ORCA GENERAL REQUIREMENTS Page 1
LASSEN VOLCANIC NATIONAL PARK
REMOVE ASBESTOS (ACM) FLOORING AT
Qtrs. 16 and 17
PROJECT SPECIFICATIONS
GENERAL REQUIREMENTS
DATE: April 2023
PART 1 – SUMMARY OF WORK (SECTION 01 11 00)
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. General: All work outlined below will be performed under a single contract.
B. Project Location: This project is located at Quarters 16 and 17 within Lassen Volcanic National
Park Headquarters, Tehama County, CA. The buildings are located 35 miles east of Red Bluff, CA.
Directions to Qtrs. 16 and 17 (LAVO) from Red Bluff, CA.: To access the project site, take Highway 36 east from Red Bluff to park headquarters, 1 mile West of Mineral, California. A map is attached and can also be found in the park’s public website: http://www.nps.gov/lavo/index.htm . Mineral, California has food and lodging, but no fuel or repair services.
C. Project Background: Quarters 16 and 17 currently have existing resilient vinyl floor coverings.
Rehabilitation of the buildings by NPS has been halted due to asbestos being found in the existing resilient sheet flooring in both buildings.
Project Scope of Work: The Work consists of the following:
The National Park Service requires the removal and disposal of approximately 1200 sq. ft. of Asbestos
Containing Material (ACM) vinyl resilient flooring recently discovered in the existing flooring in
Quarters 16 and 17. Quarters 16 has 620 SF of flooring area and Quarters 17 has 572 SF of flooring area.
All areas with ACM need to be removed. Anything on top of or in the work area will be moved by the
NPS to allow access to all areas for removal of any ACM flooring by the contractor. The resilient flooring tested 25% chrysolite but the mastic test results were none detected. Results attached as
Attachment 2.
Specifications for ACM Flooring Removal and Abatement:
• DEQ Permits, equipment mobilization and materials.
• Abatement as per California Code of Regulation (CCR) Title 8, Section 1529.
• One (1) Air Clearance via PCM.
• Disposal of asbestos containing building materials (ACBM) at an approved landfill.
http://www.nps.gov/lavo/index.htm
ORCA GENERAL REQUIREMENTS Page 2
• Copies of permits and disposal forms to be provided at end of project.
1.2 REFERENCE DOCUMENTS / REPORTS
A. General: The following reference documents / reports are attached or available upon request to supplement the information in the specifications:
1. NPS Forms (RFI, CM-16, and QC Daily Report)
2. Park Regulations
1.3 GOVERNMENT-FURNISHED ITEMS
A. The Government may furnish products and materials for incorporation into the work.
1. The government will arrange and pay for delivery of government furnished items to the project site based on the contractor’s approved construction schedule.
2. After delivery, the government will inspect delivered items for damage. If items are damaged, defective, or missing, the government will arrange for replacement.
3. The contractor is responsible for receiving, unloading, and handling government furnished items at project site for use in the work.
4. The contractor is responsible for protecting government furnished items during storage, handling, and the work, including damage from exposure to the elements.
5. If government furnished items are damaged as a result of the contractor’s operations, the contractor shall repair or replace the items in-kind.
B. Government-Furnished Items: The government will furnish the following products or materials for use on this contract: None anticipated
1.4 PUBLIC / STAFF USE OF THE SITE
A. General: The project site will be closed to the public & staff during construction. The contractor shall always conduct his operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the
Contracting Officer.
1.5 CONTRACTOR USE OF SITE
A. General: Limit use of the site during the construction period to the project area limits as identified at the site visit.
B. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
C. Park Entry: Headquarters is not gated and contractor shall have full access to the work sites during business hours.
ORCA GENERAL REQUIREMENTS Page 3
1. Provide the Contracting Officer with a listing of all contract personnel and their associated vehicles entering the HQ area.
2. Provide the Contracting Officer with a listing of anticipated deliveries for each week.
D. Site Access: The contractor shall access the project site as agreed with NPS. Do not drive vehicles off road or access non-project areas without permission from the contracting officer or their representative.
E. Working Hours: Normal business hours, Monday – Friday, 8:00am to 4:30 pm.
F. Staging and Storage: Confine the storage of equipment and materials to the staging / lay-down / storage areas as established at the preconstruction meeting.
G. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to a Law Enforcement Ranger or Park Dispatch at the first available opportunity at 530-595-6150.
H. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings and buildings under construction or renovation.
Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
PART 2 – WORK RESTRICTIONS (SECTION 01 11 40)
2.1 WORK RESTRICTIONS
A. General: The Contractor must comply with the following work restrictions:
B. Vehicles / Heavy Equipment:
1. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
2. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts.
3. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles always.
4. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to
ORCA GENERAL REQUIREMENTS Page 4 enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
5. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the
Contracting Officer of spills.
6. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
7. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
8. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road).
Oversized vehicles must not exceed the clearances along the Park road corridor.
Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates, and estimated arrival times at the park entrance; and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
9. Road & Weight Restrictions: All vehicle load, weight, and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11).
No loads heavier than the current load rating for park roads and bridges will be permitted.
C. Resource Protection:
1. General: The Park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
2. Preservation of Natural Features: Prevent damage to natural surroundings. Do not attach ropes, wires, guy lines, cables, or chains to trees or vegetation. Restore damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.
3. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and watch for animals on or alongside road or at the jobsite. Contact YOSE Dispatch at 209-379-1992 immediately if animal is hit or injured or will not move off the road.
ORCA GENERAL REQUIREMENTS Page 5
The following measures are required to minimize disturbance to endangered wildlife:
a. Work shall be conducted to ensure the work area is cleaned up at the end of each work shift so that loose tools, debris, and materials are not left out in a manner that could present a hazard to a listed species.
b. Noise and vibrations of equipment shall be kept to a minimum when working in the vicinity of a listed species.
c. Hazmat spill prevention protocols shall be employed when using gas-powered equipment.
d. Tarps shall be used to contain all paint chips and building debris from exterior surfaces that may fall to the ground.
e. Ensure loose nails and screws do not make it to the ground when working on exterior surfaces as these can be detrimental to listed species.
4. Archaeological Resources: Archaeological resources are physical evidence of past human activity, including evidence of the effects of that activity on the environment.
Archaeological resources are found above and below ground and underwater. The
Contractor’s Project Superintendent, or designee, will observe all ground-disturbing activities in archaeological sensitive areas. If the Contractor discovers resources, the
Contractor shall stop work or relocate to a non-sensitive area and contact the Contracting
Officer immediately. The Park may also have an Archaeological Monitor at the jobsite who is authorized to stop work upon discovery of archaeological resources.
Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.
5. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.
PART 3 – PROJECT MANAGEMENT (SECTION 01 31 00)
3.1 SUBMITTALS
A. Division 01 Submittal Documents: The following documents shall be submitted a minimum of one week prior to the Preconstruction Meeting. If all of these documents have not been received one week prior to the scheduled Preconstruction Meeting date, the meeting will be cancelled and the Notice to Proceed (NTP) will not be issued. Work shall not commence until written Notice to Proceed has been issued.
1. Contractor Licensing Board Asbestos Certification - Submit a copy of the Contractor’s
California State Contractor’s Licensing Board Asbestos Certification in accordance with the California Business and Professional Code, Section 7058.5.
2. Letter designating the Project Superintendent.
ORCA GENERAL REQUIREMENTS Page 6
3. Construction Schedule - Submit a baseline schedule with start date, end date, major work activities and durations, estimated pre-final inspection date, and other major milestones.
Provide updates to baseline schedule as needed / requested during construction.
4. Schedule of Values (SOV) – Submit a schedule of values with a breakdown of component work activities for which progress payments will be requested. The total costs for the component work activities shall equal the total contract price.
5. Accident Prevention Plan (APP) – Submit an accident prevention plan with the name of the supervisor responsible for executing the plan, a job hazard analysis for each major work activity, first aid procedures, and planning for potential emergency situations.
6. Storm Water Pollution Prevention Plan (SWPPP) – For projects with ground disturbance estimated to be greater than 1-acre, complete and submit a SWPPP to the Authority
Having Jurisdiction that satisfies all Federal and State permit requirements under the
National Pollution Discharge Elimination System (NPDES) prior to NTP. For projects with ground disturbance estimated to be less than 1-acre, complete and submit a SWPPP to the NPS with best management practices to prevent the discharges of pollutants.
7. A list of Subcontractors for this project.
8. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
9. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
B. Division 02-49 Submittal Documents: The following documents shall be submitted to the
Contracting Officer prior to construction start. If these documents have not been received and approved by the NPS prior to construction, the construction start date may be delayed.
1. Product Data – Not used.
2. Samples – Not used.
3. Shop Drawings – Not used.
3.2 PRECONSTRUCTION MEETING
A. Preconstruction Meeting: Before the start of construction, the Contracting Officer will arrange for a preconstruction meeting either on site or via teleconference. The meeting agenda will include the following topics:
1. NPS Roles & Responsibilities
2. Key Contractor Personnel
3. Coordination with Subcontractors
4. Correspondence & Submittal Procedures
5. Submittals
a. Status of Division 01 Submittals
ORCA GENERAL REQUIREMENTS Page 7
b. Schedule & SOV
c. Safety & Accident Prevention Plan
d. Storm Water Pollution Prevention Plan
e. Status of Division 02-49 Submittals
6. Park Rules & Regulations
7. Work Hours and Weekend, Holiday, and Night Work
8. Project Information
a. Park Access & Vehicle Reporting
b. Jobsite Access & Parking
c. Staging, Storage, and Lay Down Area(s)
d. Temporary Facilities & Controls
e. Jobsite Restrictions
f. Resource Protection
g. Weather, Climate, Environmental Conditions
h. Reference Documents
i. Other Contracts / Ongoing Work
9. Labor Standards Provisions
10. Labor Interviews
11. Payroll Reports
12. Payments to the Contractor
13. Change Orders / Modifications
14. Progress Meetings
15. QC Daily Reports
16. Inspections
17. Acceptance and Rejection of Work
18. Closeout Procedures & Submittals
19. Contract Period of Performance
20. Notice to Proceed
3.3 REQUESTS FOR INFORMATION (RFIs)
A. General: On discovery of the need for additional information or interpretation of the Contract
Documents, the Contractor shall prepare and submit a RFI utilizing the form attached.
1. Contracting Officer will only respond to RFIs submitted by the Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. RFI Form: Include a detailed, legible description of the subject or item needing information or interpretation on the RFI Form with:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, if applicable.
6. Photographs or sketches if applicable.
7. Contractor's suggested resolution. If the Contractor's suggested resolution impacts the contract time or the contract sum, Contractor shall state impact in the RFI.
C. Response to the RFI: The Contracting Officer will review each RFI, determine the action required, and respond accordingly.
ORCA GENERAL REQUIREMENTS Page 8
PART 4 – SUBMITTAL PROCEDURES (SECTION 01 33 23)
4.1 SUBMITTAL PROCEDURES
A. CM-16 Transmittal Form: All submittals shall be transmitted using National Park Service CM-
16 form attached to the end of this specification section. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Complete all applicable fields, sign the form, and attach all supporting documentation.
PART 5 – SAFETY REQUIREMENTS (SECTION 01 35 23)
5.1 SAFETY REQUIREMENTS
1. First Aid Equipment: Provide adequate first aid equipment for all contract employees and the hazards associated with the types of ongoing construction work at the site.
2. First Aid Training: Provide adequate training to all Contractor personnel to ensure prompt and efficient application of first aid.
3. Personal Protective Equipment (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees.
4. Hazardous Materials: Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury. Store hazardous materials in accordance with manufacturer’s and OSHA recommendations. Maintain SDS onsite for each chemical used on the jobsite. Immediately report all spills of hazardous materials to the contracting officer.
5. Safety Meetings: At a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the week.
6. Emergency Contacts: Post telephone numbers and reporting instructions for ambulance, hospital, fire department, police, and park dispatch in conspicuous locations at the site.
7. Emergency Reporting: In the event of an emergency medical incident, the Contractor shall
Dial 911 as needed. The Contractor shall also contact Park Dispatch at 541-592-2100 for any medical emergency, traffic accident, or personal injury occurring within the Park. Park
Dispatch is called so that the entrance station will be prepared should any emergency vehicles need to enter the Park and so that any available Emergency Medical Services personnel in the
Park might respond until such time as the ambulance arrives.
PART 6 – QUALITY REQUIREMENTS (SECTION 01 40 00)
5.1 QUALITY REQUIREMENTS
A. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of
ORCA GENERAL REQUIREMENTS Page 9 materials, workmanship, construction, finishes, and functional performance are in compliance with applicable specifications, drawings, building codes and standards.
B. Quality Control (QC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. The Contractor’s Quality Control Supervisor shall utilize the forms attached at the end of this Section. The submission frequency of the QC Daily
Report to the contracting officer will be determined at the preconstruction meeting.
PART 7 – TEMPORARY FACILITIES & CONTROLS (SECTION 01 50 00)
7.1 TEMPORARY FACILITIES & CONTROLS
A. General: The contractor will be allowed to set up temporary facilities and controls as outlined. All temporary facilities and controls shall be removed from the site before final acceptance of the work.
B. Temporary Utilities: The following utilities / services are available for use at the project site:
1. Electrical Power Service: Electrical power service is available from facilities at or near the project site for use on the contract without charge, but not available inside either building proper. Provide all connections and extensions of services in a safe manner in compliance with NEC, NEMA, and UL standards and regulations
2. Water Service: Potable water service is available from facilities at or near the project site for use on the contract without charge, but not available inside either building proper.
Provide all connections and extensions of services with proper backflow prevention devices in compliance with AWWA standards and local regulations.
3. Sanitary Facilities: Restrooms are available at or near the project site for use on the contract without charge. Please keep toilet clean so as not to add extra work for maintenance staff.
4. Telephone Cellular Service: The project site not does have cellular service , but is spotty.
C. Temporary Office: The construction of temporary office buildings or installation of trailers will not be allowed in the park. If the contractor requires office space, the park will attempt to accommodate the contractor with an existing space for administrative work.
D. Temporary Enclosures: For uncontrolled sites, the contractor shall construct an enclosure fence, barrier, or partition to prevent people and animals from entering the project site except by gates / doors.
E. Temporary Traffic Controls: Not used.
PART 8 – EXECUTION (SECTION 01 73 40)
8.1 EXECUTION
A. Examination: Examine the project area and site facilities and verify compatibility between existing conditions and the scope of work.
ORCA GENERAL REQUIREMENTS Page 10
B. Preparation: Take field measurements or conduct surveys to verify dimensions before fabrication or installation.
C. Installation: Install all systems or components according to the specifications, manufacturer’s recommendations, permit conditions (where applicable), and local, State, and Federal codes, standards, and regulations.
D. Correction of the Work: Upon discovery of defects or damage of new work or to existing facilities damaged by new work, repair or replace damaged systems or components and restore substrates and finishes.
E. Progress Cleaning: Clean the project site and work area on a daily basis. Keep site free of waste and debris in proper containment. Properly dispose of all waste and debris offsite.
F. Final Cleaning & Waste Disposal: At the completion of the work, clean all surfaces and remove all waste materials, trash, tools, equipment, machinery, and surplus items from the project site and legally dispose of all waste items.
PART 9 – CLOSEOUT PROCEDURES (SECTION 01 77 00)
9.1 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. When the project, or a designated portion of the project, is substantially complete, the
Contractor shall request a final inspection in writing. Upon receipt of the written request that the project is substantially complete, the Contracting Officer will proceed with a final inspection within ten (10) days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.
B. If the work is determined to be substantially complete at the final inspection, the Contracting
Officer will prepare a Letter of Substantial Completion with a Punch List of deficiencies to be corrected before final acceptance. The Contractor shall complete the work described in the
Punch List within thirty (30) calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.
C. If the work is determined to be not substantially complete, the Contracting Officer will notify the Contractor in writing. The Contractor may request a new final inspection. All re-inspection costs may be charged against the Contractor in accordance with the Inspection of
Construction clause of the contract.
D. After all deficiencies have been corrected and the project is complete, a Letter of Final
Acceptance will be issued by the Contracting Officer.
9.2 CLOSEOUT SUBMITTALS
A. Operation & Maintenance (O&M) Manual: Not used.
9.3 DEMONSTRATION & TRAINING
A. Demonstration & Training: Not used.
ORCA GENERAL REQUIREMENTS Page 11
Map of Park Headquarters. Quarters 16 and 17 circled.
Exterior view of Quarters 16
ORCA GENERAL REQUIREMENTS Page 12
Photo showing existing conditions inside Quarters 16 and 17. NPS will be responsible for removing all furniture before contractor starts work.
Floor plan of Quarters 17 (below)
ORCA GENERAL REQUIREMENTS Page 13
Floor plan of Quarters 16 (below)
ORCA GENERAL REQUIREMENTS Page 14
EMSL Analytical, Inc.
464 McCormick Street San Leandro, CA 94577 Tel/Fax: (510) 895-3675 / (510) 895-3680 http://www.EMSL.com / sanleandrolab@emsl.com
EMSL Order: 092308256 Customer ID: LASS75 Customer PO:
Project ID:
Attention: Gary Mott Phone: (530) 595-6220 Lassen Volcanic National Park Fax: (530) 595-3272 PO Box 100 Received Date: 04/12/2023 9:00 AM Mineral, CA 96063 Analysis Date: 04/15/2023 Collected Date: 04/06/2023 - 04/10/2023
ORCA GENERAL REQUIREMENTS Page 15
Project: QUARTERS 16, MINERAL HEADQUARTERS DISTRICT , QTRS 17 AND DRAKESBAD
Test Report: Asbestos Analysis of Bulk Materials via AHERA Method 40CFR 763 Subpart E Appendix E supplemented with EPA 600/R-93/116 using Polarized Light Microscopy Sample Description Appearance % Fibrous % Non-Fibrous Non-Asbestos Asbestos % Type
2-Linoleum Flooring 092308256-0002 Matrix 25% Chrysotile Non-fibrous (Other) 60% 10% Gray/Tan 5% Cellulose Fibrous Homogeneous LINOLEUM FLOORING, QTRS.16 This is a composite result of both vinyl and backing layer
2-Mastic 092308256-0002A Matrix None Detected Non-fibrous (Other) 80% 20% Yellow Non-Fibrous Homogeneous LINOLEUMFLOORING, QTRS.16 Analyst(s) Stacy Trinh Le (6) Cecilia Yu, Laboratory Manager or Other Approved Signatory EMSL maintains liability limited to cost of analysis. Interpretation and use of test results are the responsibility of the client. This report relates only to the samples reported above, and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no responsibility for sample collection activities or analytical method limitations. The report reflects the samples as received.
Results are generated from the field sampling data (sampling volumes and areas, locations, etc.) provided by the client on the Chain of Custody. Samples are within quality control criteria and met method specifications unless otherwise noted. The above analyses were performed in general compliance with Appendix E to Subpart E of 40 CFR (previously EPA 600/M4-82-020 “Interim Method”) but augmented with procedures outlined in the 1993 (”final”) version of the method. This report must not be used by the client to claim product certification, approval, or endorsement by NVLAP, NIST or any agency of the federal government. Non-friable organically bound materials present a problem matrix and therefore EMSL recommends gravimetric reduction prior to analysis. Unless requested by the client, building materials manufactured with multiple layers (i.e. linoleum, wallboard, etc.) are reported as a single sample. Estimation of uncertainty is available on request.Samples analyzed by EMSL Analytical, Inc San Leandro, CA NVLAP Lab Code 101048-3, WA C884
Initial report from: 04/15/2023 14:44:49
ASB_PLM_0008_0001 - 1.78 Printed: 4/15/2023 2:44 PM