A06 0040469875 20190607 Project Specifications.pdf

PDF 2 MB Posted

Attached to
MECHANICAL SYSTEM UPGRADES FOR CHARLESTOWN NAVY YA Federal contract opportunity
Solicitation number
140P4320R0004
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This document is a pre-solicitation announcement for mechanical system upgrades at two buildings in the Charlestown Navy Yard in Boston. The National Park Service is soliciting quotes for a base requirement to remove and replace two air handling units and one boiler in one building, with two options - to remove and replace an air handling unit in another building and replace select components of an air handling unit in a third area. The solicitation will be issued on or around July 31, 2020 via SAM.gov and will include specifications and drawings. This is a total small business set-aside for NAICS code 236220 with a size standard of $39.5 million. Interested vendors should monitor the website for amendments. The period of performance is anticipated to be 180 days starting November 1, 2020. Pricing is expected to be firm-fixed price.

View the file

Other files for this federal contract opportunity

Other files attached to MECHANICAL SYSTEM UPGRADES FOR CHARLESTOWN NAVY YA, newest first.
File Type Posted
A06 0040469875 20190607 Drawings.pdf PDF
R002 Temp Parking Application .pdf PDF
B03 140P4320R0004 20200313 Wage Determination MA20200001 Mod 3.pdf PDF
Attachment 0004 Limitations on Subcontracting Report.xlsx XLSX spreadsheet
Sol_140P4320R0004.pdf PDF
B08 140P4320R0004 Attach R001 PPQ.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BOSTON NATIONAL HISTORICAL PARK

CHARLESTOWN NAVY YARD

BOSTON, MASSACHUSETTS

MECHANICAL SYSTEM UPGRADES

FOR CHARLESTOWN NAVY YARD BLDGS. 22 & 28

USS CONSTITUTION MUSEUM

BOST

PMIS NO. 232490

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

06/07/2019

TABLE OF CONTENTS

SECTION TITLE

Division 1

01 11 00 01 26 01 01 27 00 01 31 00 01 32 16 01 33 23 01 35 23 01 40 00 01 42 00 01 50 00 01 57 19.11 01 57 19.12 01 57 23 01 67 00 01 73 29 01 73 40 01 74 19 01 77 00 01 78 23 01 81 13

Division 22

22 10 00 22 11 19

Division 23

23 05 00 23 05 19 23 05 23 23 05 29 23 05 48 23 05 53 23 05 93 23 07 13 23 07 19 23 09 00 23 11 10 23 21 13 23 21 23 23 31 13

Summary of Work Contract Modification Procedures Definition of Contract Line Items Project Management & Coordination Construction Schedule Submittal Procedures Safety Requirements Quality Requirements Reference Standards Temporary Facilities and Controls Indoor Air Quality Management Noise & Acoustics Management (NOT USED) Temporary Storm Water Pollution Prevention (NOT USED) Product Requirements Cutting and Patching Execution Construction Waste Management and Disposal Closeout Procedures Operation and Maintenance Data Sustainable Design Requirements for Non LEED Projects

Domestic Water Piping Plumbing Specialties

Mechanical General Provisions Meters and Gages Valves Hangers and Supports Mechanical Vibration and Seismic Controls Mechanical Identification Testing, Adjusting, and Balancing Duct Insulation Pipe Insulation Instrumentation and Controls for HVAC Natural Gas Piping Hydronic Piping Hydronic Pumps Metal Ducts

23 33 00 Duct Accessories 23 37 00 Diffusers, Registers & Grilles 23 41 00 Air Filters 23 51 00 Breechings, Chimneys, and Stacks 23 52 16 Condensing Boilers 23 73 13 Modular Air Handling Units 23 82 16 Air Coils

Division 26

26 05 00 Common Work Results for Electrical 26 05 19 Low Voltage Electrical Power Conductors and Cables 26 05 33 Raceways and Boxes for Electrical Systems 26 05 53 Identifications for Electrical Systems 26 27 26 Wiring Devices 26 28 16 Enclosed Switches and Circuit Breakers 26 29 11 Variable Frequency Controllers (Provided by Div 23 Contractor)

BOST - 232490 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of site.

6. Security

7. Public use of site.

8. Parking & transportation.

9. Occupancy requirements for buildings.

10. Conduct of operations.

11. Work Restrictions.

12. Historic nature of work.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Boston National Historical Park, Charlestown, Massachusetts. Building 22 and Building 28, the USS Constitution Museum.

B. The Work consists of the following:

1. BASE BID: HVAC supplying 1st and 2nd Floor in Building 28.

Remove two existing Air Handling Units (AHU-3 & AHU-4) and one boiler supplying the 1st and 2nd floors of Building 28. Furnish, install and test one new Air Handling Unit (AHU-

3) with two heating coils and two new boilers to supply the first and second floors of Building 28.

2. OPTION A: AHU supplying the Museum lobby in Building 22.

Remove existing DX Air Handling Unit (AHU-9). Furnish, install and test a new DX Air Handling Unit (AHU-9) supplying the Museum lobby space, including modifications to existing ductwork in the lobby.

3. OPTION B: Replace select components of existing AHU-2 in Building 22 Substation.

• Remove existing HW coil and CHW coil and furnish, install and test new replacement coil.

• Remove existing mixing box. Furnish, install and test new mixing box with filter and modify ductwork as indicated.

BOST – 232490 01 11 00 - 2

1.3 GOVERNMENT FURNISHED MATERIALS (NOT USED)

1.4 CONTRACTOR USE OF SITE

A. General: The Museum will remain open for the duration of the contract. Contractor shall have full use of mechanical spaces and chiller area for construction operations during the construction period during normal business hours of the USS Constitution Museum, when Museum staff are present at the site.

B. Storage of Materials: Confine parking, storage areas and field offices to locations as indicated on drawings and as directed by the Contracting Officer. The Government assumes no responsibility for the security of any Contractor equipment, materials, or supplies and such responsibility remains that of the Contractor. Contractor is advised of the spatial limitations of the contractor-use areas and that additional off-site vehicular parking may be required. Storage will not be permitted in existing structures.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

D. Driveways and Entrances: Keep driveways, roadway and entrances serving premises clear and available to Government, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Contractor will use main entrance into Charlestown Navy Yard and park in the designated locations.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Hauling Restrictions: Comply with all legal load restrictions in hauling materials. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1.5 SECURITY

A. The Charlestown Navy Yard is a secure facility. All persons and vehicles entering the yard are subject to search by Navy Security and National Park Service law enforcement personnel. The Contractor shall furnish a list of all personnel and vehicles (including license plate numbers) anticipated to be on site at a minimum of three days prior to the start of work and shall update such list as appropriate during the duration of the work.

B. All Contractor personnel shall have appropriate identification and shall furnish such identification to authorized National Park Service law enforcement personnel upon request. A current driver’s license is required to operate a motor vehicle in the Charlestown Navy Yard.

C. The National Park Service reserves the right to suspend access to the Charlestown Navy Yard in response to changing security levels, special conditions and Government shutdowns.

1.6 PUBLIC USE OF SITE

BOST - 232490 01 11 00 - 3

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

Road closures will not be permitted, without specific approval of Contracting Officer. Road closures are to be scheduled, planned and approved by the Contracting Officer at a minimum of five (5) business days in advance.

1.7 PARKING AND TRANSPORTATION

A. Except for Contractor’s vehicles actively employed in the work, NPS cannot guarantee Contractor’s employee vehicles can be accommodated within the Charlestown Navy Yard. The Contractor is urged to encourage workers to carpool or provide other environmentally responsible modes of transportation to bring workers to the site. Parking shall be in areas designated on the drawings. In no case will overnight parking be permitted. Parked vehicles shall not be left running.

1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).

b. Maintain occupied and common area and facilities clean and presentable for use, including restroom facilities if so allocated.

1.9 CONDUCT OF OPERATIONS

A. At all times the Contractor’s operations shall be conducted in conformance with the rules and regulations promulgated by the National Park Service and the Board of Directors of the USS Constitution Museum.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests for approval to the Contracting Officer two (2) business days in advance of any proposed weekend or holiday work.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

D. All Contractor employees, sub-contractors and work forces shall maintain a professional and respectful mode of behavior and dress at all times on the project site. At all times the Contractor’s personnel shall conduct and present themselves in a manner which is respectful of the museum’s student and family oriented educational environment and programs.

1.10 WORK RESTRICTIONS

BOST – 232490 01 11 00 - 4

A. On-Site Work Hours: Work shall be limited to normal business hours of the USS Constitution Museum when Museum staff are present at the site between 8:00 a.m. and 6:00 p.m., Monday through Friday.

1. The Contractor shall submit to the Contracting Officer two (2) business days in advance a written request for any additional site access beyond normal business hours. No additional site access is permitted without expressed approval in advance by the Contracting Officer.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional cost to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two (2) business days in advance of any proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: All utility shutdowns will be kept to a minimum and performed during hours with the least impact to Museum and Park visitors and operations.

D. Interruptions of Heating and Cooling Systems. Interruption of heating and cooling systems shall be avoided and kept to a minimum to assure a stable environment for Museum collections and for visitor comfort.

1. The Contractor shall indicate on the construction schedule and provide not less than two (2) business days’ advance notice to the Contracting Officer for any anticipated interruption of heating or cooling systems of more than two hours in order to allow Museum Staff to implement interim climate control measures.

2. No interruption of heating or cooling systems for more than two hours is permitted without expressed approval of the Contracting Officer.

E. Perform all on-site operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer

F. Non-Smoking Building: Smoking and vaping are never permitted within any building or within 25 feet of entrances, operable windows, or outdoor air intakes. Other areas of the park may be off-limits to smoking and will be designated by the Contracting Officer.

BOST - 232490 01 11 00 - 5

1.11 HISTORIC NATURE OF THE WORK

A. Buildings 22 and 28 are both contributing resources in the Boston Naval Shipyard National Historic Landmark District. The Contractor shall take all necessary precautions to protect the elements of the buildings not scheduled to receive work. Any damage to such elements shall be repaired by the Contractor at no expense to the Government.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

BOST - 232490 01 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel 12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

BOST - 232490 01 26 01 - 2

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. 8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

8. Personal vehicles i.e. Superintendent Pickup trucks

A. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

B. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1. Social Security

BOST - 232490 01 26 01 - 3

2. Medicare

3. Workers Compensation– Policy and company calculation to be made available.

4. FUTA– Cap Rate and percentage to be proportionally allocated over one year.

4. SUTA– Cap Rate and percentage to be proportionally allocated over one year.

5. Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

C. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

D. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

E. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

F. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://en.wikipedia.org/wiki/Bank http://en.wikipedia.org/wiki/Bank

BOST - 232490 01 26 01 - 4

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form. for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

3. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

4. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.

All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

5. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification. C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS. D.

Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

http://www.nps.gov/dscw/publicforms.htm#ct http://www.nps.gov/dscw/publicforms.htm#ct http://www.nps.gov/dscw/publicforms.htm#ct http://www.nps.gov/dscw/publicforms.htm#ct

BOST - 232490 01 26 01 - 5

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit………………7.5%

BOST - 232490 01 26 01 - 6

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

BOST - 232490 01 27 00 - 7

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No.0001 BASE BID: HVAC supplying 1st and 2nd Floor in Bldg. 28.

Remove two existing Air Handling Units (AHU-3 & AHU-4) and one boiler supplying the 1st and 2nd floors of Building 28. Furnish, install and test one new Air Handling Unit (AHU-3) with two heating coils and two new boilers to supply the first and second floors of Building 28.

1. This item consists of all associated work as required or shown on the contract drawings.

2. Measurement for payment will be agreed upon by the Contractor and a NPS representative.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No.0002 OPTION A: AHU supplying the Museum lobby in Bldg. 22.

Remove existing DX Air Handling Unit (AHU-9). Furnish, install and test a new DX Air Handling Unit (AHU-9) supplying the Museum lobby space, including modifications to existing ductwork in the lobby.

1. This item consists of all associated as required or shown on the contract drawings.

2. Measurement for payment will be agreed upon by the Contractor and a NPS representative.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item No.0003 OPTION B: Replace select components of existing AHU-2 in Bldg. 22 Substation. Replacement of AHU-2 select components (HW Coil, CHW Coil and filter/mixing box) supplying the Museum connector space.

1. This item consists of all associated work as required or shown on the contract drawings.

2. Measurement for payment will be agreed upon by the Contractor and a NPS representative.

3. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

CONTRACT

LINE ITEM

NUMBER

(CLIN)

CONTRACT LINE ITEM (CLI) TITLE QUANTITY

UNIT OF

MEASURE

UNIT PRICE TOTAL PRICE

00010

AHU-3 and AHU-4 shall be removed and be consolidated into one new (AHU-3) air handling unit with two zones two re-heat coils.

1 Lump Sum

00020 OPTION A, (AHU-9 Replacement) 1 Lump Sum

00030 OPTION B, (AHU-2 Component Replacement)

1 Lump Sum

CONTRACT PRICE SCHEDULE

SOLICITATION NUMBER: 140P4320R0004

PARK - PMIS: BOST 232490

DEVELOPED AREA: Charlestown Navy Yard Bldgs. 22 & 28

TOTAL PRICE FOR BASE PLUS ALL OPTIONS (Contract Line Item Numbers 00010 through 00030) ------->>>

Notice: Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items.

Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of summation error, the total corrected amounts govern. Round totals & extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Refer to section “H” of this solicitation for additional information regarding contract options.

TOTAL BASE PRICE (Contract Line Item Number 00010) ---------------------------------------->>>

In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II.

PROJECT TITLE: Mechanical System Upgrades for Charlestown Navy Yard Bldgs. 22 & 28 - USS Constitution Museum

PARK - PMIS

CPS - 1

BOST - 232490 01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. Project meetings.

7. Environmental Coordination.

8. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm

BOST - 232490 01 31 00 - 2

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. As-built drawings (hard copies and AutoCAD)

10. Commissioning activities.

1.4 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. Procurement schedule.

4. A comprehensive breakdown of the Schedule of Values.

5. Accident Prevention Plan.

6. A list of Subcontractors for this project.

7. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

8. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

9. Waste Management Plan.

10. Quality Control Plan.

11. Indoor Air Quality (IAQ) Management Plan.

12. Contractors Commissioning Plan.

BOST - 232490 01 31 00 - 3

B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.

Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in format utilizing the provided format.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

BOST - 232490 01 31 00 - 4

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.6 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Project Schedule.

5. Schedule of Values.

6. Resolution of comments on required Division 01 documents.

7. Coordination of Subcontractors.

8. Labor law application.

9. Modifications.

10. Payments to Contractor.

11. Payroll reports.

12. Contract time.

13. Liquidated damages.

14. Contractor Performance Evaluation.

15. Display of Hotline posters.

16. Notice to proceed.

17. Correspondence procedures.

18. Acceptance/rejection of work.

19. Progress meetings.

20. Submittal procedures.

21. Environmental requirements.

22. Permit requirements.

23. As-constructed drawings/operation and maintenance (O&M) manuals.

24. Saturday, Sunday, holiday and night work.

25. Reference materials.

26. Value engineering.

B. Progress Meetings: The Contracting Officer or designee will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

BOST - 232490 01 31 00 - 5

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Up-to-date project schedule.

d. Review of off-site fabrication and delivery schedules.

e. Requests for information (RFI) and other issues.

f. Modifications.

g. Work in progress and projected.

h. Status of required inspections (Special Inspections, Accessibility, etc.)

i. Inspections of work in progress and projected (Special inspections,

j. Status of Project Record Drawings and O&M manuals.

k. Other business relating to work.

1.7 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan (WMP).

c. Implementation of the Indoor Air Quality (IAQ) Management Plan.

d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

e. Training for Contractor personnel in accordance with their position requirements.

f. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Hazardous Waste Abatement and Management.

4. Indoor Air Quality (IAQ) Management.

5. Construction Waste Management.

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the building industry.

BOST - 232490 01 31 00 - 6

2. Overview of environmental issues related to the Project.

3. Review of site specific procedures and management plans:

a. Construction Waste Management.

b. Indoor Air Quality (IAQ) Management.

c. Hazardous Waste Management.

4. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR employee training records upon request of Contracting Officer.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Hazardous Waste Management Plan.

1.8 PERMITS

A. General:

1. Permits and Responsibilities: The Contractor shall, without additional expense to the

Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occurs as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.

2. For the purpose of this contract the Contractor will not be considered an agent of the Government. Therefore the Contractor will comply with the appropriate Federal, State and local laws.

B. Coordination with Agency(ies) with Jurisdiction Issuing Permits

1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.

C. Administrative Procedures:

1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts and to ensure orderly execution of the Work.

2. Supply all needed information to Agency(ies) with Jurisdiction issuing permits, pay any fees required and provide all material needed to comply with the permit’s conditions and provisions.

3. Supply copies of permits to the CO when the permits are obtained.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

BOST - 232490 01 32 16 - 1

CONSTRUCTION SCHEDULE

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float. E. Float:

The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

BOST - 232490 01 32 16 - 2

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: All schedules and reports submitted shall be provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.

B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.

D. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two paper copies.

1.4 QUALITY ASSURANCE

A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:

1. Review software limitations, content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including work between facilities.

4. Review delivery dates for Government-furnished products.

5. Review time required for review of submittals and re-submittals.

6. Review requirements for tests and inspections by independent testing and inspecting agencies.

7. Review time required for completion and startup procedures.

8. Review time required for obtaining and activating permits.

9. Review and finalize list of construction activities to be included in schedule.

10. Review baseline schedule comments, resolve issues and progress on incorporating them

11. Review procedures for updating schedule.

12. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.

B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the

BOST - 232490 01 32 16 - 3

Construction Schedule. A resume outlining the qualifications of the Scheduler shall be submitted to the Contracting Officer for acceptance. The Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency in the use of scheduling software. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.

2. Secure time commitments for performing critical elements of the Work from parties involved.

3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.

D. An acceptable Schedule of Values shall be agreed upon…

This is the start of the file's text. The full file is on GovTribe.