This is an Acceptable Quality Level (AQL) inspection form and performance standards document for janitorial services at a Bureau of Land Management facility. The AQL establishes that the contractor must maintain 15 or fewer deficiencies during any 30-day calendar month with a maximum of 3 deficiencies per individual inspection. Failure to perform any specific task outlined in the inspection standards will result in non-compliance with AQL requirements. The Contracting Officer's Representative (COR) or designated project inspector will conduct random inspections of all services performed.

Payment is structured on a deficiency-based scale: full payment is made when deficiencies number 5 or fewer per month; 90% payment when deficiencies range from 6-10; 80% payment when deficiencies range from 11-15; and pro-rated payment based on days meeting AQL standards when deficiencies exceed 15 or when more than 3 deficiencies are documented per inspection. The document specifies detailed inspection standards covering floors (vacuuming, sweeping, mopping, scrubbing), restrooms (fixtures, walls, floors, disinfection), restroom supplies, waste and recycling containers, drinking fountains, glass doors, and windows. Repeated failure to meet AQL standards may result in default termination. The contractor must also ensure annual tile floor cleaning, stripping, and resealing in the Interpretive Center on a designated date.

View the file

Other files for this federal contract opportunity

Other files attached to YH- YHONA_JANITORIAL SERVICES, newest first.
File Type Posted
B03_Wage_Determinations.pdf PDF
A06_Site_map_-_Attachment_C.jpg JPG image
A06_Corrective_Action_Plan_-_Attachment_D.docx DOCX document
A06_Interpretive_Center_floor_plan_-_Attachment_B.pdf PDF
Sol_140L4326Q0021.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit A

Acceptable Quality Level (AQL) (Per E.2.0) The AQL is 15 or fewer deficiencies during a 30 day calendar month with no more than 3 deficiencies per inspection. Failure to perform any specific task in Section C noted during an inspection will result in not meeting AQL. Contractor may be called back by government representative to reperform deficient services. Repeated failure to meet the AQL will be grounds for default termination. Inspection of services performed will be performed on a random basis by the COR or designated project inspector.

PAYMENT (Per E.3.0) Payment will be made at the unit price as shown in Section B in accordance to the following terms: Where the number of deficiencies found during inspections is no more than 5 for all inspections during a calendar month, full payment will be made. Where the number of deficiencies is from 6 to no more than 10, 90% payment will be made. Where the number of deficiencies is from 11 to no more than 15, 80% payment will be made. Where the number of deficiencies is greater than 15, or greater than 3 deficiencies per inspection are documented not meeting AQL, a pro-rated payment will be made after input from government and contractor utilizing the Contract Corrective Action Plan document (Attachment D) based on the days calculated that met AQL at the daily rate.

Where the number of deficiencies exceeds the AQL of 15, the Contractor will be instructed to take necessary action to ensure that future performance conforms to contract requirements. If the Contractor fails to perform to contract requirements the Government may (1) by contract or otherwise, perform the services and charge to the Contractor any cost incurred that is directly related to the performance of such service, (2) issue payment based on the pro-rated calculation for work that met AQL, or (3) terminate the contract for default.

Contractor shall meet the following minimum inspection standards for Government acceptance:

Date:
Pass
Deficiency

E.2.2.1 Floors (vacuuming, sweeping, mopping, scrubbing) - All floors and mats shall be clean and free of visible dust, dirt, gum, debris, scuff marks, and stains. Floors to be mopped will be swept first. Restroom floors shall be disinfected. No dirt or debris shall be left in corners, under furniture/mats, or behind doors. Once per year on designated date tile floors in Interpretive center will be cleaned, stripped, and resealed.

E.2.2.2 Restrooms - All fixtures, walls, floors, partitions, counter tops, risers, doors, etc. shall be free of dust, debris, smudge marks, streaks, water spots, stains and disinfected to provide a clean and odorless appearance throughout. Chrome/metal fixtures shall have a polished appearance. Mirrors shall be clean and free of dirt, streaks, water spots, and smudge marks.

E.2.2.3 Supplies - Restrooms shall be stocked with sufficient supplies to ensure that the supplies will last until the next service.

E.2.2.4 Waste and recycling containers - All waste and recycling containers shall be emptied and plastic liners replaced. Soiled containers shall be cleaned and disinfected and be odor free. Waste and recycling will be placed in designated dumpsters outside of loading dock room 150 behind Interpretive Center

E.2.2.5 Drinking Fountains - Shall be clean and disinfected and free of streaks, stains, and water spots and have a polished appearance.

E.2.2.6 Glass Doors - Glass, handles, and door surfaces shall be clean and free of dust, streaks, smudge marks, stains, and water spots. Handles/openers shall have a polished appearance.

E.2.2.7 Windows - Shall be clean and free of dust, streaks, smudge marks, and water spots.