A06_SOW_18RD_EVENT_AREA_GRADING.pdf

PDF 312 KB Posted

Attached to
BLM-CO GJFO 18RD EVENT AREA GRADING
Solicitation number
140L1725Q0036
Issued by

About this file

This Statement of Work (SOW) details grading services for a 3-acre event area at the Bureau of Land Management's Grand Junction Field Office in Colorado. The contractor will level and grade a gravel surface to create a stable, functional area capable of supporting large gatherings, vehicles, and structures like tents and stages. Specific requirements include leveling the surface within a +/- 1-inch tolerance, ensuring proper drainage to prevent water accumulation, compacting the gravel to achieve 95% maximum dry density, and creating smooth transitions for vehicles and pedestrians. The work must comply with American Public Works Association (APWA) specifications for grading and drainage, and a no-cost pre-work meeting will be held to discuss project details and timing to avoid interference with scheduled events. The project is associated with a NEPA environmental assessment (DOI-BLM-CO-S080-2018-0037-EA) for a 18 Road Mountain Bike Event Venue.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

Bureau of Land Management Grand Junction Field Office Grand Junction, CO 81506

Statement of Work (SOW)

18 Road Event Area Grading Grand Junction Field Office

This Statement of Work (SOW) is for the BLM Grand Junction Field Office (GJFO).

DESCRIPTION OF SERVICES

The contractor will provide grading services to a gravel surface of approximately 3-acre event area to ensure it is level, stable, and functional. The area will need to support large gatherings, vehicles, and structures like tents and stages.

o Level the gravel to ensure a smooth and even surface.

o Address any low or high spots that could create uneven terrain or puddles.

o Compact the gravel to provide a firm, stable surface suitable for traffic, booths, and structures.

o Assess the current drainage flow and identify any areas prone to water accumulation. Improve basic drainage features to prevent water buildup and ensure the area remains accessible during wet conditions.

o Grade the area to promote proper water flow, especially around key traffic zones, entrances, and seating areas.

o Grade access points and parking areas to ensure smooth, safe transitions for vehicles o Compact the area for long-term stability and a polished appearance.

o Ensure that the gravel surface is firm, level, and visually even across the entire site.

QUALITY ASSURANCE PLAN

Inspection will be done by the Government Representatives:

The Government will consider the work acceptable when the contracted services meet the standards illustrated in the “Description of Services”. If the work does not meet these requirements, the contractor will be notified to take corrective action. Payments for services will be made according to these requirements. Any additional cost for the corrective action will be the responsibility of the contractor.

MEASURABLE STANDARDS

The surface must be level within a tolerance of +/- 1 inch over the entire area No standing water should be present 24 hours after a rain event.

The compacted gravel must achieve a minimum density of 95% of the maximum dry density as determined by ASTM D1557.

Drainage improvements must ensure water flows away from key traffic zones, entrances, and seating areas without pooling.

INDUSTRY SPECIFICATIONS

The work must comply with the latest edition of the American Public Works Association (APWA) specifications for grading and drainage.

PRE-WORK MEETING

A no-cost pre-work meeting will be held to discuss the project requirements, site conditions, and any other relevant details, namely the timing of work as it cannot interfere with scheduled events that utilize the area to be graded.

NEPA

DOI-BLM-CO-S080-2018-0037-EA

Recreation: 18 Road Mountain Bike Event Venue