Scope of Work Summary
This is a Scope of Work document for a federal construction project by the U.S. Fish and Wildlife Service (USFWS) at Flint Hills National Wildlife Refuge Headquarters in Hartford, Kansas.
The project involves constructing a reinforced concrete parking lot measuring 75 feet by 39.5 feet by 6 inches thick, along with ADA-compliant sidewalks totaling approximately 121.5 linear feet in multiple sections (81.5'x6', 30'x6', and 10'x10.5'). Work includes subgrade preparation with excavation, compaction, and moisture conditioning; aggregate base installation; concrete finishing, edging, curing, and jointing; parking lot striping and signage; ADA curb ramps with compliant slopes; removal of existing pavement; and site restoration with grading, topsoil, and seeding. Technical specifications require concrete strength of minimum 4,000 psi, air content of 6½ ±1½%, reinforcement via rebar or welded wire mesh, and liquid membrane-forming curing compound applied per manufacturer recommendations. All testing and compaction must meet ASTM standards.
The contractor must complete all work within 240 calendar days from Notice to Proceed. Required submittals include concrete mix design, work schedule, traffic control plan, material certifications, testing plan, disposal plan, and site-specific safety plan. The contractor is responsible for following OSHA and federal regulations, maintaining a safe worksite, coordinating inspections with the Contracting Officer's Representative (COR), protecting utilities and structures, providing daily safety briefings, and delivering daily activity logs, testing reports, waste disposal documentation, as-built drawings, and final inspection documentation. The COR is Michael Smith (michael_d_smith@fws.gov, 719-256-5527), and the Project Site Point of Contact is Branden Doering (branden_doering@fws.gov, 620-203-1470). No government-furnished materials are provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B01_-_Synopsis_Of_Proposed_Contract_Activity_(PreSolicitation_Notice)_1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USFWS Flint Hills NWR Headquarters Parking Lot Replacement Scope of Work
1. Project Title Concrete Parking Lot and Sidewalk Construction – Flint Hills NWR
2. Project Location Flint Hills NWR Headquarters Parking
530 W Maple Ave Hartford, Kansas 66854
38.31222, -95.96418
3. Background & Purpose The purpose of this project is to provide safe, durable, and ADA compliant access by constructing or replacing concrete parking areas and sidewalks. This project improves visitor access, staff mobility, and overall site safety.
4. Scope of Work
4.1 Parking Lot Construction
• Construct concrete parking lot per drawings.
• Prepare subgrade with excavation, compaction, moisture conditioning, and ensure proper drainage.
• Install aggregate base.
• Place reinforced concrete 75’x39.5’x6” .
• Finish, edge, cure, and joint concrete.
• Install striping and signage as required.
4.2 Sidewalk Construction
• Construct ADA-compliant sidewalk 81.5’x6’, 30’x6’, and 10’x10.5’.
• Maintain ADA slopes.
• Construct ADA compliant curb ramp.
4.3 Demolition & Removal
• Remove existing concrete, pavement, or materials.
4.4 Site Restoration
• Restore all disturbed areas with grading, topsoil, seeding, and stabilization measures.
5. Technical Specifications
• Concrete strength: minimum 4,000 psi.
• Air content: 6 ½ +/- 1 ½%.
• Reinforcement: [Rebar/Welded Wire Mesh].
• Curing method: Liquid membrane-forming curing compound applied at manufacturer recommendations.
• Compaction and material testing per ASTM standards.
6. Submittals
• Concrete mix design.
• Work schedule.
• Traffic control plan.
• Material certifications.
• Testing plan.
• Disposal plan.
• Safety plan.
7. Period of Performance The Contractor shall complete all work within 240 calendar days from Notice to Proceed.
8. Government Furnished Materials (GFM) None
9. Contractor Responsibilities
• Follow OSHA, state, and Federal regulations.
• Maintain a clean and safe worksite.
• Coordinate inspections with COR.
• Protect existing utilities and structures.
10. Quality Assurance / Quality Control
• Provide and follow QA/QC plan.
• Perform all testing with certified technicians.
• Repair or replace deficient work at no additional cost.
11. Safety
• Comply with all jobsite safety requirements.
• Provide daily safety briefings.
• Submit site-specific safety plan.
12. Environmental & Cultural Compliance
• Follow all environmental protection requirements.
• Prevent sediment runoff and spills.
• Protect biological and cultural resources.
13. Deliverables
• Daily activity logs.
• Testing reports.
• Waste disposal documentation.
• As-built drawings.
• Final inspection documentation.
14. COR & Points of Contact COR: Michael Smith 719-256-5527 michael_d_smith@fws.gov
Project Site POC: Branden Doering 620-203-1470 branden_doering@fws.gov mailto:douglas_smith@fws.gov mailto:branden_doering@fws.gov
15. Attachments
| USFWS Flint Hills NWR Headquarters Parking Lot Replacement Scope of Work |
| 1. Project Title |
| 2. Project Location |
| 3. Background & Purpose |
| 4. Scope of Work |
| 4.1 Parking Lot Construction |
| 4.2 Sidewalk Construction |
| 4.3 Demolition & Removal |
| 4.4 Site Restoration |
| 5. Technical Specifications |
| 6. Submittals |
| 7. Period of Performance |
| 8. Government Furnished Materials (GFM) |
| 9. Contractor Responsibilities |
| 10. Quality Assurance / Quality Control |
| 11. Safety |
| 12. Environmental & Cultural Compliance |
| 13. Deliverables |
| 14. COR & Points of Contact |