About this file
This document outlines the requirements for wastewater pumping services at Lassen Volcanic National Park. The contractor will be responsible for pumping an estimated 85,000 gallons of wastewater from over 50 septic tanks and vault toilets located throughout the park between January 1, 2024 and December 31, 2024. Tanks range in size from 1,200 to 16,000 gallons. The wastewater must be hauled to an approved disposal site outside the park boundaries. The contractor must respond within three days when notified that a tank needs servicing. Notification will come from specified park contacts. The contract includes four optional one-year extensions through December 31, 2028. The related federal contract opportunity is solicitation number 140P8424Q0003 for wastewater pumping services at Lassen Volcanic National Park issued by the National Park Service of the Department of the Interior.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amended_Provisions_and_Clauses_140P8424Q0003_0001.docx | DOCX document | |
| Sol_140P8424Q0003_Amd_0001.pdf | ||
| Amendments_Questions_and_Answers_140P8423Q0003_LAVO_Wastewater_Pump_0001.docx | DOCX document | |
| B08_Attachment_4_140P8423Q0003_52_212-3_Full_Text_(Sep_2023).pdf | ||
| B03_Wage_Determination_Tehama_County_LAVO_Wastewater.pdf | ||
| B03_Wage_Determination_Plumas_County_LAVO_Wastewater.pdf | ||
| Sol_140P8424Q0003.pdf | ||
| B08_Solicitation_ATT_1_140P8424Q0003_Quote_Sheet.pdf | ||
| B08_Solicitation_ATT_5_Tech_Info_Form_140P8423Q0003.pdf | ||
| B03_Wage_Determination_Lassen_County_LAVO_Wastewater.pdf | ||
| B03_Wage_Determination_Shasta_County_LAVO_Wastewater.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Lassen Volcanic National Park
Wastewater Pumping
Solicitation # 140P8424Q0003
LASSEN VOLCANIC NATIONAL PARK (LAVO)
WASTEWATER PUMPING SPECIFICATIONS 2024
1) The estimated volume of wastewater to be pumped during contract period January 1, 2024, to December 31, 2024, is 85,000 gallons. Gallons to be pumped vary, depending on usage and the length of the summer season.
2) The base 2024 contract period will start on January 1, 2024, and terminate on December
31, 2024. An option for 4 additional contract years is included. Each option year if exercised will begin on January 1st and end on December 31st of each subsequent year.
3) Septic tanks and vault toilets are located throughout Lassen Volcanic National Park (See exhibit 1, map). There are upward of 50 tanks within the park (See exhibit 2, table).
Tanks range in size from 1,200-gallon vaults to 16,000-gallon septic tanks (vaults have been counted as one tank though there are two compartments).
4) Wastewater must be hauled to a state-approved waste disposal site outside of Lassen
Volcanic National Park. The contractor is responsible for the arrangement and disposal of all waste.
5) Contractor vehicles and all equipment must be free of leaks and in safe operating condition. Contractor is responsible for the complete cleanup of all spills or leaks within
Lassen Volcanic National Park. Contractor vehicles must be free of any non-indigenous vegetative material.
6) The first pumping is estimated to start January 1, 2024, through December 31, 2024.
However, additional pumping will be assessed on an as needed basis throughout the year.
Contractor will be contacted when vaults fill to within 18” of the top of tank, or if a tank is in need of servicing (Heavy sludge layer).
7) Lassen Volcanic National Park will notify the contractor of the vaults and or septic tanks to be pumped. This will include the order of priority as well as dates of desired pumping.
A minimum response time of three (3) days is required. Notification of pumping will only be made by Merita Kimball, Robert Morris or the Chief of Maintenance.
8) Lassen Volcanic National Park must be notified if the contractor is called out on emergency service for an extended period of time i.e.: wildfire. The Park must be notified with as much lead time as feasible in order to make alternative arrangements with a qualified contractor.
9) Option years:
a. January 1, 2025, to December 31, 2025
b. January 1, 2026, to December 31, 2026
c. January 1, 2027, to December 31, 2027
d. January 1, 2028, to December 31, 2028
Exhibit 1 Map
Exhibit 2 Table – List of LAVO Septic and Vault Tanks
LOCATION TYPE EACH SIZE GAL. EA.
HEADQUARTERS SEPTIC 1 1,500
" VAULT 1 1,200
SOUTHWEST (Visitor Ctr) SEPTIC 1 12,400
" DOSING 1 2,400
KINGS CR. PICNIC AREA VAULT
VAULT
1,500
1,200
SUMMIT LAKE HORSE
CORRAL
VAULT 1 1,200
BUMPASS TRAILHEAD VAULT 2 1,200
PEAK PARKING LOT VAULT 2
1,200
SOUTH SUMMIT LAKE
VAULT
NORTH SUMMIT LAKE SEPTIC
VAULT
2,400
1,200
SUMMIT LAKE RANGER STA. SEPTIC
VAULT
1,500
1,200
DEVASTATED PARKING LOT VAULT 1 1,200
LOST CREEK CAMPGROUND VAULT 5 1,200
CRAGS CAMPGROUND VAULT 5 1,200
MANZANITA LAKE
CAMPGROUND
SEPTIC
SEPTIC
16,000
16,000
" SEPTIC 1 2,400
LOCATION TYPE EACH SIZE GAL. EA.
" VAULT 2 1,200
MANZ. LAKE HOUSING AREA SEPTIC 1 10,000
CROSSROADS SEPTIC 1 2,000
BUTTE LAKE CAMPGROUND SEPTIC
VAULT
4,000
1,200
JUNIPER LAKE VAULT
VAULT
SEPTIC
1,500
1,200
1,250
LAKE HELEN PICNIC AREA
WARNER VALLEY CAMP.
AND TRAILHEAD
WARNER VALLEY RANGER ST. SEPTIC
1,500
DRAKESBAD GUEST RANCH
SEPTIC
GREASE
10,000
3,000
Merita Kimball COR
Lassen Volcanic National Park
530-595-6235
Cell – 530-276-7957
File details come from the government source that posted it. Updated .