A04_-_Statement_of_Work_1.pdf

PDF 364 KB Posted

Attached to
NV ASH MEADOWS NWR CRY SPRNGS RESTORE Federal contract opportunity
Solicitation number
140FGA25R0024
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This Statement of Work (SOW) details a design-build contract for the U.S. Fish and Wildlife Service's Ash Meadows National Wildlife Refuge (AMNWR) in Nye County, Nevada. The project involves comprehensive restoration of the Crystal Springs system, including decommissioning and partial removal of three dams (Crystal Springs, Horseshoe, and Lower Crystal Springs) and their associated reservoirs. Key scope elements include reconstructing approximately 1 mile of naturalized spring outflow channels, removing approximately 5 miles of irrigation infrastructure, installing up to 7 fish barriers, controlling non-native plant species, and implementing visitor access improvements such as a new trail, two overlook structures, and a parking area.

The contract is structured as a design-build services agreement with a planned performance period from September 1, 2024, to February 28, 2027. The contractor will be responsible for comprehensive services including design, permitting, environmental assessments, cultural resource clearance, hazardous materials sampling and mitigation, construction, and site restoration. Major objectives include ecological restoration, native species habitat enhancement, and improving public access and recreation opportunities. The project will require extensive environmental and technical analyses, including hydrology, hydrogeology, and biological assessments, with specific focus on protecting endangered species like the Ash Meadows Amargosa Pupfish and addressing potential contaminants such as PFAS and heavy metals.

View the file

Other files for this federal contract opportunity

Other files attached to NV ASH MEADOWS NWR CRY SPRNGS RESTORE, newest first.
File Type Posted
EA__Template_508-Compliant__Jan2025_2.pdf PDF
FINAL__UCS__EA_8-15-2013_2.pdf PDF
FONSI__Template_508-Compliant__Jan2025_2.pdf PDF
EA__Guidance_508-Compliant__Jan2025_2.pdf PDF
A14_-_Sources_Sought_Notice_1.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Design/Build Services for Crystal System Dam Decommissioning and Spring Outflow Restoration to include All Associated Appurtenances

[Includes Partial Decommissioning, Breaching, and Removal of Crystal Springs Dam, Horseshoe Dam, and Lower Crystal Springs Dam]

U.S. Fish and Wildlife Service

Ash Meadows National Wildlife Refuge (AMNWR) – Nye County, Nevada

REVISED: May 8, 2025.

1.0. GENERAL INFORMATION.

1.1 Summary:

The Contractor shall provide Design/Build Services for the Planning, Design, Remediation, Construction, Decommissioning, Breaching, and Removal of Crystal Springs Dam, Horseshoe Dam, and Lower Crystal Springs Dam, Decommissioning and Removal of Crystal Springs Reservoir, Horseshoe Reservoir, and Lower Crystal Springs Reservoir, Removal of Existing Irrigation Infrastructure and Site Restoration, Re-construction of New Spring Outflow Channel(s), Construction of Visitor Access Improvements, and All Associated Appurtenances.

The Project Area of Interest includes approximately 5 miles of irrigation ditch and irrigation berm and approximately 1 mile of new spring outflow channels to be constructed under this Design/Build Contract. The Desert National Wildlife Refuge Complex (DNWRC), Ash Meadows National Wildlife Refuge (AMNWR), is requesting Design/Build Services to restore its largest spring system, Crystal Springs. Discharge from Crystal Springs supports a diverse array of habitat types including wet meadows, emergent marshes, alkali flats, and riparian areas.

Crystal Springs and its drainage were previously modified and developed for agricultural uses.

Remaining irrigation infrastructure is aging rapidly, creating a requirement for remedial action and an opportunity to restore natural habitats for the benefit of rare fish, wildlife, and plants.

This project includes a comprehensive restoration of the Crystal Springs system to restore ecological function and incorporates visitor access and interpretation enhancements to increase opportunities for outdoor education and recreation.

Primary Objectives.

The Project is to accomplish the following Primary Objectives. The Contractor shall include the following Primary Objectives into their Scope of Work (Scope of Services).

Remediation Services.

For Remediation Services, the Contractor shall perform the following Design/Build services:

Development, preparation, and submittal of a Hazardous Materials Sampling and Testing

Plan and associated regime for evaluating and analyzing Air, Water, and Soil Quality. The Sampling and Testing Plan is to consider contaminates of concern at the Project Site. The contaminates of concern at Ash Meadows National Wildlife Refuge include but are not limited to: Per- and Polyfluoroalkyl Substances (PFAS) and Heavy Metals.

Specifically, the PFAS constituents of concern include 29 different chemicals.

Refer to Attachment for the 29 different chemicals under consideration. These chemicals shall be sampled, tested, and evaluated in the surrounding Air, Water, and Soil by the Contractor and Contractor’s Consultants.

Specifically, the Heavy Metals constituents of concern include but are not limited to:

Arsenic, Cadmium, Chromium, Copper, Nickel, Lead, and Mercury. Refer to Attachment, “Fugitive Dust Analysis, Crystal Reservoir,” for a description of all constituents of concern at the Project Site currently expected. These chemicals from the Fugitive Dust Analysis shall be sampled, tested, and evaluated in the surrounding Air, Water, and Soil by the Contractor and Contractor’s Consultants.

Development, preparation, and submittal of a Hazardous Materials Survey and Report summarizing the materials sampling and testing performed, test results, recommendations, conclusions, mitigation measures, and removal requirements.

Development, preparation, and submittal of a Follow-up Hazardous Materials Mitigation and

/ or Removal Plan based on the Hazardous Materials Sampling and Testing performed at the Project Site and Follow-up Test Results.

Design/Build Contractor’s implementation of the Hazardous Materials Mitigation and / or Removal Plan.

West Crystal Springs Outflow Restoration.

For the West Crystal Springs Outflow Restoration, the Contractor shall perform the following Design/Build services:

Re-construction of naturalized spring outflow channels (approximately (1) mile minimum).

Final channel design and routing will be informed by the Contractor’s Consultant’s hydrological analyses and evaluations.

Revegetation and non-native / invasive plant species control along outflow channels.

Construction of up to seven (7) Fish Barriers within newly constructed Crystal Springs Outflow Channels with removable sections at strategic locations to control the spread of non-native species. The actual quantity of Fish Barriers installed will be a function of the actual channel design performed by the Design/Build Contractor’s Architect-Engineer.

The salvaging of native fish from artificial ditches and impoundments and release of the native fish into their natural environments is to be performed by USFWS and State Partners.

However, the Design/Build Contractor shall be required to closely coordinate their Dewatering and Diversion Plan and On-Site Work Activities with the USFWS during fish salvaging.

The removal of non-native green sunfish from the Project Area and upstream reaches of the Project Site is to be performed by USFWS and State Partners.

Reclamation of Irrigation Infrastructure.

For Reclamation of Irrigation Infrastructure, the Contractor shall perform the following Design/Build services:

Reclamation of approximately (5) miles of Irrigation Ditch and Berm. [Reclamation

Priorities to be informed by Hydrological Analyses]. Reclamation services to include demolition, removal, recycling, and/or disposal of reinforced cast-in-place concrete slab-on-grade channel sections and removal of existing berms.

Decommissioning of Crystal Reservoir and Existing Spur Roads and Parking Areas.

Decommissioning and breaching of Crystal Springs Dam, Horseshoe Dam, and Lower Crystal Springs Dam as part of the decommissioning of Crystal Reservoir, Horseshoe Reservoir, and Lower Crystal Springs Reservoir.

Revegetation and non-native / invasive plant species control within current Crystal Reservoir Foot Print and adjacent developed areas.

Restoration of Horseshoe and Lower Crystal Reservoirs / Marshes to recreate historic Wetland Form and Function.

Visitor Access Improvements and Interpretive Enhancements.

For Visitor Access Improvements and Interpretive Enhancements, the Contractor shall perform the following Design/Build services:

Construction and installation of a New Trail partially compliant with Americans with

Disabilities Act / Architectural Barriers Act (ADA-ABA) Requirements. The New Trail is to be installed through Restored Outflow Reaches of Crystal Springs. The New Trail shall connect Existing Crystal Springs Boardwalk with Horseshoe and Lower Crystal Marshes.

Construction and installation of (2) New Overlook Structures with Interpretive Signs.

Construction and installation of a New Parking Lot (Parking Area) adjacent to the Restoration Area and Downstream Marshes.

Construction of Gravel Access Road Improvements. The Existing Gravel Access Road Improvements to consist of re-grading and re-surfacing of approximately 1.4 miles of Existing Gravel Access Road (Crystal Loop Road).

1.2 Section L – Instructions and Section M – Evaluation Factors:

Refer to Section L and M of the Solicitation for Evaluation Factors.

1.3 Regulatory Requirements:

It is the Contractor’s responsibility to construct the Project in compliance with applicable requirements of federal and state laws, codes, rules, regulations, ordinances, and standards, including, but not limited to, those outlined below. Contractor shall have copies available of applicable codes and regulations for ready reference. These shall include, but are not limited to:

- State and Local Regulatory Requirements,

- Federal Regulatory Requirements,

- Occupational Safety and Health Administration (OSHA) Codes and Standards,

- Fish and Wildlife Service (FWS) Policies,

- All Codes and Standards Not Referenced, but Governing Work under this Project / Contract,

- NFPA 101 Fire and Life Safety Code, Latest Edition,

- International Building Code as adopted by the Local Authority Having Jurisdiction,

- International Plumbing Code,

- International Mechanical Code,

- National Electrical Code,

- Architectural Barriers Act (ABA),

- American’s With Disabilities Act (ADA)

1.4 In the event of a conflict, the most stringent laws, codes, regulations, standards, and provisions shall apply.

2.0. WORK LOCATION AND PERIOD OF PERFORMANCE.

2.1 Work Location: Ash Meadows National Wildlife Refuge (AMNWR), HCR 70, Box 610Z, Amargosa Valley, Nevada, 89020.

Project Location Coordinates: 36.419729, -116.336032

The Project Location Coordinates show a portion of the Project Area located near Ash Meadows NWR – Crystal Springs Reservoir and Horseshoe Reservoir. The Entire Project Area is detailed on a separate attachment from this Statement of Work document.

Refer to separate attachment.

The USFWS does not know the exact coordinates for the multiple project improvements because this will depend on the Design, Engineering, and Construction to be performed under this Design and Build Contract (Design / Build Contract).

2.2 Period of Performance:

Start Date: September 1, 2024 – Estimated (Depends on NTP Date).

End Date: February 28, 2027 – Estimated (Depends on NTP Date).

Site Conditions of the area of interest consists of wetlands, wetland meadows, open water and riparian habitats, open lake marshes, wet meadows, alkali meadows, and riparian woodlands.

Construction Work Window:

(September 1 – February 28) – This Work Window applies to portions of the Project Area where there are shrubs and shrub nesting birds.

(June 1 – February 28) – This Work Window applies to portions of the Project Area without shrubs and without shrub nesting birds.

The Design/Build Contractor will be required to Sub-Contract / Sub-Consult with a Bird Specialist for a Bird Survey and for Follow-up Bird Clearing Services in and around shrub / ground covered areas.

After Follow-up Bird Clearing Services, the Design/Build Contractor has the ability to perform Project Work during an extended June 1 – February 28 Work Window.

In the event of damage to government property resulting from construction, the contractor shall return the damaged area to its original or improved condition. The contractor will also be instructed where to access the Construction Site to minimize potential damage to the existing resources.

The Period of Performance for this Contract is 3-years and 5-months from the actual date of Notice to Proceed (NTP) Letter. Anticipated Delivery Date for NTP Letter is 30 Days Following Initial Contract Award Date. Above dates shown are tentative and subject to change. Contractor shall coordinate with the Refuge Manager and/or Project Leader for a Proposed Construction Work Window. The Final Accepted Construction Work Window will be mutually agreed to between the Contractor and USFWS Ash Meadows NWR prior to Construction.

2.3 Normal Business Hours for the Refuge, Monday thru Friday 7:00 a.m. - 5:00 p.m. Work Activities shall be performed during Normal Business Hours. Limited accommodation to an alternate schedule maybe possible with coordination with on-site FWS employees.

In the event of emergencies, Contractor shall provide contact information.

2.4 Non-duty hours include week nights, weekends, and Government holidays (New Year’s Day, Martin Luther King JR.’s Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day).

3.0. DEFINITIONS.

Not Used.

4.0. BACKGROUND.

The Ash Meadows National Wildlife Refuge (AMNWR) is owned, operated, and managed by the U.S. Fish and Wildlife Service (USFWS). The Refuge is located approximately 20 miles southeast of Amargosa Valley, Nevada. The nearest major city is Las Vegas, Nevada located approximately 108 miles southeast of AMNWR. Note, the nearest town is Pahrump, Nevada located approximately 29.8 miles southeast of AMNWR.

The Future Awarded Contract is to result in the Design-Build of approximately 1 mile minimum of New Naturalized Spring Outflow Channels, Non-native Invasive Plant Species Removal, Re-vegetation along the entire length of the New Spring Outflow Channels, (7) Fish Barriers, salvaging of native fish and re-location, permanent removal of non-native fish, a New Trail System, Two (2) New Overlook Structures, New Interpretive Signs, New Parking Area, Resurfacing of the existing Gravel Access Road (Crystal Loop Road), Demolition, Removal, Recycling and/or Disposal of Irrigation Infrastructure and Site Restoration, and Decommissioning, Breaching, and Removal of Crystal Springs Dam / Reservoir, Horseshoe Dam / Reservoir, and Lower Crystal Springs Dam / Reservoir.

5.0. SCOPE OF WORK.

The Scope of Work for the Project is described as follows:

Design Permits. Contractor shall be in charge of development, preparation, and submittal of Design Permit Applications and Supporting Documents to the Permit Agencies / Permit Authorities for Review and Approval / Disapproval detailing the Project Improvements on 100% Final Draft Construction Documents.

Pre-Abatement, Abatement, and Post Abatement Permits. Contractor shall be in charge of development, preparation, and submittal of Permit Applications and Supporting Documents to the Permit Agencies / Permit Authorities for Review and Approval / Disapproval for Pre- Abatement, Abatement, and Post Abatement Work Activities and Work Tasks.

Pre-Demolition, Pre-Construction, and Construction Permits. Contractor shall be in charge of development, preparation, and submittal of Permit Applications and Supporting Documents to the Permit Agencies / Permit Authorities for Review and Approval / Disapproval for Pre- Demolition, Pre-Construction, and Construction Work Activities and Work Tasks.

Contractor shall be responsible for Identification of All Associated Project Permits through a Permit Registry. After identifying permits, the Contractor shall apply for, Pay, and Secure Permits to result in successful project delivery.

To reiterate, the Scope of Work for this contract shall include the Design, Permitting, Construction, and Installation of the Following Project Design Elements:

High Level Description.

Work Items:

(All Work Items Unless Noted Otherwise, are to be performed by the Design/Build Contractor) Remediation Services.

Remediation Services to include but not be limited to: Hazardous Materials Sampling and Testing Plan and associated regime for evaluating and analyzing Air, Water, and Soil Quality at the Project Site. Hazardous Materials Survey. Design/Build Contractor’s implementation of the Sampling and Testing Plan and Summation of the Test Results, Recommendations, and Conclusions. Development, preparation, and submittal of a Follow-up Hazardous Materials Abatement, Containment, Removal, and Disposal Plan based on the Hazardous Materials Sampling and Testing performed at the Project Site and Test Results.

Naturalized Spring Outflow Channels (1 mile minimum).

Non-native Invasive Plant Species Removal.

Re-vegetation and Non-Native / Invasive Plant Species Control along the entire length of the

New Spring Outflow Channels.

Up to (7) Fish Barrier Structures with Optional Water Control Features including removable sections at strategic locations to control the spread of non-native fish species. The quantity of Fish Barriers installed will be a function of the actual channel design performed.

The salvaging of native fish from artificial ditches and impoundments and re-location to the New Spring Outflow Channels is to be performed by USFWS and State Partners.

The Design/Build Contractor shall closely coordinate their On-Site Dewatering and Diversion Plan Activities with USFWS to facilitate the salvaging of native fish as required.

The Design/Build Contractor is not expected to perform fish salvaging activities its self.

The permanent removal of non-native Green Sunfish from the Project Area and upstream reaches is to be performed by USFWS and State Partners.

New Trail System (through restored Outflow Channel Reaches).

Two (2) New Overlook Structures.

Interpretive Signs.

New Parking Area adjacent to restoration area and downstream marshes.

Resurfacing of approximately 1.4 miles of the Existing Gravel Access Road

(Crystal Loop Road).

Abatement, Containment, Removal, and Disposal:

Abatement, containment, removal, and disposal of contaminated water and soils.

Demolition, Removal, Recycling, and/or Disposal:

Reclamation of approximately 5 miles of Irrigation Ditch and Berm (Irrigation Infrastructure)

(i.e. demolition, removal, recycling, and/or disposal of cast-in-place reinforced concrete slab-on-grade channel ditch sections, removal of existing berms, and in-fill of irrigation channel ditch sections, includes project area leveling of ground surface and removal of non-native and invasive plant species and revegetation).

Partial Decommissioning, Breaching, and Removal:

Crystal Springs Dam and Reservoir.

Horseshoe Dam and Reservoir.

Lower Crystal Springs Dam and Reservoir.

The Contractor shall accomplish the following Tasks if awarded this contract:

5.1. TASK 1. Field Verification Site Visit. Review of Existing Site Features and Existing Site Conditions. Document Review, Planning, Development, Preparation, and Submittal of Project Documents.

(BASE TASK).

Review Drawing Pages (If Available) and All Associated Contract Documents.

Review Project Nomination Document titled, “AMNWR, Project Nomination, Crystal Springs Outflow Restoration, Round 19.

Review Project Nomination Budget titled, “AMNWR. Project Nomination. Budget and Detail Expenses. Round 19.”

Review Available Record Drawings and Specifications (if and when available) previously prepared for select improvements at the Ash Meadows NWR and occurring within or adjacent to the current Design/Build Project’s anticipated and expected Project Area.

Perform a Field Verification Site Visit and Review Existing Site Features and Existing Site Conditions. [The General Contractor Management Team and their Design Team shall be required to Attend this Field Verification Site with USFWS.]

After Performing the Field Verification Site Visit, Develop, Prepare, and Submit General Requirement Specification Submittals under Division 01.

Develop, Prepare, and Submit Technical Specification Submittals under All Remaining Division Sections.

As New Technical Specifications are included during the Development of 35% Design Drawings to 100% Construction Documents, the Contractor shall revise their Submittal Registry and Submittals as Necessary.

Lastly, the Design/Build Contractor shall develop, prepare, and submit Field Verification Site Visit Notes after the site visit. The Field Verification Site Visit Notes shall include a narrative description written jointly between the Design/Build Contractor’s Project Manager and Superintendent and the Design/Build Contractor’s Professional Engineer either in-house or under subcontract to the Design/Build Contractor.

The purpose of the Field Verification Site Visit Notes shall be to notate the anticipated and expected Project Scope at Ash Meadows NWR Crystals Springs, Crystal Springs Dam, Crystal Springs Reservoir, Horseshoe Dam, Horseshoe Reservoir, Lower Crystal Springs Dam, and Lower Crystal Springs Reservoir. The Field Verification Site Visit Notes will include an introduction, discussion, observations, and recommendations/conclusions section defining and describing the project scope and requirements and explicitly noting what is currently within the scope and what is currently beyond the scope of the Awarded Design/Build Contract.

Once the Design/Build Contractor’s recommendations/conclusions are determined and concurrence / agreement has been obtained by USFWS, the Design/Build Contractor shall proceed to TASK No. 2 Field Report – Technical Memorandum (to include preparation and submittal of Conceptual Design Drawings).

Deliverables:

(1) Electronic Copy of the Design-Build Contractor’s Field Verification Site Visit Notes.

Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available.

5.2. TASK 2. Field Report – Technical Memorandum, Preparation of Conceptual Design Alternatives (10 – 15% Detail Drawings).

(BASE TASK).

Develop, prepare, and submit a Field Report – Technical Memorandum. The Field Report – Technical Memorandum is to include Concept Drawings, Narrative Descriptions, Topographic Survey Background Base Map, a Hydrology and Hydraulic Systems Analysis and Evaluation, a Hydrogeology Analysis and Evaluation, Geotechnical Investigation Report, Engineer’s Opinion of Probable Construction Cost, and a Permit Registry.

As part of the Field Report – Technical Memorandum submit a minimum of (3) Conceptual Design Alternatives. The Conceptual Design Alternatives to consist of 10-15% Detail Concept Drawings and Specifications defining and describing different orientations and alignments for the Project Improvements at Crystal Springs and Crystal Springs Outflow.

Conceptual Design Services to include requisite Biology, Hydrogeology, Engineering Geology, Landscape Architecture, and Engineering disciplines (e.g. Fish Biologists, Wildlife Biologists, Hydrologists, Hydrogeologists, Engineering Geologists, Landscape Architecture Consultants, Geotechnical Consultants, Civil Consultants, Structural Consultants, and Permitting Consultants). Architect-Engineer (A-E) shall verify coordination with TERO, NEPA, Cultural Resources, and other required Project Participants through the USFWS Project Leader and/or Project Manager. Further, the A-E shall identify FWS directorates and contacts participating in this project, descriptions of required functional requirements, and descriptions of required connections for the Project Improvements.

For the Permit Registry, the A-E shall provide a list of All Federal, State, County, and Local Permits required for this specific Project/Contract.

The objective of this deliverable shall be to provide USFWS options to select a Preferred Alternative for further Design Development.

The potential Task Breakdown is as follows:

A. Review existing drawings and photographs (if available) for Ash Meadows NWR provided at Solicitation.

B. Review existing Project Nomination Document and Budget Document for Ash Meadows NWR, which describes the Intent of the Project.

C. Perform a Field Verification Site Visit (TASK 1) to review Existing Refuge Drawings and develop an understanding of the existing Crystal Springs System and structures located on the Crystal Springs System.

D. Develop, prepare, and submit Field Report – Technical Memorandum, Conceptual Design Alternatives, Topographic Survey Background Base Map, Hydrology and Hydraulics Report, Hydrogeology Report, Geotechnical Investigation and Report, Engineer’s Opinion of Probable Construction Cost, and a list of All Federal, State, County, and Local Permits Required for the Project Activities.

Major Design Features of Work to be incorporated into the Project at the Conceptual, 35%, 65%, and 100% Stages:

New Naturalized Spring Outflow Channels.

Up to (7) New Fish Barriers with Optional Water Control Features located and installed within the Naturalized Spring Outflow Channels.

Up to (4) New Bottomless Culverts or similar at Road Crossing Points 1, 2, 3, and 4 located and installed within the Naturalized Spring Outflow Channels.

Reclamation of Approximately (5) Miles of Existing Irrigation Ditch and Berm.

Decommissioning, Partial Breaching, and Partial Removal of Crystal Springs Dam and

Crystal Springs Reservoir.

Decommissioning, Partial Breaching, and Partial Removal of Horseshoe Dam and

Horseshoe Reservoir.

Decommissioning, Partial Breaching, and Partial Removal of Lower Crystal Springs Dam and Lower Crystal Springs Reservoir.

Removal of All Remaining Sections of Crystal Springs Dam and Reservoir, Horseshoe Dam and Reservoir, and Lower Crystal Springs Dam and Reservoir.

Decommissioning of Existing Spur Roads and Parking Areas. Site Leveling.

Revegetation and Non-Native / Invasive Plant Species Control to include Removal of Non-

Native and Invasive Plant Species and Planting of Replacement Native Plant Species.

Restoration of Lower Crystal Springs Reservoir / Marshes to recreate historic Wetland Form and Function.

New Trail partially compliant with Architectural Barriers Act and Americans with

Disabilities Act (ABA-ADA).

(2) New Overlook Structures with Interpretive Signs.

New Parking Lot (Parking Area).

Crystal Loop Road Improvements (Gravel Access Road).

Deliverables:

(1) Electronic Copy of the Field Report – Technical Memorandum.

(1) Electronic Copy of the Conceptual Design Alternatives.

(1) Electronic Copy of the Topographic Survey Background Base Map.

(1) Electronic Copy of the Hydrology and Hydraulic Systems Analysis and Evaluation.

(1) Electronic Copy of the Hydrogeology Analysis and Evaluation.

(1) Electronic Copy of the Geotechnical Investigation Report.

(1) Electronic Copy of the Engineer’s Opinion of Probable Construction Cost.

(1) Electronic Copy of the List of All Federal, State, County, and Local Permits Required for the Project Activities (Permit Registry).

Deliverables to be submitted in PDF File Extension and DOCX File Extension (if available).

Drawing Deliverables to be submitted in PDF and DWG File Extension. Construction Cost Deliverable to be submitted in PDF and XLSX File Extension.

5.3. TASK 3. Remediation Services.

- Hazardous Materials Sampling and Testing Plan.

- Hazardous Materials Survey and Report.

- Follow-up Hazardous Materials Mitigation and / or Removal Plan.

- Hazardous Materials Abatement, Containment, Removal, and Disposal.

(BASE TASK).

For this Work Task, the Design/Build Contractor, Design/Build Contractor’s Professional Engineer, and the Design/Build Contractor’s Health / Safety Professionals either in-house or under subcontract shall develop, prepare, and submit a Hazardous Materials Sampling and Testing Plan and associated regime for evaluating and analyzing Air, Water, and Soil Quality at the Project Site.

The Sampling and Testing Plan is to consider contaminates of concern at the Project Site.

The contaminates of concern at Ash Meadows National Wildlife Refuge include but are not limited to: Per- and Polyfluoroalkyl Substances (PFAS) and Heavy Metals.

Specifically, the PFAS constituents of concern include 29 different chemicals. Refer to separate attachment for the 29 different chemicals under consideration. These chemicals shall be sampled, tested, analyzed, and evaluated in the surrounding Air, Water, and Soil by the Design/Build Contractor’s Health / Safety Professionals.

Specifically, the Heavy Metals constituents of concern include but are not limited to: Arsenic, Cadmium, Chromium, Copper, Nickel, Lead, and Mercury. Refer to Attachment, “Fugitive Dust Analysis, Crystal Reservoir,” for a description of all constituents of concern at the Project Site currently expected. These chemicals from the Fugitive Dust Analysis shall be sampled, tested, analyzed, and evaluated in the surrounding Air, Water, and Soil by the Design/Build Contractor’s Health / Safety Professionals.

Following development, preparation, and submittal of a Hazardous Materials Sampling and Testing Plan, the Design/Build Contractor’s Health / Safety Professionals shall develop, prepare, and submit a Hazardous Materials Survey and Report summarizing the materials sampling and testing performed, test results, recommendations, conclusions, mitigation measures, and removal requirements.

Lastly, the Design/Build Contractor’s Health / Safety Professionals shall develop, prepare, and submit a Follow-up Hazardous Materials Mitigation and / or Removal Plan based on the Hazardous Materials Sampling and Testing performed at the Project Site and Follow-up Test Results.

Responding to the Hazardous Materials Mitigation and / or Removal Plan, the Design/Build Contractor shall implement the Mitigation and / or Removal Plan and perform Abatement, Containment, Removal, and Disposal of the Hazardous Materials as required to result in successful project delivery.

Deliverables:

(1) Electronic Copy of the Design/Build Contractor’s Health / Safety Professionals’ Materials Sampling and Testing Plan.

(1) Electronic Copy of Design/Build Contractor’s Health / Safety Professionals’ Hazardous Materials Survey and Report.

(1) Electronic Copy of Design/Build Contractor’s Health / Safety Professionals’ Hazardous Materials Mitigation and / or Removal Plan.

(1) Electronic Copy of the Design/Build Contractor’s Pre- and Post- Abatement Report.

5.4. TASK 4. Follow-up Detailed Hydrology, Hydrogeology, and Hydraulic Report.

(BASE TASK).

For this Work Task, the Design/Build Contractor’s Professional Engineer, Hydrologist, and Hydrogeologist either in-house or under subcontract shall develop, prepare, and submit a Follow-up Hydrology, Hydrogeology, and Hydraulic Report based on TASK No. 1 Field Verification Site Visit and TASK No. 2 Field Report – Technical Memorandum.

The Follow-up Hydrology, Hydrogeology, and Hydraulic Report shall be submitted at the 10-15%, 35%, 65%, and 100% project document milestones.

The Follow-up Hydrology, Hydrogeology, and Hydraulic Report shall assess and evaluate how performing new construction improvements and decommissioning existing construction improvements at Ash Meadows NWR changes the before, during, and after Site Hydrology, Hydrogeology, and Hydraulics.

In particular, the U.S. Fish and Wildlife Service expects the Design/Build Contractor to assess and evaluate the before, during, and after upstream and downstream effects of decommissioning, breaching, and removing of Crystal Springs Dam and Reservoir, Lower Crystal Springs Dam and Reservoir, and Horseshoe Dam and Reservoir. The release of waters from theses (3) separate earthen embankment dam structures will require the Design/Build Contractor in Consultation with their Professional Engineers, Professional Dam Safety Engineers, and Consultants, to develop a strategy for controlled release of impoundment flows and upstream drainage flows because according to the Formal SEED Inspection Report for Crystal Springs Dam:

“If Crystal Springs Dam failed, the dam-failure flood wave would flow into Lower Crystal Dam.

From Lower Crystal Dam, the flood water would cross Stateline Road and continue into California. A hazard classification was performed and recommended that Crystal Springs Dam be classified as a Low Hazard Dam (Wheeler, 2019).”

USGS Reports.

Currently, the USGS plans to perform or is performing (2) Primary Support Efforts for the USFWS Crystal Springs Outflow Restoration Project. Primary Support Effort (1) is to develop, prepare, and submit an Endangered Plant (Amargosa Niterwort) Analysis Report and Primary Support Effort (2) is to develop, prepare, and submit a hydrological modeling report. The USGS reports are anticipated to be received within 12- to 18-months after this Design/Build Contract is awarded. The Design/Build Contractor shall incorporate the findings of these (2) USGS Reports into their Follow-up Detailed Hydrology, Hydrogeology, and Hydraulic Report and Final Draft Construction Documents. It should be noted, the USGS Reports should inform the design solutions presented in the Final Draft Construction Documents.

Major Design Features of Work:

[Requiring Hydrology, Hydrogeology, and Hydraulic Analysis and Evaluation]

Partial Decommissioning, Breaching, and Removal of Crystal Springs

Dam / Reservoir.

Partial Decommissioning, Breaching, and Removal of Horseshoe Dam / Reservoir.

Partial Decommissioning, Breaching, and Removal of Lower Crystal Springs Dam / Reservoir.

Optional Full Decommissioning, Breaching, and Removal of the (3) Dams.

New Naturalized Spring Outflow Channels [approximately 1 mile minimum].

Construction of up to (7) New Fish Barriers with Optional Water Control Features within the New Naturalized Spring Outflow Channels.

Reclamation of Irrigation Ditch and Berm [approximately 5 miles].

Construction of up to (3) New Bottomless Culverts or similar at road crossings and as necessary to allow for Fish Passage.

Estimations, Reviews, and Evaluations:

Estimate Inundation and Inundation Potential for multiple Conceptual Design Alternatives.

Review and Evaluate:

- Inundation and Inundation Potential for multiple Conceptual Design Alternatives.

- Meteorological Data and how this influences Inundation and Inundation Potential.

- Soil Saturation and Wetland Formation.

Deliverables:

(1) Electronic Copy of the 10-15% Follow-up Hydrology, Hydrogeology, and Hydraulic Report to include All Modeling Software Inputs and Outputs and Interpretation of the Inputs and Outputs. Include any relevant plans, elevations, sections, and construction details.

(1) Electronic Copy of the 35% Follow-up Hydrology, Hydrogeology, and Hydraulic Report to include All Modeling Software Inputs and Outputs and Interpretation of the Inputs and Outputs. Include any relevant plans, elevations, sections, and construction details.

(1) Electronic Copy of the 65% Follow-up Hydrology, Hydrogeology, and Hydraulic Report to include All Modeling Software Inputs and Outputs and Interpretation of the Inputs and Outputs. Include any relevant plans, elevations, sections, and construction details.

(1) Electronic Copy of the 100% Follow-up Hydrology, Hydrogeology, and Hydraulic Report to include All Modeling Software Inputs and Outputs and Interpretation of the Inputs and Outputs. Include any relevant plans, elevations, sections, and construction details.

Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available.

All Modeling Software Deliverables shall be submitted in DOCX and PDF File Extensions and include separate files with the Modeling in its native File Extensions.

For example, For HEC-RAS software, the native File Extension would be HDF or similar.

For Auto-Desk software, the native File Extension would be DWG or similar.

For EPANET software, the native File Extension would be INP or similar.

5.5. TASK 5. 35% Draft Design Documents (Drawings and Specifications).

After the Selected Preferred Alternatives are determined from TASKs 1, 2, and 4, the A-E shall develop, prepare, and submit 35% Draft Design Documents (Drawings and Specifications) detailing and describing the Preferred Alternatives.

The 35% Draft Design Documents (Drawings and Specifications) shall fully define and describe All Base and Option Tasks / Elements selected for Contract Award and required for constructing this Project. The Level of Detail for the Design and Engineering Sections of Work shall be as follows:

The 35% Submittal Documents shall describe All of the Architectural and Engineering Design Elements to be included in the Final Document Package, including, but not limited to the following:

Renderings, Existing Conditions Plans, De-watering and Diversion Plans, Demolition Plans, Site Plans, Topographic Survey Background Base Maps, Stream Channel Maps, Sections, Elevations, Details, Engineering Design Drawings, Design Criteria, Design Parameters, Design Calculations, Code Analyses, Project Constraints, Environmental Constraints, Engineering Design Schedules, Project Design Narrative Description, and Technical Specifications.

The 35% Technical Specifications shall be Developed, Prepared, and Submitted in PDF and DOCX File Extensions. The 35% Technical Specifications shall be incorporated into the 65% Technical Specifications.

The Contractor shall incorporate the findings of any Cultural Resource Evaluations (provided by the USFWS Project Leader) to determine necessary Cultural Coordination, Report / Application Preparation (including supporting documents), or documents for processing through the State/Tribe regulatory entity. (For example, TERO agreements if Applicable).

The Drawings shall indicate work, which has Increased any Scope (beyond the Scope of the Contract) using Revision Clouds and Annotations. A separate Accounting by the Contractor shall be provided in XLSX File Extension for Changes to Scope (considered beyond the Scope of the Contract) Any Changes to Scope beyond the Scope of the Contract shall be Approved by the Government (USFWS) prior to the Contractor continuing with the next Design Iteration. The 35% Submittal shall identify “Work by Others” required for the Project to be successfully Constructed / Installed as Designed.

The Contractor’s Professional Engineer under Subcontract shall conduct a Safety Analysis - Perform Code Reviews, and Ensure the Design and Construction complies with (but is not limited to) the USFWS Manuals, Current Edition of the Federal and State OSHA Safety Standards and Requirements, Applicable Bridge and Dam Safety Regulations, National Fire Protection Association 101 Life Safety Code, National Electrical Code, International Plumbing Code, International Building Code, International Mechanical Code, National Gas Code, and Similar Model Codes.

The Contractor shall be required to Apply For, Pay, and Secure Permit Applications, Inspections, and Develop, Prepare, and Submit Supporting Documents (to include but not be limited to: Environmental, Cultural Resource Clearance, Utility Company, Local Building Department, and Local Department of Transportation Permits and Inspections).

Unless explicitly agreed to otherwise by the USFWS, Identify, Annotate, Develop, Prepare, and Submit Permit Applications for USFWS Signature with Supporting Documents (To Include But Not be Limited To: Permit Drawings, Narratives, Biological Assessments, and Similar).

In summary, this 35% Draft Submittal shall include All of the Above Items to result in 35% Detail Drawings, 35% Technical Specifications, and a 35% Design and Construction Schedule.

(1) Electronic Copy of 35% Drawings and Specifications (plans, elevations, sections, and construction details).

(1) 35% Design Summary / Project Narrative.

(1) 35% Design and Construction Project Schedule.

(1) Completed USFWS Safety Checklist.

(1) Copy of All Permit Applications and Supporting Documents.

(1) Electronic Copy of the 35% Permit and Submittal Registry

Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available.

5.6. TASK 6. 65% Draft Construction Documents (Drawings and Specifications).

(BASE TASK).

After Responding to 35% USFWS Review Notes (TASK 5), the Contractor’s Architect-Engineer Company shall develop, prepare, and submit 65% Draft Construction Documents consisting of Drawings, Specifications, and an Engineer’s Opinion of Probable Construction Cost and the Contractor’s Opinion of Probable Construction Schedule. The Contractor shall provide Review Copies of the 65% Construction Documents to the USFWS within 45 Calendar Days after Receipt of Review Notes concerning the 35% Draft Design Submittal.

Deliverables:

(1) Electronic Copy of the 65% Drawings and Specifications (to include plans, elevations, sections, and construction details).

(1) Electronic Copy of the 65% Design Summary / Project Narrative.

(1) Electronic Copy of the Engineer’s Opinion of Probable Construction Cost.

(1) Electronic Copy of the Contractor’s Opinion of Probable Construction Schedule.

(1) Electronic Copy of the 65% Permit and Submittal Registry.

Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available. Registries (Registers) for Permits and Submittals shall be submitted in XLSX File Extensions.

5.7. TASK 7. 100% Draft and Final Draft Construction Documents (Drawings and Specifications).

(BASE TASK).

After Finalizing the Response to the 65% USFWS Review Notes (TASK 6), the Contractor’s Architect-Engineer Company shall develop, prepare, and submit 100% Draft and Final Draft Construction Documents consisting of Final Drawings, Specifications, and a Contractor’s Opinion of Probable Construction Schedule.

Deliverables:

(1) Electronic Copy of 100% Draft Drawings and Specifications (to include plans, elevations, sections, and construction details) for Review and Approval.

(1) Electronic Copy of 100% Final Drawings and Specifications (to include plans, elevations, sections, and construction details).

(1) Printed 22 x 34 Inch Size Drawings and (1) Printed 8.5 x 11 Inch General and Technical Specifications Manual mailed to Ash Meadows National Wildlife Refuge.

(1) Electronic Copy of the 100% Draft Design Summary / Project Narrative for Review and Approval.

(1) Electronic Copy of the 100% Final Design Summary / Project Narrative.

(1) Electronic Copy of the 100% Draft and Final Draft Engineering Design Calculations for Landscape Architecture, Fish Biology, Wildlife Biology, Civil, Water Resources, Environmental, and Structural Engineering Design Elements.

(1) Electronic Copy of the 100% Permit and Submittal Registry, which includes a Minimum Listing of Required Submittals to be submitted Prior to, During, and After Construction. The Submittal Registry shall incorporate the Permit Registry Prepared and Submitted in previous Work Tasks.

As-Built Record Drawings. The Contractor shall work with the Site Superintendent and Foreman during Construction to Document any Field Changes and provide CAD As-Built Record Drawings at the Closeout of the Project.

Deliverables:

(1) Electronic Copy of As-Built Record Drawings.

(1) Printed Mark-Up 22 x 34 Inch Size Drawings and (1) Printed Mark-Up 8.5 x 11 Inch General and Technical Specifications Manual mailed to Ash Meadows National Wildlife Refuge.

Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available. Registries (Registers) for Permits and Submittals shall be submitted in XLSX File Extensions.

5.A. TASK A. Environmental Permitting Assistance.

(OPTION TASK) – Qualified Estimate.

Using the 35%, 65%, and 100% Design and Construction Drawings (TASKs 5, 6, and 7) as a basis, assist the Fish and Wildlife Service with the regulatory permits by providing a Detailed Project Description. Documents to be submitted to the Service for review and the Final Documents developed, prepared, and submitted to the Service.

In summary, the actual Final Documents for Permit Applications and Permit Support Documents to be based on the 100% Final Draft Construction Documents prepared.

As a result, a Comprehensive Project Description is required. The Project Description is to describe in detail the project work activities and durations.

The project description shall at a minimum include estimates on noise levels, the amount and type of vegetation removal, the amount of fill used, wetland impacts, the amount of sedimentation and turbidity from the Proposed Project, and impacts on Proposed Threatened and Endangered Species and Critical Habitat Areas.

The Project Description could be 30 to 50 pages in length and depending on the extent and size of the Project Improvements to be performed.

Note, a Comprehensive Detailed Project Description is provided as a separate attachment to this Statement of Work to demonstrate the level of effort expected in the preparation of the document.

The potential Task Breakdown is as follows:

Prepare and submit a Draft Detailed Project Description for USFWS Review.

Prepare and submit a Draft and Final Draft Wetland Survey and Ordinary High Water Mark

Delineation for USFWS Review (If Required).

The Wetland Survey and Ordinary High-Water delineation at a minimum should include the following:

- Introduction.

- Project Location.

- Background.

- Purpose and Requirements.

- Wetland survey/delineation.

- Ordinary High Water Mark Delineation.

- Wetland Impacts.

- Wetland Mitigation.

Prepare and submit a Final Draft Detailed Project Description to USFWS incorporating previous Review Notes and Comments.

NOTE: The USFWS is to submit the Final Permit Application and Support Documents unless noted otherwise.

Deliverables:

(1) Electronic Copy of the DRAFT Detailed Project Description.

(1) Electronic Copy of the DRAFT and FINAL DRAFT Wetland Delineation Survey and Ordinary High Water Mark Delineation.

(1) Electronic Copy of the FINAL DRAFT Detailed Project Description.

Deliverables to be submitted in PDF File Extension and DOCX File Extension.

5.B. TASK B. National Environmental Policy Act (NEPA) Documentation and Follow-up NEPA Review.

(OPTION TASK) – Qualified Estimate.

Develop, prepare, and submit necessary NEPA Documentation using the Detailed Project Description. The NEPA Documentation could consist of a Formalized Environmental Assessment (EA) if that is the Agency’s Level of NEPA Review determination.

After the NEPA Documentation is developed, prepared, and submitted, the Design/Build Contractor and their Permitting Consultant(s) shall perform the three levels of NEPA review to include Categorical Exclusion (CATEX), Environmental Assessment (EA), and Environmental Impact Statement (EIS). For the purposes of this Design/Build Contract and to ensure a thorough analysis of the Project, Project Improvements, and Effects of implementing Project Actions, the USFWS will not pre-determine what the required Level of NEPA Review would be because the Project Improvements require further definition before an actual Level of NEPA Review determination is established by the Agency.

However, for the purposes of estimating and establishing the Design/Build Contractor’s Proposal, the Design/Build Contractor shall assume an Environmental Assessment (EA) would be required for the Project Work Activities to be performed.

For the NEPA Documentation and Review, the Design/Build Contractor and their Permitting Consultants will identify public scoping items and conduct public meetings during times of the day that the public is available and include translators where necessary. The selection of appropriate times is to allow the public to attend the meetings. The Design/Build Contractor and their Permitting Consultants will synthesize topics to be included or dismissed for consideration in the EA Documentation. Similarly, the Design/Build Contractor and their Permitting Consultants will provide a summary of administrative records and after meeting minutes and applicable after meeting notes.

(1) Electronic Copy of the NEPA Documentation.

(1) Electronic Copy of the Public Review Questions and Answers.

(1) Electronic Copy of the Public Meeting Agenda.

(1) Electronic Copy of the Public Meeting Minutes and Notes.

(1) Electronic Copy of Information Synthesized from the Public Meeting.

Deliverables to be submitted in PDF File Extension and DOCX File Extension.

5.C. TASK C. Section 7 Biological Assessment and Biological Opinion.

(OPTION TASK) – Qualified Estimate.

Develop, prepare, and submit Section 7 Biological Assessment and Biological Opinion Documentation using the Detailed Project Description prepared in TASK A.

Deliverables:

(1) Electronic Copy of the Section 7 Biological Assessment and Biological Opinion Documentation.

Deliverables to be submitted in PDF File Extension and DOCX File Extension.

5.D. TASK D. Permit Support Documents.

(OPTION TASK) – Qualified Estimate.

Develop, prepare, and submit permit support documents for the Nevada Division of Environmental Protection (NDEP) Temporary Working in Waterways.

Develop, prepare, and submit permit support documents for the Nevada State Engineer Application for Decommission, Breach, or Removal of a Dam.

Develop, prepare, and submit permit support documents for the Clean Water Act Sections 401 and 404 Permits (If Required).

(1) Electronic Copy of the NDEP Temporary Working in Waterways, Support Documents.

(1) Electronic Copy of the Nevada State Engineer Application for the Decommission, Breach, or Removal of a Dam, Support Documents.

(1) Electronic Copy of the CWA Sections 401 and 404, Support Documents.

Deliverables to be submitted in PDF File Extension and DOCX File Extension.

5.E. TASK E. Develop, Prepare, and Submit Permit Applications and Supporting Documents to the Regulatory Agencies for Review and Approval / Conditional Approval

(OPTION TASK) – Qualified Estimate.

Organize the identified Permits in the 100% Permit Registry (TASK 6). Develop and prepare the Permit Applications and Permit Support Documents for All Federal, State, County, and Local Permits. Submit the Finalized Permit Applications and Permit Support Documents (to include the Detailed Project Description and/or portions of the Detailed Project Description) to the USFWS for Refuge Manager Signature. Obtain the USFWS Signature Copies of the Applications and submit the executed signature copies of the Permit Applications and Permit Support Documents to each Federal, State, County, and Local Regulatory Agency for Review and Approval / Conditional Approval and Pay All Permit Fees, Processing Fees, and Plan / Specification Review Fees. Participate on Section 7 Consultation Meetings as required during the Regulatory Agency Review Period.

Permit Applications and Permit Support Documents shall be submitted for the following (at a Minimum):

Nevada Division of Environmental Protection (NDEP) Temporary Working in Waterways.

Nevada State Engineer Application for…