A06_-_140L1722Q0031-Section_013201_1.docx

DOCX document 23 KB Posted

Attached to
GAOA LSFO IRISH CANYON VAULT TOILET REPL
Solicitation number
140L1722Q0031
Issued by

View the file

Other files

File Type Posted
A06_-_140L1722Q0031-Section_033533_1.docx DOCX document
A06_-140L1722Q0031-Section_013300_1.docx DOCX document
A06_-_140L1722Q0031-Maps_and_Plans_1.pdf PDF
A06_-_140L1722Q0031-Section_311000_1.docx DOCX document
A06_-__140L1722Q0031-Section_033000_1.docx DOCX document
A06_-_140L1722Q0031-_Section_329200_1.docx DOCX document
A06__-_140L1722Q0031-_Section_034150_1.docx DOCX document
A04_-140L1722Q0031-_Bid_Schedule_1.pdf PDF
A06_-_140L1722Q0031-_Section_129300_00_1.docx DOCX document
A06_-_140L1722Q0031_-_Section_010090_1.docx DOCX document
A06_-_140L1722Q0031-Section_033550_1.docx DOCX document
A06_-__140L1722Q0031-Section_312000_1.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bureau of Land Management - Colorado State Office 01 32 01.00 Project Schedule

GENERAL

SUBMITTALS

Government approval is required for submittals with a "G" designation. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals Initial Project Schedule; G

PRODUCTS

Not Used

EXECUTION

GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, and pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required.

PROJECT SCHEDULE DETAILED REQUIREMENTS

Level of Detail Required Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution.

Mandatory Tasks Include the following activities/tasks in the initial project schedule and all updates.

Submission, review and acceptance of submittals.

Long procurement activities Contractor's pre-final inspection.

Government's pre-final inspection.

Final inspection.

Government Activities Include Government activities that could impact progress. These activities include, but are not limited to: Government inspections of work, Government approval of submittals.

WEEKLY PROGRESS MEETINGS

Conduct a weekly meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities.

FAILURE TO ACHIEVE PROGRESS

Should the progress fall behind the approved project schedule, the Contracting Officer may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.

Failure to Perform Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the Contracting Officer pursuant to FAR 52.236-15 Schedules for Construction Contracts, FAR 52.249-10 Default (Fixed-Price Construction), and other contract provisions.

Recovery Schedule Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.

End of Section