
1. Approved full-size Samples will be returned and may be used in the Work.
C. Product Schedule: Indicating types, quantities, sizes, and installation locations of each accessory required.
1. Identify locations.
2. Identify accessories.
1.4 INFORMATIONAL SUBMITTALS
A. Sample Warranty: For manufacturer's special warranties.
1.5 CLOSEOUT SUBMITTALS
A. Maintenance Data: For accessories to include in maintenance manuals.
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 2
1.6 WARRANTY
A. Manufacturer's Special Warranty for Mirrors: Manufacturer agrees to repair or replace mirrors that fail in materials or workmanship within specified warranty period.
1. Failures include, but are not limited to, visible silver spoilage defects.
2. Warranty Period: 2 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 PRIVATE-USE BATHROOM ACCESSORIES
A. Source Limitations: Obtain living unit bathroom accessories from single source from single manufacturer.
B. Basis-of-Design Product: Subject to compliance with requirements, provide Franklin Brass by Liberty Hardware Manufacturing Corporation; a Masco company; or a comparable product by one of the following:
1. American Specialties, Inc.
2. Basco, Inc.
3. Bobrick Washroom Equipment, Inc.
4. Bradley Corporation.
5. Ginger by Brasstech, Inc.; a Masco company.
6. Material and Finish: Stainless steel, ASTM A480/A480M No. 4 finish (satin).
C. Toilet Tissue Dispenser:
1. Basis-of-Design Product: D2408SN – Franklin Brass.
2. Description: Single-roll dispenser.
3. Mounting: Surface mounted.
4. Capacity: Designed for 4-1/2 or 5-inch diameter tissue rolls.
5. Material and Finish: Brushed chrome-plated zinc alloy (zamac).
D. Glass Shower Door Frameless sliding shower door with premium 3/8-inch glass
1. Frameless sliding shower door with premium 3/8 in glass.
2. Slim top track with semi-hidden rollers and soft-close system.
3. Fully frameless, premium 3/8-inch ANSI certified tempered safety glass panels.
4. Clear glass panels.
5. Glass panels feature Spot Guard glass treatment for easy cleaning, to resist water spots and hardwater stains, and reduce soap scum and limescale bui ldup when properly maintained.
6. Modern, sleek, reversable track with semi-hidden rollers and no metal side jambs.
7. Size: Minimum 12 inches wider than opening by 72 inches high.
8. Fully frameless, premium 3/8 inch ANSI certified tempered safety glass panels.
E. Robe Hook:
http://www.specagent.com/Lookup?ulid=11636 http://www.specagent.com/Lookup?uid=123457157273 http://www.specagent.com/Lookup?uid=123457157273 http://www.specagent.com/Lookup?uid=123457157270 http://www.specagent.com/Lookup?uid=123457157278 http://www.specagent.com/Lookup?uid=123457157271 http://www.specagent.com/Lookup?uid=123457157272 http://www.specagent.com/Lookup?uid=123457157275
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 3
1. Basis-of-Design Product: D2402SN –Franklin Brass.
2. Description: Double-prong unit.
3. Material and Finish: Satin chrome-plated zinc alloy (zamac).
F. Private-Use Towel Bar:
1. Basis-of-Design Product: D2424;30SN – Franklin Brass.
2. Description: 3/4-inch square tube with rectangular end brackets.
3. Mounting: Flanges with concealed fasteners.
4. Length: 24 inches and 30 inches.
5. Material and Finish: Polished aluminum
G. Private-Use Towel Ring:
1. Basis-of-Design Product: D2416SN –Franklin Brass.
2. Description: Pin projecting approximately 2-1/2 inches from wall with circular ring.
3. Pin Material and Finish: Polished chrome-plated zinc alloy (zamac).
4. Ring Material and Finish: Matching pin.
2.2 CUSTODIAL ACCESSORIES
A. Source Limitations: Obtain custodial accessories from single source from single manufacturer.
2.3 MATERIALS
A. Stainless Steel: ASTM A240/A240M or ASTM A666, Type 304, 0.031-inch-minimum nominal thickness unless otherwise indicated.
B. Steel Sheet: ASTM A1008/A1008M, Designation CS (cold rolled, commercial steel), 0.036-inch-minimum nominal thickness.
C. Galvanized-Steel Mounting Devices: ASTM A153/A153M, hot-dip galvanized after fabrication.
D. Fasteners: Screws, bolts, and other devices of same material as accessory unit, unless otherwise recommended by manufacturer or specified in this Section, and tamper and theft resistant where exposed, and of stainless or galvanized steel where concealed.
E. Chrome Plating: ASTM B456, Service Condition Number SC 2 (moderate service).
F. Mirrors: ASTM C1503, Mirror Glazing Quality, clear-glass mirrors, nominal 6.0 mm thick.
2.4 FABRICATION
A. General: Fabricate units with tight seams and joints, and exposed edges rolled. Hang doors and access panels with full-length, continuous hinges. Equip units for concealed anchorage and with corrosion-resistant backing plates.
TOILET, BATH, AND LAUNDRY ACCESSORIES 102800 - 4
3.1 INSTALLATION
A. Install accessories according to manufacturers' written instructions, using fasteners appropriate to substrate indicated and recommended by unit manufacturer. Install units level, plumb, and firmly anchored in locations and at heights indicated.
1. Remove temporary labels and protective coatings.
3.2 ADJUSTING AND CLEANING
A. Adjust accessories for unencumbered, smooth operation. Replace damaged or defective items.
B. Clean and polish exposed surfaces according to manufacturer's written instructions.
END OF SECTION 102800
1 Section 15400
PLUMBING FIXTURES, EQUIPMENT, AND SPECIALTIES
1.1 SUMMARY
A. Section includes the following:
1. Plumbing fixtures, rough-in, setting and connection
1.2 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specifications, apply to this Section.
1.3 SUBMITTALS
A. Product Data: Provide submittals on all items furnished under this section.
B. Closeout Submittals: Submit Operating and Maintenance (O&M) data and parts list for each item of equipment, control, and accessory; including "troubleshooting" maintenance guide.
1.4 SEISMIC REQUIREMENTS
A. All system components must comply with the seismic requirements. These include requirements for anchorage, internal, and attached/imbedded components. Included are the minimum 2006 International Building Code requirements plus additional criteria for this project.
PART 2 - PRODUCTS
2.1 PLUMBING FIXTURES AND TRIM
A. Approved manufacturers are:
1. Water Closets - Kohler, American Standard, Universal Rundle, Eljer, Zurn (Or approved equal in quality and durability)
2. Lavatories - Kohler, American Standard, Universal Rundle, Eljer, Zurn (Or approved equal in quality and durability) 3 Water Closet Seats - Furnished with fixture or equal of Olsonite, Beneke, Sperzel, Bemis, Zurn
4. Flush Valves - Delany, Sloan, Zurn (Or approved equal in quality and durability) (Or approved equal in quality and durability)
5. Showers – Best Bath or approved equal.
6. Traps, Stops, Supplies, Drains - Brasscraft, Kohler American Standard, Zurn (Or approved equal in quality and durability)
7. Faucets - Chicago Faucet, American Standard, Kohler (Or approved equal in quality and durability)
8. Fixture Carriers - Josam, Smith, Zurn, Wade
2 Section 15400
B. Provide plumbing fixtures complete with trim, supply, and waste connections as scheduled on the drawings and SOW.
C. All exposed trim shall be chrome-plated brass unless otherwise specified in schedule.
D. All mixing valve, shower valves, and faucets shall be certified per NSF Standard 61, Section 9.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Plumbing Fixtures:
1. Set fixtures level with solid backing behind lavatory supports.
2. Provide chrome-plated anchor bolts and washers for all lavatories and china bolt caps for all floor-mounted water closets.
3. Remove all labels, clean fixtures, and leave installation ready for use.
4. Provide rigid bracing…
This is the start of the file's text. The full file is on GovTribe.