A06_-_140L1722Q0031-Section_013201_1.docx
DOCX document 23 KB Posted
- Attached to
- GAOA LSFO IRISH CANYON VAULT TOILET REPL
- Solicitation number
- 140L1722Q0031
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A06_-_140L1722Q0031-Section_033533_1.docx | DOCX document | |
| A06_-140L1722Q0031-Section_013300_1.docx | DOCX document | |
| A06_-_140L1722Q0031-Maps_and_Plans_1.pdf | ||
| A06_-_140L1722Q0031-Section_311000_1.docx | DOCX document | |
| A06_-__140L1722Q0031-Section_033000_1.docx | DOCX document | |
| A06_-_140L1722Q0031-_Section_329200_1.docx | DOCX document | |
| A06__-_140L1722Q0031-_Section_034150_1.docx | DOCX document | |
| A04_-140L1722Q0031-_Bid_Schedule_1.pdf | ||
| A06_-_140L1722Q0031-_Section_129300_00_1.docx | DOCX document | |
| A06_-_140L1722Q0031_-_Section_010090_1.docx | DOCX document | |
| A06_-_140L1722Q0031-Section_033550_1.docx | DOCX document | |
| A06_-__140L1722Q0031-Section_312000_1.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bureau of Land Management - Colorado State Office 01 32 01.00 Project Schedule
GENERAL
SUBMITTALS
Government approval is required for submittals with a "G" designation. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Initial Project Schedule; G
PRODUCTS
Not Used
EXECUTION
GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, and pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required.
PROJECT SCHEDULE DETAILED REQUIREMENTS
Level of Detail Required Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution.
Mandatory Tasks Include the following activities/tasks in the initial project schedule and all updates.
Submission, review and acceptance of submittals.
Long procurement activities Contractor's pre-final inspection.
Government's pre-final inspection.
Final inspection.
Government Activities Include Government activities that could impact progress. These activities include, but are not limited to: Government inspections of work, Government approval of submittals.
WEEKLY PROGRESS MEETINGS
Conduct a weekly meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities.
FAILURE TO ACHIEVE PROGRESS
Should the progress fall behind the approved project schedule, the Contracting Officer may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.
Failure to Perform Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the Contracting Officer pursuant to FAR 52.236-15 Schedules for Construction Contracts, FAR 52.249-10 Default (Fixed-Price Construction), and other contract provisions.
Recovery Schedule Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.
End of Section