A06_Drawings_Fort_Howes_Water_Storage_Tank_Replacement.pdf

PDF 3 MB Posted

Attached to
FORT HOWES WATER STORAGE TANK Federal contract opportunity
Solicitation number
140L3626Q0032
Issued by
Department of the Interior Bureau of Land Management

About this file

This document is a set of technical construction drawings and specifications for the Fort Howes Water Storage Tank Replacement project managed by the Bureau of Land Management's Eastern Montana Dakotas District Office in Fort Howes, Montana.

The project involves the demolition of an existing 19,000-gallon concrete water storage cistern and installation of a new 20,000-gallon reinforced fiberglass construction (FRP) water storage tank. Key construction requirements include: replacement of existing water supply and drain piping with new PVC lines; installation of new gate valves, frost-free hydrants, and check valves; trenching to a minimum depth of 6.0 feet with specified backfill materials and compaction standards; installation of geotextile fabric and stone bedding layers around the tank; pressure testing and disinfection of all new waterline piping per AWWA standards; and compliance with OSHA excavation requirements (1926.651). The new tank specifications require NSF-approved fittings, a Xerxes single-wall FRP tank design with precast deadman hold-down strap system, 30-inch manway access with hinged lockable cover, NSF-approved tangential nozzles for inlet and drain outlets, and a vent pipe with bug screen. The contractor must use manufacture-certified installers and submit test reports for soil compaction, tank pressure tests, and material certifications to the contracting office. The project drawings include site schematics, demolition plans, tank profile details, thrust block requirements, gate valve assembly details, standard utility trench specifications, and deadman installation dimensions specific to a 10-foot diameter tank.

View the file

Other files for this federal contract opportunity

Other files attached to FORT HOWES WATER STORAGE TANK, newest first.
File Type Posted
Sol_140L3626Q0032_Amd_0001.pdf PDF
B09_Amended_Solicitation_0001_0001.pdf PDF
Bid_Schedule_Fort_Howes_Water_Storage_Tank_Replacement.pdf PDF
B03_WD_MT20260076_Dated_5_18_2026.pdf PDF
Sol_140L3626Q0032.pdf PDF
A06_Specfications_Fort_Howes_Water_Storage_Tank_Replacement.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N A

TI

O

N A

L

SY

ST

EM

O F

PU

BL

IC

L

A N

D S

U .S

. D

EP

A

RT

M

EN

T O

F

TH

E

IN

TE

RI

O R

BU

RE

A U

O F

LA

N

D M

A N

A G

EM

EN

T

GENERAL NOTES:

1. ALL EXCAVATIONS ARE TO

FOLLOW OSHA 1926.651.

2. INSTALL WATER STORAGE

TANK PER MANUFACTURE

INSTRUCTIONS AND THE

ADDITIONAL BACKFILL

REQUIREMENTS IN THE

CONSTRUCTION DRAWINGS.

3. TEST WATER STORAGE TANK

PER MANUFACTURE

INSTRUCTIONS.

4. SUBMIT ALL TEST REPORTS

FOR SOIL COMPACTION, TANK

PRESSURE TEST, MATERIAL

CERTIFICATIONS FOR THE

BACKFILL TO THE

CONTRACTING OFFICE.

5. INSTALLATION TO BE

PERFORMED BY

MANUFACTURE CERTIFIED

INSTALLERS.

BACKFILL REQUIREMENTS:

1. INSTALL A GEOTEXTILE MATERIAL AT THE PERIMETER INTERFACE OF THE NATIVE SOIL AND BETWEEN THE

PRIMARY AND SECONDARY BACKFILL LAYERS THAT MEETS THE FOLLOWING: 100% POLYPROPYLENE STABLE

FIBER, NEEDLE-PUNCHED, WEIGHT 3.5 OUNCES PER SQUARE YARD.

2. OVERLAP ALL GEOTEXTILE SEAMS A MINIMUM OF 12 INCHES.

3. PRIMARY BACKFILL AND BASE COURSE (BEDDING LAYER)- USE COURSE AGGREGATE AS BACKFILL

4. PRIMARY BACKFILL MATERIAL SHOULD BE A MIX OF WELL-GRADED STONES, CONFORMING TO THE 6,67,7 AND 8

SIZES OF ASTM C33.

5. PRIMARY BACKFILL, NO MORE THAN 5% OF MATERIAL CAN PASS THROUGH THE #8 SIEVE.

6. COMPACT PRIMARY BACKFILL USING 3 PASSES WITH VIBRATORY EQUIPMENT IN 12" LIFTS .

7. SECONDARY BACKFILL - COMPACT TO ACHIEVE A MINIMUM OF 90% STANDARD PROCTOR DENSITY.

8. SECONDARY BACKFILL- 100% OF THE MATERIAL TO PASS THROUGH A 1-INCH SIEVE.

9. SECONDARY BACKFILL - INSTALL IN 12" LIFTS.

10. RESEED DAMAGED SURFACE AREA VEGETATION WITH NATIVE GRASS MIXES, PROTECT AREA AND WATER UNTIL

SEED GERMINATES.

11. DO NOT ALLOW BACKFILL TO FALL FROM EQUIPMENT MORE THAN 2-3 FEET TO PROTECT TANK.

N A

TI

O

N A

L

SY

ST

EM

O F

PU

BL

IC

L

A N

D S

U .S

. D

EP

A

RT

M

EN

T O

F

TH

E

IN

TE

RI

O R

BU

RE

A U

O F

LA

N

D M

A N

A G

EM

EN

T

DEADMAN INSTALLATION DIMENSIONS FOR A 10 FOOT DIAMETER 20,000 GALLON TANK.

1. A -STRAP EYE TO ANCHOR POINT - 38 INCHES

2. B - ALTERNATE DIMENSION - 26 INCHES - REQUIRES PRE APPROVAL BY BUREAU OF LAND MANAGEMENT

ENGINEERING

3. C- STRAP LENGTH -236 INCHES

4. D - CENTER OF TANK TO CENTER OF DEADMAN - 70 INCHES..

5. INSTALL MANUFACTURE'S DEADMAN SYSTEM IN BASE LAYER.

6. ALL ANCHORING CABLES AND COMPONENTS TO BE HOT DIPPED GALVANIZED.

7. FOLLOW MANUFACTURE'S INSTRUCTIONS FOR TERMINATING THE CABLES TO THE DEADMAN.

8. DEADMAN SYSTEM SUPPLIED BY THE MANUFACTURE OF THE WATER STORAGE TANK.

COVER SHEET 040826
EXISTING SITE 040826
ENLARGED EXISTING SITE SCHEMATIC 040826
SITE PLAN 040826
DETAILS 040826
WATER STORAGE TANK 040826
TANK INSTALLATION 040826
Sheets and Views
11X17
TANK INSTALLATION DEADMAN 040826
Sheets and Views
11X17
2026-04-09T11:07:55-0600
DAVID ROBERTS