A05_PWS_Crawford_Cultural_Inventory_2026.pdf

PDF 575 KB Posted

Attached to
CONTRACT ARCHAEOLOGICAL INV. CRAWFORD
Solicitation number
140L1726Q0051
Issued by

About this file

This is a Performance Work Statement (PWS) for a non-personnel services contract to conduct Class III archaeological inventory on Bureau of Land Management lands administered by the Uncompahgre Field Office in Montrose and Crawford Counties, Colorado near the town of Crawford.

The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, and materials necessary to complete an intensive Class III cultural inventory of 967 acres of public land with a 57.5-foot buffer on each side of routes being analyzed. The project aims to identify, record, and evaluate cultural resources for potential eligibility to the National Register of Historic Places, compile cultural and paleontological data for future research, and satisfy Section 106 obligations under the National Historic Preservation Act. The period of performance extends from contract award (expected September 2026) through April 14, 2028. Fieldwork must occur between August 1 and November 30 to minimize impacts on big game, sensitive species, and migratory birds. The survey area encompasses 967 acres total with 402 acres previously inventoried, 15 known sites, 4 known isolated finds, and low to moderate to high site potential across Red Rock Canyon, Black Ridge, Grand View Mesa, Cathedral Peak, and Grizzly Ridge USGS quadrangles.

Contractor-furnished deliverables include: Task I—Pre-filed file search and records/literature review (due 4 weeks after award); Task II—Class III inventory and resource identification including intensive pedestrian surveys at 15-meter transect intervals and recording/evaluation of cultural resources (fieldwork authorization required 5 days prior); Task III—Draft report and site forms with GIS data (due 6 weeks after fieldwork completion); and Task IV—Final report and site forms addressing BLM comments (due 3 weeks after BLM draft review, with 10-day COR final review and 10-day contractor revision period). The contractor must hold or obtain a BLM-Colorado Cultural Resource Use Permit (CRUP) with qualified personnel, maintain a quality control program, and adhere to BLM Colorado Handbook guidelines, BLM-Colorado Digital Data Specifications Guide, and OAHP Colorado Cultural Resource Survey Manual standards. The contract type is Lowest Price Technically Acceptable with 100 percent inspection surveillance for all performance requirements and zero deviation tolerance from standards. No security clearances are required, and the contractor is responsible for safeguarding all government information and materials. Key personnel include a contract manager available 8:00 a.m. to 4:30 p.m. Monday through Friday, a qualified crew chief or field director on-site at all times during fieldwork, and field crew personnel.

View the file

Other files

File Type Posted
Sol_140L1726Q0051.pdf PDF
A06_SHAPE_Cultural_Inventory_967_Acres.zip ZIP file
B03_2015-5435_REV_31.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

UNCOMPAHGRE FIELD OFFICE CULTURAL RESOURCES INVENTORY IN

GUNNISON SAGE GROUSE HABITAT, MONTROSE AND CRAWFORD COUNTIES,

COLORADO

PART 1: GENERAL INFORMATION

1. General

This is a non-personnel services contract to provide Class III archaeological inventory. The

Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Description of Services

The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform Class III archaeological inventory as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.

Complete an intensive Class III cultural inventory of public land administered by the Bureau of

Land Management Land, Uncompahgre Field Office in Montrose and Delta counties, near the town of Crawford, Colorado. The area of survey for this project will be defined as the routes being analyzed, with a 57.5 foot buffer on each side (115 foot wide) which will result in 967 acres of area for survey.

The intent of this archeological inventory is to identify, record, and evaluate cultural resources for their potential eligibility to the National Register of Historic Places to aid the BLM in resource management, compile cultural and paleontological data for future research, and to satisfy the BLM’s obligations to Section 106 of the National Historic Preservation Act.

Most of the roads were never formally aligned in ways beneficial to the landscape. As a result, most of the roads are poorly drained and intercept considerable water as they travel perpendicular to the natural contours on the landscape. Very little maintenance has ever been conducted on the roads. The roads have incised into the landscape and are drying the surrounding landscape by moving water efficiently off the landscape rather than giving it a chance to infiltrate deep into the soil profile. Habitat for Gunnison sage-grouse would be enhanced by providing cultural inventory for roads which would enable BLM to install rolling dips and lead out ditches on existing roads and reconnect water directly back to sagebrush habitats, increasing overall vigor of grass, forbs and sagebrush within Gunnison sage-grouse nesting habitat.

This performance work statement is for archaeological inventory to identify, record and evaluate cultural resources for their potential eligibility to the National Register of Historic Places to aid the BLM in resource management. Following the completion of field work the results will be prepared in draft and final report documents that include data synthesis of all cultural resources and analysis within the project area.

1.2 Objectives

• The intent of this archeological inventory is to determine potential eligibility to the

National Register of Historic Places by identifying, recording and evaluating cultural resource.

• Compile cultural and paleontological data for future research.

• Satisfy the BLM’s obligations to Section 106 of the National Historic Preservation Act.

• The results will be prepared in draft and final report documents that include data synthesis of all cultural resources and analysis within the project area.

1.3 Scope - Class III cultural inventory.

Services include: Class III cultural inventory on the routes identified with a 57.5 foot buffer on each side and the total acres surveyed will be 967 acres. The contractor shall accomplish: pre-filed file search and records/literature review, an inventory and resource identification, draft report and site forms and a final report and site forms.

AREA OF

SURVEY TOTAL

967 Acres

PREVIOUS

INVENTORIES IN

THE VICINITY

402 Acres

Known Sites 15

Known Isolated

Finds

Site Potential Low/Moderate/High

USGS QUADS Red Rock Canyon, Black Ridge, Grand

View Mesa, Cathedral

Peak Grizzly Ridge

1.4 Period of Performance

The period of performance shall be from when the contract is awarded (expected in September

2026) through April 14, 2028.

1.5 General Information

1.5.1 Quality Control

The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. The QCP will be delivered within 30 days after contract award. After acceptance of the quality control plan the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system. Quality

Assurance

The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the

Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.5.2 Quality Assurance

The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the

Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.5.3 Recognized Holidays

The contractor is not required to work on holidays.

New Year’s Day Labor Day

Martin Luther King Jr.’s Birthday Columbus Day

President’s Day Veteran’s Day

Memorial Day Thanksgiving Day

Independence Day Christmas Day

Juneteenth National Independence Day

1.5.4 Hours of Operation

The contractor is not responsible for conducting business during specific hours as work is occurring at the contractor’s facilities.

1.5.5 Place of Performance

The work to be performed under this contract will be performed on BLM lands for field survey and at contractor facilities. BLM facilities or offices will not be utilized by the contractor as part of this contract.

1.5.6 Type of Contract

The government will award a Lowest Price Technically Acceptable contract.

1.5.7 Security Requirements

No security clearances are required as this contract is executed at the contractor’s facility.

1.5.8 Physical Security

The contractor shall be responsible for safeguarding all government, information provided for contractor use. No government facilities or equipment will be provided. At the close of each work period materials shall be secured.

1.6 Special Qualifications

The Contractor and any subcontractors must currently hold, or be able to obtain, a BLM-CO

Cultural Resource Use Permit (CRUP), and the work must be conducted by personnel under that permit qualified to work on the Uncompahgre Field Office. All CRUP permit stipulations will be followed.

1.6.1 Special Requirements

To minimize impacts on big game, sensitive species, and migratory birds, on the ground work

(i.e. field work) will occur between August 1 to November 30.

Activities shall not be performed during periods when the soil is too wet to adequately support vehicles. If vehicles create ruts more than 4 inches deep, activities must cease as the soil will be deemed too wet to adequately support vehicles.

1.7 Post Award Conference/Periodic Progress Meetings

T he Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart

42.5. The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.8 Contracting Officer Representative (COR)

The (COR) will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and

Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.9 Key Personnel

The follow personnel are considered key personnel by the government: The follow personnel are considered key personnel by the government:

• Contract Manager

• Crew chief or field director

• Field crew

The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between

8:00 a.m to 4:30 p.m. Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons. Qualifications for all key personnel are listed below:

Each field crew must be supervised in the field by a qualified crew chief and/or field director listed on the Cultural Resource Use Permit (CRUP). A crew chief or field director must always be on-site. The Contractor and any subcontractors must currently hold, or be able to obtain, a

BLM-CO Cultural Resource Use Permit (CRUP).

1.9.1 Identification of Contractor Employees

All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

1.10 Contractor Travel

Contractor will be required to travel to the field site to complete the Class III intensive cultural inventory. This is part of the overall contract and not separate.

1.11 Data Rights

The Government has unlimited rights to all documents/material produced under this contract.

All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the

Contracting Officer. All materials supplied to the Government shall be the sole property of the

Government and may not be used for any other purpose. This right does not abrogate any other

Government rights.

1.11.1 Organizational Conflict of Interest

Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational

Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the

Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting

Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the

Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may effect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

PART 2: DEFINITIONS AND ACRONYMS

2. Definitions and Acronyms

2.1 Definitions

2.1.1 Class III Inventory

Professionally conducted, continuous, intensive pedestrian surveys of an entire target area

(100%). The goal is locating and locating and recording all cultural resource properties that have surface and exposed-profile indications, through systematic inspection carried out by a crew of trained observers walking a series of parallel transects until the area has been thoroughly examined. Crew spacing should not be wider than 15-20 meters apart. Intensive inventory describes the distribution of properties in an area; determines the number, location and condition of properties; determines the types of properties actually present within the area; permits classification of individual properties; and records the physical extent of specific properties.

2.1.2 Contractor

A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.3 Contracting Officer

A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.4 Contracting Officer’s Representative (COR)

An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.5 Cultural Resource

Any definite location of past human activity, occupation, or use, identifiable through field inventory (survey), historical documentation, or oral evidence. This term may be applied to archaeological, historic, or architectural sites, structures or places, or places of traditional cultural or religious importance to specified social and/or cultural groups, whether or not represented by physical remains.

2.1.6 Defective Service

A service output that does not meet the standard of performance associated with the Performance

Work Statement.

2.1.7 Deliverable

Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.8 Historic Property

Any prehistoric or historic district, site, building, structure, or object included in, or eligible for inclusion in the NRHP. The term includes, but is not limited to, artifacts, records, and remains that are related to and located within such properties. The phrase “eligible for inclusion in the

NRHP” includes both properties formally determined as such by the Secretary of the Interior and all other properties that meet National Register listing criteria and those sites already identified as eligible during consultation between the BLM and the Colorado SHPO.

2.1.9 Key Personnel

Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.10 Physical Security

Actions that prevent the loss or damage of Government property.

2.1.11 Quality Assurance

The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.12 Quality Assurance Surveillance Plan (QASP)

An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.13 Quality Control

All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.14 Subcontractor

One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.15 Undertaking

Actions assisted, licensed, permitted, approved, funded, or authorized by BLM, as defined in the

Code of Federal Regulations [36 CFR 800.2(o)]. Undertakings for which BLM is considered the lead agent, whether or not they involve federal lands, are federal actions.

2.1.16 Workday

The number of hours per day the Contractor provides services in accordance with the contract.

2.1.17 Work Week

Monday through Friday, unless specified otherwise.

2.2 Acronyms

ACOR Alternate Contracting Officer's Representative

BLM Bureau of Land Management

CFR Code of Federal Regulations

CO Contracting Officer

CONUS Continental United States (excludes Alaska and Hawaii)

COR Contracting Officer Representative

COTR Contracting Officer's Technical Representative

COTS Commercial-Off-the-Shelf

DIAR Department of the Interior Acquisition Regulation

DOI Department of the Interior

FAR Federal Acquisition Regulation

HIPAA Health Insurance Portability and Accountability Act of 1996

OCI Organizational Conflict of Interest

OCONUS Outside Continental United States (includes Alaska and Hawaii)

ODC Other Direct Costs

PIPO Phase In/Phase Out

POC Point of Contact

PRS Performance Requirements Summary

PWS Performance Work Statement

QA Quality Assurance

QAP Quality Assurance Program

QASP Quality Assurance Surveillance Plan

QC Quality Control

QCP Quality Control Program

TE Technical Exhibit

PART 3: GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. Government Furnished Items and Services

3.1 Services, Facilities, Utilities, Equipment

The Government will not provide any services, facilities, utilities, or equipment.

3.2 Materials

The Uncompahgre Field Office archaeologist will assist with the field office portion of the records search and will provide cultural files to the contractor.

Travel Route Assessment form is to be used, in lieu of OAHP revisit form, to document site condition and to note any travel related impacts (e.g., Appendix 7 of the Travel Management

Plans Programmatic Agreement between BLM Colorado, the Colorado State Historic

Preservation Office SHPO, and the Advisory Council on Historic Preservation). The BLM will provide a copy of the form prior to fieldwork.

PART 4: CONTRACTOR FURNISHED ITEMS AND SERVICES

4. Contractor Furnished Items and Services

4.1 Supplies, Equipment, Facilities, and Services

The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.

PART 5: SPECIFIC TASKS

5. Specific Tasks

5.1 Basic Services

The contractor shall provide services for Class III Cultural Inventory.

5.2 Task I: Pre-Filed File Search, Records/Literature Review

Due 4 weeks after contract award

Task I consists of completing a file search overview with a synthesis of data for known historic, ethnographic and archeological data that encompass the project area, and the area within one mile of the project boundary. This research is necessary to identify and compile all available known cultural data previously recorded and inventoried areas that includes recorded resources, isolates, and potential unrecorded resources to develop an interpretive narrative overview for understanding and writing the Literature Review of the project area.

Prior to starting fieldwork, the consultants must complete a records search of both the OAHP database, the UFO cultural resource files, and a review of the GLO historic maps. GLO historic maps are expected to be accessed online. The UFO archaeologist will assist with the field office portion of the records search.

Available existing cultural resource data shall include, but not limited to, Uncompahgre Field

Office cultural resource inventory records, Colorado State Institutional Archives, Repositories, listed properties in the State Historic Sites Inventory, National American Engineering Records, and Historic American Buildings Survey records, appropriate historic contexts, and the Colorado

Office of Archaeology and Historic Preservation COMPASS cultural resource database. Other available sources of information may be obtained from, and not limited to, State and National

Registers, published and unpublished manuscripts, aerial photographs, General Land Office maps, Mining Ledgers, historical photographs, Museums and library reference material. Data gathered will then be used to develop a Literature Review overview of the project area for prehistoric, historic and potential traditional cultural properties (TCP’s). At the time of submitting this contract, no TCP’s in the project area have been identified by tribes during consultation.

After completion of the file search and Literature Review, the results will need to disseminate the gathered data within summarized tables, maps, photographs, narrative, or other informative formats. The Literature Review will consider explicit types of resources that might be encountered, and potential research questions based on prehistory, historic and ethnology of these areas, and surrounding region. All discussions will need to be accurately identified and referenced in the bibliography.

Previously recorded resources within one mile shall be presented in a table format. All sites shall be listed with their state trinomial number, site type, date recorded and the previous evaluation status of eligible, not eligible, or unevaluated/needs data to the National Register, and the report reference. Isolated finds and non-eligible resource data may remain in table format. National

Register eligible resources, and unevaluated resources, within and immediately adjacent to the

APE shall be further described in brief narrative detail as discussion points in support of the

Literature Review and anticipated inventory expectations.

A draft of this Literature Review shall be submitted to the COR prior to the issuance of a fieldwork authorization form. After review, the COR may suggest additional comments or directives to ensure a comprehensive overview and developed Literature Review.

5.3 Task II: Inventory and Resource Identification

5.3.1 Task II-A: Class III Inventory

Task II consists of completion of a Class III inventory, an intensive level cultural resource inventory within the specified survey area to locate and record new sites and isolated finds and previously recorded sites.

Fieldwork authorization: A fieldwork authorization must be submitted to the COR at least 5 days prior to start of fieldwork. It can be submitted via email (preferred) or can be submitted at the same time as the file search is conducted in the UFO.

The task will be conducted under the provisions of the BLM Colorado Cultural Resource Use

Permit and will conform to guidelines contained in the most current versions of the BLM

Colorado Handbook of Guidelines and Procedures for Inventory, Evaluation, and Mitigation of

Cultural Resources, the BLM-Colorado Digital Data Specifications Guide, the requirements in this statement of work, and the OAHP Colorado Cultural Resource Survey Manual.

The Contractor must locate the boundaries of the survey areas prior to commencement of the survey. Use of GPS units, benchmarks, 7.5 minute topographic maps, aerial photographs (where available), roadways and other landscape features, if needed, is required to ensure ground control and confidence in the inventory area and in the location of cultural resources.

An intensive pedestrian survey at transect intervals not exceeding 15 meters within the block survey areas will be conducted to identify and record all cultural resources. Actual ground examination should result in the identification and recording of all cultural resources observable on the surface and in exposed subsurface profiles.

Each field crew must be supervised in the field by a qualified crew chief and/or field director listed on the CRUP. A crew chief or field director must be on-site at all times.

The Contractor must notify the Contract Officer’s Representative (COR) or Project Inspector by telephone and with written confirmation immediately upon the discovery of human remains, funerary objects, sacred objects, or objects of cultural patrimony (as defined in 43 CFR 10.2) and must immediately stop any activities connected with such discovery and make a reasonable effort to protect the discovered remains or objects.

5.3.2 Task II-B: Recording and Evaluation of Cultural Resources

The Contractor must record each cultural resource identified following the BLM Colorado

Handbook of Guidelines and Procedures for Inventory, Evaluation, and Mitigation of Cultural

Resources, the BLM-Colorado Digital Data Specifications Guide, the requirements in this performance work statement, and the OAHP Colorado Cultural Resource Survey Manual.

The NRHP evaluations will be completed for all previously recorded sites. Care will be taken in coordinating the site numbers when previously recorded sites are re-located to assure that the correct site number are used since they may have associated curated collections. Original site numbers for these sites will be retained as much as possible even though expanded recording may reveal a much larger site area than originally documented.

When re-mapping previously recorded sites, new maps should build off of earlier site maps.

Feature and structure numbers from earlier maps should be carried forward to the new map. New features or structures will be numbered to follow the last number.

The full extent of sites will be intensively recorded, even if sites extend outside the survey area

(record portions of sites outside survey areas).

To refine or complete National Register eligibility recommendations, evaluative testing (soil probing, trowel testing, auger testing, or shovel testing) will be conducted at all sites where the contractor is unable to determine site eligibility based on surface evidence. This evaluative testing during field recording should be used to determine the potential for subsurface cultural deposits and the site boundary, as needed. Evaluative testing should not exceed three (3) square meters of site surface. Testing locations should also be shown on the site map. The level of testing should not be conducted in a manner that impacts or destroys information that contributes to the sites eligibility. Criteria used to determine properties potentially eligible for the NRHP must be substantive, objective, and stated in the report.

Potentially eligible sites will be tested to determine site depth potential, integrity and eligibility wherever possible. The “Need Data” determination should be applied sparingly and only in those cases where both surface evidence and limited testing yield ambiguous results. Previous determinations of “Need Data” will be resolved.

Scaled site maps will include detailed drawings of site features, structures, locations of diagnostic artifacts, artifact concentrations, boundary, topography of the site area, as well as nearby developments or distinctive landforms (roads, power lines, well pads, canyon rims, etc.).

Locations of disturbance and the nature of disturbance will be indicated on the site map. The location of the site tag will be indicated on the site map. Any mapped item not specifically described in the map key will be individually labeled on the map.

A current assessment of site condition will be made for each site in terms of impacts from natural processes (erosion), human processes (looting/vandalism, commercial development, recreational use-motorized or other, chaining), or livestock impacts, as per OAHP management data form items 33, 34, and 35.

A GPS unit will be used to record precise site boundaries and isolated find centroids. See BLM-

Colorado Digital Data Specifications Guide (revised 9/2015).

High quality digital images (300 dpi or highest resolution setting) will be taken for use with the site forms. One site overview photo is required. Photos will be taken for unusual or diagnostic isolated finds.

Artifact collection is not authorized, however if the contractor determines artifact collection is necessary the COR is to be contacted and will collect the artifact on behalf of the consultant if deemed warranted. In-field ceramic and lithic analysis necessary to determine site function and chronology will be completed using current standard published typologies (see below).

Lithic materials will be identified to include the material type, the debitage type (core, primary, secondary, tertiary, angular debris), or the tool type. Diagnostic projectile points will be drawn and photographed and included with the site documentation. Chapter 8 of the “Crow Canyon

Archaeological Center Laboratory Manual, Version 1,” (Ortman et al 2005) is a recommended reference for material type identification.

5.4 Task III: Draft Report and Site Forms

Task III: Draft Report and Site Forms

Due 6 seeks after completion of field work.

A single digital copy of the draft report, site, isolated find, and BLM travel route assessment forms will be submitted to the COR. The report, site, and isolated find forms must include the

BLM and SHPO report numbers The BLM will provide the BLM project number. OAHP project and site number must be obtain directly from directly from OAHP using the new templates.

https://sites.google.com/state.co.us/oahp-resource-center/forms-guidance/requesting-numbers

The draft final report will include a detailed description and evaluation of all sites visited during the survey, recommendations on National Register eligibility, a discussion of site impacts observed, and site management recommendations. The evaluations should be made in the context of previous investigations and findings in the general area, and research questions for the region.

All sites brought forward as “Need Data” will include a detailed discussion of how field testing was conducted and why field testing was inconclusive and specific recommendations for additional evaluative testing to determine eligibility. The site management recommendations must take into account the current site condition based on disturbances observed while conducting the field work.

Sites will be displayed on maps as polygons (site boundaries rather than site centroids). Site maps will include the following citation: Disclosure of site locations prohibited (43 CFR 7.18).

All site forms, including site revisit forms, must have at a minimum of one photograph showing the general site location with a horizon.

Cultural resources will be recorded on the appropriate OAHP forms, following OAHP form instruction and guidance. The Contractor shall use the latest updates of the form available at the time of report preparation.

Sites documented prior to 2000 will be completely re-recorded on Colorado OAHP component forms. Sites recorded after 2000 can be documented on an OAHP revisit form as long as no significant changes to the site are observed.

An OAHP revisit form will be completed for previously recorded sites that cannot be relocated, for documentation purposes.

A UFO travel route assessment form will be completed for each site in the survey areas (both newly and previously recorded). A Travel Route Assessment form is to be used, in lieu of OAHP revisit form, to document site condition and to note any travel related impacts (e.g., Appendix 7 of the Travel Management Plans PA between BLM CO, the CO SHPO, and the ACHP). The

BLM will provide a copy of the form prior to fieldwork.

Site, isolated find, and survey GIS data (shapefiles) that meet the current BLM-Colorado Digital

Data Specifications Guide will be submitted via shared drive.

BLM Review of Draft Report

Due 3 weeks after receipt of draft report, the BLM will submit a review of the draft report with comments and/or corrections to the contractor, which must be addressed in the final report.

5.5 Task IV: Final Report and Site Forms

Due 3 weeks after receipt of BLM draft report comments.

Task IV consists of writing the draft report, GIS data and draft attachments. This task consists of data synthesis of the results from previous Tasks to develop the Final Report. The report will reflect all fieldwork results accomplished during this contract and should require minimal editing to produce the Final Report. OAHP site forms, figures and maps are referred to as attachments and should also be in a draft state that requires minimal editing before the final attachments are delivered.

One hard copy of the final report, site, and isolated find forms addressing all changes and corrections identified from the draft report review will be submitted to the PI. Digital copies of the final report, site and isolated find forms, BLM travel route assessment form, photos, and shapefiles of site, isolated find, and survey area locations that meet the current BLM-Colorado

Digital Data Specifications Guide will also be submitted to the COR via a shared drive. Hard copy site forms are to be separate from the report (do not bind the report and site forms together).

The BLM retains ownership of, and all rights to, all artifacts collected, records, data, maps, drawings, photographs, samples, artifacts, GIS products, automated data bases, or other products.

These items cannot be used by the Contractor without written permission from the BLM.

5.5.1 BLM Final Report Review

Due 10 days after receipt of final report.

Upon receipt of the final report the COR shall have 10 calendar days to review the final report for acceptance or resubmission. If any revisions are needed, the contractor will have 10 calendar days from submission of final comments to resubmit the final report.

PART 6: APPLICABLE PUBLICATIONS

6. Applicable Publications (Current Editions)

6.1 General

The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures. Additional requirements include:

• BLM-Colorado Digital Data Specifications Guide (revised 9/2015).

• Appendix 7 of the Travel Management Plans PA between BLM CO, the Colorado State

Historic Preservation Office, and the Advisory Council on Historic Preservation.

• Office of Archaeology and Historic Preservation. Standards and templates:

https://sites.google.com/state.co.us/oahp-resource-center/forms-guidance/requesting-numbers

PART 7: TECHNICAL EXHIBIT LIST

7. Attachment/Technical Exhibit List

Technical Exhibit 1 – Performance Requirements Summary

Technical Exhibit 2 – Deliverables Schedule

Technical Exhibit 3 - Map of project area

TECHNICAL EXHIBIT 1: PERFORMANCE REQUIREMENTS SUMMARY

The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance

Objective

Standard Performance

Threshold

Method of

Surveillance

PRS # 1. The contractor shall provide Task I: Pre-filed File search, Records/Literature review (5.2)

The contractor provided a complete records search of both the OAHP database, the UFO cultural resource files, and a review of the GLO historic maps. After completion of the file search and Literature Review, the results will need to disseminate the gathered data within summarized tables, maps, photographs, narrative, or other informative formats.

Previously recorded resources within one mile shall be presented in a table format. All sites shall be listed with their state trinomial number, site type, date recorded and the previous evaluation status of eligible, not eligible, or unevaluated/needs data to the National Register, and the report reference. Isolated finds and non-eligible resource data may remain in table format.

National Register eligible resources, and unevaluated resources, within and immediately adjacent to the APE shall be further described in brief narrative detail as discussion points in support of the Literature Review and anticipated inventory expectations.

A draft of this Literature Review shall be submitted to the COR prior to the issuance of a fieldwork authorization form. After review, the

COR may suggest additional comments or directives to ensure a comprehensive overview and developed Literature Review.

Zero deviation from the standard.

100 Percent

Inspection:

Inspect and evaluate performance each time task is performed.

PRS # 2. The provide Task II-A:

Class III Inventory

(5.3.1)

Completion of a Class III inventory, an intensive level cultural resource inventory within the specified survey area to locate and record new sites and isolated finds and previously recorded sites The task will be conducted under the provisions of the BLM Colorado Cultural

Resource Use Permit and will conform to guidelines contained in the most current versions standard.

100 Percent

Inspection:

Inspect and evaluate performance is performed.

of the BLM Colorado Handbook of Guidelines and Procedures for Inventory, Evaluation, and

Mitigation of Cultural Resources, the BLM-

Colorado Digital Data Specifications Guide, the requirements in this statement of work, and the

OAHP Colorado Cultural Resource Survey

Manual.

PRS # 3. The contractor shall provide Task II-B:

Recording and

Evaluation of

Cultural Resources

(5.3.2)

The Contractor must record each cultural resource identified following the BLM Colorado

Handbook of Guidelines and Procedures for

Inventory, Evaluation, and Mitigation of Cultural

Resources, the BLM-Colorado Digital Data

Specifications Guide, the requirements in this performance work statement, and the OAHP

Colorado Cultural Resource Survey Manual. The

NRHP evaluations will be completed for all previously recorded sites. Care will be taken in coordinating the site numbers when previously recorded sites are re-located to assure that the correct site number are used since they may have associated curated collections. Original site numbers for these sites will be retained as much as possible even though expanded recording may reveal a much larger site area than originally documented.

When re-mapping previously recorded sites, new maps should build off of earlier site maps.

Feature and structure numbers from earlier maps should be carried forward to the new map. New features or structures will be numbered to follow the last number.

standard

100 Percent

Inspection:

Inspect and evaluate performance each time task is performed.

PRS # 4. The contractor shall provide Task III:

Draft Report and

Site Forms (5.4)

A single digital copy of the draft report, site, isolated find, and BLM travel route assessment forms will be submitted to the COR. The report, site, and isolated find forms must include the

BLM and SHPO report numbers The BLM will provide the BLM project number. OAHP project and site number must be obtain directly from directly from OAHP using the new templates.

Inspect and evaluate performance each time task is performed

PRS # 5 The contractor shall provide 5.5 Task IV:

Final Report and

Site Forms (5.5).

Task IV consists of writing the draft report, GIS data and draft attachments. This task consists of data synthesis of the results from previous Tasks to develop the Final Report. The report will reflect all fieldwork results accomplished during this contract and should require minimal editing

Inspect and evaluate performance is performed to produce the Final Report. OAHP site forms, figures and maps are referred to as attachments and should also be in a draft state that requires minimal editing before the final attachments are delivered.

PRS #6 The provide Task IV:

Revisions to Final

Report (5.5.1).

Upon receipt of the final report the COR shall have 10 calendar days to review the final report for acceptance or resubmission. If any revisions are needed, the contractor will have 10 calendar days from submission of final comments to resubmit the final report.

TECHNICAL EXHIBIT 2: DELIVERABLES SCHEDULE

Deliverable Frequency # of Copies Medium/Format Submit To

5.2 Task I: Pre-Filed

File Search, Records/Literature

Review

Due once – 4 weeks after contract award

One draft of this

Literature Review shall be submitted to the COR prior to the issuance of a fieldwork authorization form. After review, the

COR may suggest additional comments or directives to ensure a comprehensive overview and developed Literature

Review.

By email to the COR

COR – Angela

Losasso alosasso@blm.gov

Fieldwork authorization request

Due once – 5 days prior to the start of fieldwork or can be submitted at the same time as

5.2 Task I.

One request shall be submitted to the COR

By email to the COR

COR – Angela

Losasso alosasso@blm.gov

5.3 Task II:

Inventory and

Resource

Identification

1.6.1 Special

Requirements:

To minimize impacts on big game, sensitive species, and migratory birds, on the ground work (i.e. field work) will occur between August

1 to November

Not Applicable Not Applicable Not Applicable

5.4 Task III: Draft

Report and Site

Forms

Due once – 6 weeks after completion of fieldwork

One digital copy of the draft report, site, isolated find, and BLM travel route assessment

By email to the COR

Site, isolated find, and survey GIS data

(shapefiles) that meet the current

BLM-Colorado

Digital Data

Specifications Guide

COR – Angela

Losasso alosasso@blm.gov

Share drive link

TBD

mailto:alosasso@blm.gov mailto:alosasso@blm.gov

Deliverable Frequency # of Copies Medium/Format Submit To will be submitted via shared drive to the

COR.

5.5 Task IV: Final

Report and Site

Forms

Due once – three weeks after receipt of

BLM’s review of draft report.

One digital copy of the final report, site and isolated find forms, BLM travel route assessment form, photos, and shapefiles of site, isolated find, and survey area locations that meet the current BLM-

Colorado Digital Data

Specifications Guide

Digital copies of the final report, site and isolated find forms, BLM travel route assessment form, photos, and shapefiles of site, isolated find, and survey area locations that meet the current

BLM-Colorado

Digital Data

Specifications Guide will be submitted via a shared drive.

COR – Angela

Share drive link

TBD

5.5.1 Task IV:

Revisions to Final

Report

Due once – 10 days after final

BLM review and request for additional changes

One hard copy of the final report, site, and isolated find forms. Hard copy site forms are to be separate from the report

(do not bind the report and site forms together).

One digital copies of the final report, site and isolated find forms, BLM travel route assessment form, photos, and shapefiles of site, isolated find, and survey area locations that meet the current BLM-

Colorado Digital Data

Specifications Guide.

Hard copies to COR by US Postal Mail.

Digital copies of the final report, site and isolated find forms, BLM travel route assessment form, photos, and shapefiles of site, isolated find, and survey area locations that meet the current

BLM-Colorado

Digital Data

Specifications Guide will be submitted via a shared drive.

COR – Angela

Hard Copy

Montrose Public

Lands Center

2465 South

Townsend Avenue

Montrose, CO 81401

Digital copy by email:

alosasso@blm.gov

TECHNICAL EXHIBIT 3: MAP OF PROJECT AREA

File details come from the government source that posted it. Updated .