A06_Attachment_1-_Statement_of_Work-_Specifications_2026_Alfalfa_Hay.pdf

PDF 162 KB Posted

Attached to
Procure alfalfa hay for the animals at the Rock Sp
Solicitation number
140L6226Q0015
Issued by

About this file

This is a Statement of Work (SOW) for hay procurement and delivery services issued by the Bureau of Land Management (BLM) Rock Springs Wild Horse and Burro Facility in Rock Springs, Wyoming. The BLM requires approximately 2,500 tons of 2026 crop alfalfa hay to be procured and delivered to the facility located at Lionkol Road, Rock Springs, WY 82901. The hay must meet specific quality standards including crude protein content between 14% and 25%, domestic origin, proper curing and storage, and freedom from mold, dust, heat damage, spoilage, and prohibited weeds. Bales must measure either 3 ft. × 4 ft. × 8 ft. (approximately 1,300 pounds) or 3 ft. × 3 ft. × 8 ft. (approximately 800 pounds), be free from damage, and exclude top or bottom bales from outdoor stacks. All deliveries require state-certified weight tickets; handwritten tickets are not acceptable.

The contractor must coordinate hay sourcing and transportation within five business days of contract award and deliver the first load within ten business days. A minimum of six semi-truck loads per week must be delivered Monday through Friday between 7:30 a.m. and 3:30 p.m. local time, excluding federal holidays. The contractor is responsible for unloading and stacking all hay to six bales high within hay sheds using appropriate equipment; skid steers are prohibited. Pre-shipment notification must be provided three business days before delivery, including anticipated shipment date, tonnage, and carrier information. All deliveries are subject to visual inspection and potential bale opening for compliance verification. The Government will use a Lowest Price Technically Acceptable (LPTA) source selection process, evaluating offerors on subcontractor identification, quality control plan, minimum three past performance references, current 2026 hay nutritional analysis, and equipment capability. Payments will be made after confirmation and acceptance of each delivery.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Hay Procurement and Delivery Services

Bureau of Land Management (BLM)

Rock Springs Wild Horse and Burro Facility

1.0 GENERAL

The Bureau of Land Management (BLM), Rock Springs Wild Horse and Burro Facility, Rock Springs, Wyoming, requires the procurement and delivery of approximately 2,500 tons of alfalfa hay for use as livestock forage.

2.0 SCOPE OF WORK

Provide and deliver approximately 2,500 tons of 2026 crop alfalfa hay in accordance with the specifications contained in this Statement of Work (SOW).

3.0 HAY SPECIFICATIONS

3.1 Alfalfa Hay Requirements

The hay supplied under this contract shall meet the following requirements:

a. The hay shall:

1. Be harvested from the 2026 crop year.

2. Contain a crude protein content between 14% and 25%.

3. Be domestically grown within the United States.

4. Be leafy, green, well-cured, properly stored, and free from dust, mold, heat damage, or spoilage.

5. Be barn stored or protected with hay tarps. Hay stored outdoors without cover must be free from weather-related damage.

6. Be free of Russian thistle, prickly herbs, cheat grass, and any weeds or grasses deemed unsuitable or unsafe forage for domestic animals.

b. The hay shall not:

1. Contain bearded grain or forage plants with long awns (spikelets).

2. Contain less than 14% crude protein.

3. Exceed 16% moisture or contain less than 10% moisture.

4.0 BALE REQUIREMENTS

4.1 Large Bale Specifications

a. Bales shall:

1. Measure either:

o 3 ft. × 4 ft. × 8 ft., or o 3 ft. × 3 ft. × 8 ft.

2. Weigh approximately:

o 1,300 pounds for 3×4×8 bales o 800 pounds for 3×3×8 bales

b. Bales shall not:

1. Be ragged, broken, uneven in length, or have wires/twine with unequal tension.

2. Consist of top or bottom bales from outdoor stacks.

3. Exhibit any signs of rain or weather damage.

5.0 CERTIFIED WEIGHT TICKETS

1. Total shipped weight shall be verified by the Project Inspector (PI).

2. A State Certified Weight Ticket shall accompany each load delivered.

3. Handwritten weight tickets will not be accepted.

6.0 PLACE OF DELIVERY

The Contractor shall deliver, unload, and stack the hay at the following location:

Rock Springs Wild Horse and Burro Facility

Lionkol Road

Rock Springs, WY 82901

Point of Contact:

Jacob Benson

Phone: (307) 350-0002

7.0 DELIVERY SCHEDULE

1. Following contract award, the Contractor shall have up to five (5) business days to coordinate hay sourcing and transportation arrangements.

2. The first load(s) of hay shall be delivered within ten (10) business days after contract award.

3. The Contractor shall coordinate with the Contracting Officer’s Representative (COR) to deliver a minimum of six (6) semi-truck loads of hay per week to the Rock Springs Wild Horse and Burro Facility.

8.0 UNLOADING AND ACCEPTANCE

8.1 Pre-Shipment Notification

At least three (3) business days prior to shipment, the Contractor shall provide the COR with:

1. Anticipated shipment date

2. Estimated total tonnage to be shipped

3. Carrier name and contact information

8.2 Delivery Documentation

The carrier shall provide certified weight tickets for each load delivered. Handwritten weight tickets will not be accepted.

8.3 Inspection and Acceptance

1. All hay deliveries are subject to visual inspection prior to acceptance.

2. The COR may require any bale to be unloaded and opened for inspection to verify compliance with this

SOW.

3. Hay found to contain mold, heat damage, spoilage, prohibited weeds, or other non-conforming material may be rejected.

4. The COR reserves the right to reject any individual bale, load, or shipment that does not meet the requirements specified in Section 3.0.

8.4 Unloading Responsibilities

1. The Contractor shall be responsible for unloading and stacking all hay in designated areas and hay sheds at the facility.

2. The Contractor shall provide all necessary equipment for unloading and stacking operations.

3. Hay shall be stacked six (6) bales high within the hay sheds.

4. Skid steers shall not be used for unloading or stacking operations due to stacking height and stability requirements.

8.5 Delivery Hours

Deliveries shall occur between:

• 7:30 a.m. and 3:30 p.m. local time

• Monday through Friday

• Excluding weekends and Federal holidays

New Year's Day – January 1

Birthday of Martin Luther King, Jr. – Third Monday in January

Washington's Birthday (Presidents Day) – Third Monday in February

Memorial Day – Last Monday in May

Juneteenth National Independence Day – June 19

Independence Day – July 4

Labor Day – First Monday in September

Columbus Day – Second Monday in October

Veterans Day – November 11

Thanksgiving Day – Fourth Thursday in November

Christmas Day – December 25

8.6 Emergency Deliveries

If an emergency occurs, deliveries may be requested for a Saturday, Sunday, or national holiday, providing the

Contractor notifies the COR on the preceding Friday and/or within the preceding workday of the delivery date.

9.0 EVALUATION METHODOLOGY

Evaluation Methodology

The Government will use a Lowest Price Technically Acceptable (LPTA) source selection process. Award will be made to the responsible Offeror submitting the lowest evaluated price whose quote is determined to be technically acceptable in accordance with the requirements of this Statement of Work.

Quotes will first be evaluated for technical acceptability. Only those determined technically acceptable will be considered for award.

Evaluation Factors (Technical Acceptability)

The following factors will be used to determine technical acceptability. Each factor will be evaluated on a pass/fail basis:

1. Subcontractor Identification

Offeror shall identify all subcontractors/suppliers used to provide hay not grown or harvested on their own property and submit a completed Standard Form 1413 (Attachment 1), Statement and Acknowledgment.

2. Quality Control Plan

Offeror shall submit a Quality Control Plan demonstrating procedures to ensure compliance with all contract and SOW requirements.

3. Past Performance

Offeror shall provide a minimum of three (3) relevant past performance references, including contact information, contract type, dollar value, and scope of work.

4. Hay Nutritional Analysis

Offeror shall provide current 2026 hay nutritional analysis, including at a minimum: moisture content, crude protein, carbohydrates, and energy values (additional metrics such as TDN, fat, calcium, phosphorus, and magnesium may be included).

5. Equipment Capability

Offeror shall describe the equipment that will be used for unloading and stacking hay to ensure compliance with delivery requirements.

10.0 PAYMENT TERMS

Payments shall be made after confirmation and acceptance of each delivery by the Government.

File details come from the government source that posted it. Updated .