A04_Statement_of_Work_(002).pdf

PDF 252 KB Posted

Attached to
REPLACE HEATING, VENTILATION, AND AIR CONDITIONING Federal contract opportunity
Solicitation number
140P5425Q0034
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This Statement of Work (SOW) details the replacement of a 15-ton split system air conditioner at Biscayne National Park Headquarters in Homestead, Florida. The project requires removing the existing air conditioning system and installing a new Ruud or equivalent 15-ton split system, with specific requirements including compliance with Florida Building Code, Miami-Dade County High-Velocity Hurricane Zone standards, and EPA refrigerant handling regulations.

Key project specifications include dismantling and installing the air handler in an attic closet, connecting electrical and drain lines, brazing refrigerant lines, applying a coastal protective coating, and conducting system startup and commissioning. The contractor must provide a 1-year warranty covering compressor, parts, and labor. The estimated project duration is 180 days following contract approval, with work to be scheduled to minimize disruptions to park operations. Deliverables include manufacturer's warranty documents, operation manuals, and a final project report. The project will be considered complete after successful system testing, documentation submission, and approval from the designated project manager.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE HEATING, VENTILATION, AND AIR CONDITIONING, newest first.
File Type Posted
Sol_140P5425Q0034_Amd_0001.pdf PDF
B12_Solicitation_Questions_and_Responses_-_140P5425Q0034_0001.pdf PDF
Sol_140P5425Q0034.pdf PDF
B03_SCA_WD_2015-4543_(Rev__32)_7-8-2025.pdf PDF
Attachment_2_-_Pictures.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) Project Title: 15-Ton Ruud or equivalent Split System Air Conditioner Replacement Location: Biscayne National Park Headquarters

9700 SW 328th Street Homestead, FL 33033

1. Scope of Work

The contractor shall provide all necessary labor, materials, tools, and equipment to remove and replace the existing 15-ton split system air conditioner with a new Ruud or equivalent 15-ton split system in accordance with Florida Building Code (FBC) and Miami-Dade County High-Velocity Hurricane Zone (HVHZ) requirements.

2. Tasks to be Completed

A. Removal & Disposal

• Remove and properly dispose of the existing air conditioning system in compliance with EPA refrigerant handling regulations (Section 608 of the Clean Air Act).

B. Installation of New Air Conditioner

• Dismantle the new air conditioning system as necessary to allow entry into the existing dedicated closet. Closet is in the attic and due to the small and limited space, contractors need to pay extra attention to the unit's location and be prepared to work within these constraints.

• Install the air handler and make necessary duct connections to ensure compliance with ASHRAE Standard 62.1 for proper ventilation.

• Connect the system to the existing electrical, drain lines, and control wiring, ensuring compliance with:

o National Electrical Code (NEC) o Florida Building Code (FBC) Mechanical Chapter

• Install the condenser on the existing concrete slab and secure it in accordance with Miami-Dade County HVHZ requirements.

C. System Integration & Commissioning

• Brazing and System Preparation:

o Braze copper refrigerant lines, purge with nitrogen, and perform a proper vacuum using a micron gauge to meet ASHRAE 15 & 34 standards.

• Refrigerant Balancing and System Startup:

o Balance refrigerant levels as needed per manufacturer specifications.

o Conduct system startup and ensure the system operates efficiently.

• Zoning System Installation:

o Connect the system to the existing 24V zoning damper.

o Install a compatible zoning system to maintain temperature balance throughout the designated areas.

D. Protective Measures & Warranty

• Coastal Protective Coating:

o Apply a coastal protective coating to the condenser coil and cabinet to prevent corrosion and ensure durability in the high-humidity, salt-air environment of Biscayne National Park.

• Warranty Coverage:

o Provide a 1-year warranty covering:

Compressor Parts Labor

3. Exclusions

The following items are excluded from the scope of work:

• Replacement of existing zoning dampers.

• Structural modifications or additional electrical upgrades beyond the existing setup.

• Any work or components not explicitly listed in the scope of work.

4. Compliance & Regulations

All work shall comply with the following applicable standards and regulations:

• Florida Building Code (FBC): Mechanical and Electrical Requirements

• Miami-Dade County High-Velocity Hurricane Zone (HVHZ) Standards

• ASHRAE Standards 15, 34, and 62.1

• EPA Section 608 Refrigerant Management Rules

• National Electrical Code (NEC)

5. Timeline & Completion

• Project Duration: The estimated project duration is 180 days following contract approval and material availability.

• Scheduling:

o Work shall be scheduled in coordination with the client to minimize disruptions to park operations.

o The contractor must provide at least 10 business days’ notice prior to the start of work.

6. Acceptance Criteria

The completion of the project will be based on the following acceptance criteria:

• Operational Readiness: The new air conditioning system must be fully functional and meet the manufacturer’s performance specifications.

• System Testing and Commissioning:

o System commissioning and operational testing must be conducted before project closeout to verify compliance.

• Final Walkthrough:

o A final walkthrough will be conducted with the client to confirm satisfaction and compliance with the contract specifications.

o Any deficiencies identified during the walkthrough must be corrected before final acceptance.

7. Deliverables

The contractor shall provide the following deliverables:

• Equipment Documentation:

o Manufacturer’s warranty documents.

o Operation and maintenance manuals.

o Certification of coastal coating application.

• Final Project Report:

o A comprehensive summary of completed work, including inspection results and system startup verification.

8. Site Conditions and Contractor Responsibilities

A. Site Verification and Preparation

• The contractor is responsible for verifying existing site conditions and ensuring that the work area is properly prepared before the project begins.

• Any discrepancies in site conditions that could affect the project must be reported to the Contracting Officer immediately.

• Due to the small and limited space, contractors need to pay extra attention to the unit's location and be prepared to work within these constraints.

B. Safety and Environmental Protection

• All work must adhere to OSHA safety standards and EPA refrigerant management regulations.

• Appropriate safety measures shall be implemented to protect workers, visitors, and park staff during the project.

9. Project Closeout and Final Documentation

The project will be considered complete upon:

• Submission of all required documentation and warranties.

• Successful completion of system testing and verification.

• Approval from the designated project manager following the final walkthrough.

Statement of Work (SOW)
1. Scope of Work
2. Tasks to be Completed
A. Removal & Disposal
B. Installation of New Air Conditioner
C. System Integration & Commissioning
D. Protective Measures & Warranty
3. Exclusions
4. Compliance & Regulations
5. Timeline & Completion
6. Acceptance Criteria
7. Deliverables
8. Site Conditions and Contractor Responsibilities
A. Site Verification and Preparation
B. Safety and Environmental Protection

9. Project Closeout and Final Documentation