This is a Statement of Work (SOW) for emergency water hauling services at Grand Canyon National Park's North Rim, issued by the National Park Service, U.S. Department of the Interior on October 9, 2026.
The contractor must source, haul, chlorinate, test, and deliver 662,000 gallons of bulk water to North Rim water storage tanks under a firm-fixed-price award (CLIN 00010) with a base completion date of October 29, 2026. An optional 338,000 gallons (CLIN 00020) may be exercised by March 15, 2027, with delivery by May 15, 2027. Water delivery is required to meet restoration efforts following a flood that damaged the Transcanyon Waterline and rendered the Roaring Springs Pump House inoperable. The contractor must comply with Arizona Department of Environmental Quality (ADEQ) regulations and National Park Service potable water hauling policy, including sourcing water only from approved community water systems, chlorinating all loads, conducting field testing, maintaining specific residual chlorine levels (0.2–1.0 mg/L in transit; 1.0–1.5 mg/L at off-load), and pH levels (7.5–8.5 at off-load). The water will be posted as non-potable and used for system flushing and disinfection until the Government returns the system to potable service. The contractor must furnish all equipment, vehicles, personnel, chlorine, fuel, and materials, and must deliver comprehensive documentation including daily reports, delivery records, hauling logs, sanitation logs, and field test results. Critical submittals due within two calendar days of Notice to Proceed include delivery schedules, source identification packages, chlorine dosing procedures, vehicle certifications, backflow prevention assemblies, non-potable signage designs, driver rosters, safety plans, and quality control plans. Work hours are permitted between 0600 and 1900 Mountain Standard Time, seven days per week, with deliveries coordinated through the Contracting Officer's Representative. SR 67 winter closure occurs December 7, 2026; all base deliveries must be complete before this date. No overweight permits will be issued; loaded vehicles cannot exceed 80,000 pounds gross vehicle weight.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior National Park Service Grand Canyon National Park Facility Management & Engineering
Emergency Water Hauling Services
Version: 06 October 2026
Date: October 9, 2026
1 PROJECT DESCRIPTION
1.1 DESCRIPTION OF WORK
The Contractor shall furnish all supervision, labor, vehicles, equipment, materials, chlorine, fuel, and incidentals required to source, haul, chlorinate, test, and deliver bulk water to the North Rim water storage tanks at Grand Canyon National Park under a firm-fixed-price award. The
Contractor shall deliver 662,000 gallons of water (CLIN 00010)to the unloading point at the storage tanks by the base completion date in Section 4.1, following the delivery schedule in
Section 4.2. The Government may exercise an option for an additional 338,000 gallons for the
North Rim (CLIN 00020).
The water will be used to complete the restoration of the park’s North Rim water and wastewater systems — to jet sanitary sewer lines, start-up and commission the Temporary Wastewater
Treatment Plant, and to pressurize, flush, and disinfect the water distribution system — while the
North Rim’s own water supply is out of service after the 29 August 2026 flood. The water will be posted as non-potable and will not be used for drinking until the Government flushes, disinfects, and tests the system and returns it to potable service. The Contractor shall nevertheless source, handle, and haul the water as drinking water, as Arizona’s hauled water rule and National Park Service (NPS) policy require (Section 4.8).
The Contractor shall determine the number and size of vehicles, the staffing, and the methods needed to meet the delivery schedule, subject to legal load limits and the requirements of this
Statement of Work (SOW).
Key deliverables are the delivered water, non-potable water signage, chlorine dosing and field testing of every load, a delivery record for every load, and daily reports.
1.2 LOCATION
- Grand Canyon National Park, North Rim, Coconino County, Arizona 86052.
- Unloading point — the fill connection for the North Rim water storage tanks, adjacent to the North Rim Emergency Services Building on State Route (SR) 67; 36.215117, -
112.058433 (36° 12.907′ N, 112° 3.506′ W); elevation 8,366 feet [location, connection, and coordinates are from the 2023 North Rim water hauling contract — verify for 2026].
- Access — US Highway 89A to Jacob Lake, then SR 67 south to the North Rim. SR 67 is the only paved road to the North Rim developed area.
1.3 BACKGROUND
According to the Superintendent’s Letter of Compliance Completion (Planning, Environment and Public Comment (PEPC) project 138479, 4 September 2026), a flash flood in Bright Angel and Roaring Springs Canyons on 29 August 2026 damaged the Transcanyon Waterline, which supplied water to the North and South Rims. The flood also left the Roaring Springs Pump
House, the North Rim’s water supply, inoperable.
The Government is restoring North Rim utilities damaged in the 2025 Dragon Bravo Fire under a separate contract, and the lack of water affects that work.
According to the Government’s engineer, the Arizona Department of Environmental Quality
(ADEQ) is comfortable with hauling water to the North Rim storage tanks under these conditions: the water comes from a community water system; the water is posted, with abundant signage, as non-potable; and ADEQ is notified and actively engaged during hauling. The engineer also requires the source water system’s name and identification number to perform a water quality review, and requires that residual chlorine and pH be measured before each truck unloads. After consulting ADEQ on the park’s other hauled water operations, the park also requires that hauled water come only from groundwater sources.
Hauled water delivered to a public water system in Arizona is regulated under Arizona
Administrative Code (A.A.C.) R18-4-214 (Reference 1). NPS policy on potable water hauling is in Reference Manual 83A (RM-83A), Chapter 1, Section 10.0 (Reference 2). NPS owns and operates the North Rim public water system and retains responsibility for its compliance and for coordination with ADEQ (Section 5).
Water has been hauled to the North Rim before. In April 2017, a vendor hauled water to the storage tanks after major damage to the pipeline. After that event, the Arizona Department of
Transportation (ADOT) studied SR 67 and raised its allowable gross vehicle weight from 20,000 pounds to 80,000 pounds. In 2023, the park contracted for water hauling to the storage tanks from a regulated public water system after a break in the pipeline from Roaring Springs.
No ground disturbance, vegetation removal, or new construction is anticipated. The Contractor shall notify the Contracting Officer’s Representative (COR) and the Contracting Officer (CO) if ground disturbance becomes necessary. Work in the park will occur on park roads, at the unloading point, and in areas the COR or CO designates.
2 BASE AWARD
The base award (CLIN 00010) is a firm-fixed price for the delivery of 662,000 gallons of water to the North Rim storage tanks by the base completion date in Section 4.1. Each task in this section is included in the firm-fixed price.
2.1 MOBILIZATION AND SOURCE APPROVAL
- Mobilize vehicles, equipment, personnel, and field test equipment to deliver the first load within the time in Section 4.1.
- Identify the water source and submit the source identification package for Government review (Section 4.4).
- Present each truck for Government inspection before its first use (Section 4.8).
2.2 NON-POTABLE WATER SIGNAGE
- Furnish and install 3 non-potable water signs at the North Rim storage tanks, the unloading point, and other locations the COR designates (Section 4.10).
2.3 WATER SUPPLY, CHLORINATION, AND DELIVERY
- Furnish water from an approved source, including all water purchase, bulk water station, and hydrant use fees.
- Add chlorine to every load at the fill point (Section 4.5).
- Haul and deliver 662,000 gallons of water to the unloading point.
- Unload every load through a Contractor-furnished metered, backflow-protected connection to the Government-furnished connection at the unloading point (Section 4.9).
2.4 TESTING, RECORDS, AND REPORTING
- Test every load for free chlorine at fill, after chlorine is added, and for free chlorine and pH at off-load, before unloading (Section 4.5).
- Complete a delivery record for every load, keep the hauling and sanitation logs, and deliver daily reports, weekly log copies, immediate notices, and the closeout record set
(Section 4.7).
2.5 DEMOBILIZATION
- Demobilize, remove all Contractor vehicles, equipment, chemicals, and materials from the park, and deliver the closeout record set.
The firm-fixed price includes mobilization and demobilization; water purchase and fill fees;
chlorine; field testing; non-potable water signage; records and reports; fuel, labor, equipment, overhead, and profit; and winter weather operations.
3 OPTIONS
The Government may exercise the following options by written notice from the CO not later than the exercise dates in Section 4.1. Every requirement of this SOW that applies to the base quantity applies to the (CLIN 00020) quantity.
3.1 (CLIN 00020) — ADDITIONAL HAULED WATER
- Deliver an additional 338,000 gallons of water to the North Rim storage tanks, beyond the base quantity, by the (CLIN 00020) completion date in Section 4.1.
- Perform the Base award (CLIN 00010)tasks in Section 2 for the option quantity, including chlorination, field testing, records, and reporting.
4 PROJECT REQUIREMENTS
4.1 PERIOD OF PERFORMANCE
Key dates. The dates below apply to the base award (CLIN 00010)and both options. Each date is stated only in this table; other sections refer to it.
Milestone Date Base award: base quantity delivered and base period ends (the base completion date) 29 October 2026
(CLIN 00020): last day for the CO to exercise 15 March 2027 (CLIN 00020): option quantity delivered (the (CLIN 00020) completion date) 15 May 2027
SR 67 winter closure, Jacob Lake to North Rim (ADOT; Reference 3) 7 December 2026
Base period. From Notice to Proceed through the base completion date in the table above.
Mobilization. The Contractor shall not deliver water from a source until the Government approves the source (Section 4.4), and shall not use a truck until the Government has inspected it
(Section 4.8). The source identification package and the signage submittal are required with the proposal, so that both are approved before the first delivery.
Option. If the CO exercises (CLIN 00020), the Contractor shall deliver the option quantity by the (CLIN 00020) completion date in the table above, and shall submit a revised delivery schedule within 7 calendar days after the option is exercised (Section 3).
Winter closure of SR 67. ADOT closes SR 67 between Jacob Lake and the North Rim for the winter on the date in the table above (Reference 3). Any delayed deliveries must be complete before the closure. If ADOT closes SR 67 before all deliveries are complete due to unforeseen weather events, the Contractor shall notify the CO immediately. The CO will determine how any undelivered quantity will be delivered.
4.2 DELIVERY SCHEDULE
Proposed delivery schedule. The Contractor shall submit a proposed delivery schedule showing the loads and gallons it will deliver each delivery day to meet the milestones. The Contractor shall provide the schedule to the COR and the CO jointly. The Contractor shall propose any change to an accepted schedule in writing at least 72 hours before the change takes effect. An accepted schedule does not change the base quantity or the milestones.
Time. A delivery day runs from 0000 to 2359 Mountain Standard Time (MST). Arizona does not observe daylight saving time (Reference 4). All records shall use MST, including fill times recorded at any source in Utah, which observes daylight saving time until 1 November 2026.
4.3 WORK HOURS
Deliveries are permitted 7 days per week, including weekends and Federal holidays, between
0600 and 1900 MST, unless the COR approves other hours. The Contractor shall coordinate unloading times through the COR so that deliveries do not interfere with other contractors working in the North Rim developed area.
When a Government inspector is present, no load shall be unloaded without the inspector’s approval (Section 4.5).
4.4 SOURCE WATER
Source requirements. The Contractor shall obtain all water from a source that meets all of the following:
- It is a regulated public water system, or a source approved under 18 A.A.C. 5, Article 5
(Reference 1, subsection A), and it meets the requirements of the Safe Drinking Water
Act (Reference 2, Section 10.1).
- It is a community water system — a public water system that serves at least 15 service connections used by year-round residents or regularly serves at least 25 year-round residents (Reference 5, § 141.2). This is one of ADEQ’s conditions for hauling (Section
1.3).
- A surface water or ground water under the direct influence source may be utilized.
- The source utility has authorized, in writing, the Contractor’s fill point and the volumes needed for this contract.
For example, water for drainfield testing at the North Rim in April 2026 came from a hydrant on the Kanab City, Utah, municipal system, which the Government’s engineer found meets the community water system.
The Contractor may propose any source that meets these requirements.
Source approval. Before the first delivery from a source, the Contractor shall submit a source identification package (Section 6.1) that contains:
- the public water system’s name and identification number;
- written confirmation from the source utility that the system is a community water system;
- the system’s most recent Consumer Confidence Report (Reference 5, § 141.151) for the past three years; and
- the fill location — bulk water station or hydrant — and the source utility’s written authorization for the fill point and the volumes.
The Government’s engineer will use the package to perform a water quality review. The
Government will review each package within 3 business days after receipt. No water from a source shall be delivered until the Government approves the source in writing. The Contractor may propose an alternate source at any time; the same requirements apply.
Laboratory testing. Because the Government will flush, disinfect, and test the North Rim system before returning it to potable service, this SOW does not require laboratory analysis of source water or of delivered loads.
4.5 CHLORINATION AND FIELD TESTING
Chlorine. The Contractor shall use a chlorine disinfectant certified to NSF/ANSI/CAN 60
(Reference 6). Sodium hypochlorite shall also conform to ANSI/AWWA B300 (Reference 7).
The Contractor shall add chlorine at the time each load is filled if needed to achieve the target residual defined in the Acceptance Criteria table.
Test equipment. Each vehicle shall carry a free chlorine test kit that uses a DPD colorimetric method, such as Hach Method 8021, and reads at least 0.2 to 1.0 mg/L, and a pH meter or pH test kit. The Contractor shall calibrate each instrument as the method or manufacturer specifies, check it each day of use, and keep the calibration and check records.
At fill. For each load, the Contractor shall:
- record the date and time;
- uncap the connections and spray them with a 200 mg/L (200 ppm) sodium hypochlorite solution;
- flush the hydrant or fill valve before connecting any hose (Reference 2, Section 10.10);
- measure and record the free chlorine residual of the source water before loading, so that the chlorine dose accounts for it;
- add chlorine (if needed) and fill the transport tank through the backflow-protected fill connection (Section 4.8);
- measure and record the free chlorine residual after dosing, and record the type and quantity of chlorine added;
- measure and record the pH after dosing
- cap all hoses and connections; and
- record the departure time.
At off-load. For each load, before unloading, and witnessed by the Government inspector when present, the Contractor shall:
- record the arrival date and time;
- uncap the connections and spray them with a 200 mg/L sodium hypochlorite solution;
- measure and record the free chlorine residual, as A.A.C. R18-4-214(F) requires at each off-load, and the pH (Reference 1, subsection F);measure and record the pH
- check the water’s appearance and odor;
- begin unloading only when the results meet the acceptance criteria in Section 4.6 and, when an inspector is present, the inspector approves;
- after unloading, record the meter readings and gallons delivered, and sign the delivery record, with the Government inspector’s signature when present; and
- cap all hoses and connections, and restore the unloading connection to a capped, secured condition.
Loads held over. If a load remains in a transport tank more than 24 hours after fill, the
Contractor shall measure its free chlorine residual at least every 24 hours until off-load, to confirm the residual Arizona requires at all times (Reference 1, subsection F).
4.6 DELIVERY ACCEPTANCE
Acceptance criteria. Each load shall meet the following criteria before it is unloaded:
Parameter Criterion Free chlorine at fill, before dosing
0.2 mg/L, minimum
Free chlorine at fill, after dosing
Dosed to ensure that “Free chlorine at off-load” is satisfied.
Free chlorine in transit 0.2 to 1.0 mg/L at all times (Reference 1, subsection F) Free chlorine at off-load 1.0 – 1.5 mg/L pH at off-load 7.5 – 8.5 Appearance and odor at off-load Clear and colorless, with no visible particles, sheen, or objectionable odor
Accepted loads. A load is accepted when all of the following are met:
- It was filled at a source the Government has approved (Section 4.4) and carried in a truck the Government has inspected (Section 4.8).
- It was dosed with chlorine and tested at fill.
- It met the acceptance criteria at off-load.
- It was unloaded at the unloading point, and its metered volume is recorded on a delivery record signed by the Government inspector or, when no inspector was present, accepted by the COR within 1 business day.
Quantity and invoicing. Only accepted gallons, as measured by the Contractor’s meter (Section
4.9) and recorded on delivery records, count toward the base quantity and the milestones. The final delivery may be a partial load. Gallons delivered beyond the base quantity before the CO exercises (CLIN 00020) or issues a modification will not be accepted. Each invoice shall include copies of the signed delivery records for the accepted loads it covers (Reference 8, FAR 52.232-
1).
Nonconforming loads. A load that does not meet an acceptance criterion shall not be unloaded.
The Contractor shall dispose of a rejected load outside the park, or at a location the COR designates, in compliance with applicable discharge requirements. A rejected load does not count toward the base quantity or a milestone. The Contractor shall record the reason for each rejection and the corrective action taken. After 2 rejected loads from the same truck or source, the
Contractor shall stop using that truck or source until the cause is corrected and the COR approves its return to service.
4.7 RECORDS AND REPORTING
Delivery record. The Contractor shall complete a delivery record, on paper or electronically, for each load. Together, the delivery records serve as the hauling log that A.A.C. R18-4-214(F) requires and as the hauling records that RM-83A requires (Reference 1, subsection F; Reference
2, Section 10.4). Each record shall include:
- load number, truck identification, and driver name;
- source name, fill point, and the date and time of filling;
- type and quantity of chlorine added, and the free chlorine residual at fill;
- departure time, and arrival date and time at the unloading point;
- free chlorine residual and pH at off-load, and the appearance and odor check;
- meter readings and gallons delivered;
- acceptance or rejection, and the reason for any rejection;
- signatures of the driver and, when present, the Government inspector; and
- any remarks the driver considers pertinent.
Reports. The Contractor shall provide the following:
- Daily report — by 0900 the following day, to the CO, the COR, and the North Rim
Project Manager or their designee: loads and gallons delivered, cumulative gallons accepted against the current milestone, rejected loads, and incidents, with copies of that day’s delivery records.
- Weekly log copies — copies of the week’s hauling log and sanitation log, each week on the day the COR designates.
- Immediate notice — to the COR and the CO by phone within 1 hour, and in writing within 24 hours, of any rejected load, spill, or accident, and of any event that may prevent the Contractor from meeting a milestone, such as a road closure, a source restriction, or a vehicle breakdown.
Records. The Contractor shall:
- keep on board each vehicle, on paper or electronically, the hauling log; the water source location and the dates and times of loading and unloading; the written cleaning and disinfection procedures and the sanitation log; and copies of permits, licenses, and source authorizations (Reference 1, subsection F; Reference 9);
- make all records available to the Government and to ADEQ on request (Reference 1, subsection F; Reference 2, Section 10.4);
- keep hauling logs at least 3 years (Reference 1, subsection F), and keep all contract records for 3 years after final payment (Reference 8, FAR 4.703); and
- deliver a complete record set to the COR at closeout.
The Government has unlimited rights in all data first produced under this contract (Reference 8, FAR 27.404-1).
4.8 HAULING EQUIPMENT AND SANITATION
These requirements apply to every transport tank, pump, hose, fitting, valve, and appurtenance used under this contract. A “transport tank,” as used in this SOW, is a tank on a Contractor truck or trailer that holds water hauled under this contract (a “water transport container” under A.A.C.
R18-4-214). This section does not apply to the park’s storage tanks. Where A.A.C. R18-4-214, RM-83A, and this SOW differ, the most stringent requirement governs.
Arizona hauled water rule. A.A.C. R18-4-214 applies to every load (Reference 1):
- (A) “All hauled water for delivery to a public water system shall be obtained from a source that is approved pursuant to 18 A.A.C. 5, Article 5, or a regulated public water system.”
- (B) “Materials or products that come into contact with the water shall comply with R18-
4-213(B).” A.A.C. R18-4-213(B) requires conformance to ANSI/NSF Standard 61
(Reference 10).
- (C) “Roof hatches shall be fitted with a watertight cover.”
- (D) “A bottom drain valve or other provisions to allow complete drainage and cleaning of a water transport container shall be provided.”
- (E) “Hoses that are used to deliver drinking water shall be equipped with a cap and shall remain capped when not in use.”
- (F) “A water hauler shall, at all times, maintain a residual free chlorine level of 0.2 mg/l to 1.0 mg/l in the water that is hauled in a water transport container. A chlorine disinfectant shall be added at the time water is loaded into the container. The residual free chlorine level shall be measured each time water is off-loaded from the container. The water hauler shall maintain a log of all on-loading, chlorine disinfectant additions and residual-free chlorine measurements. Such records shall be maintained for at least three years and made available to the Department for review upon request.”
- (G) “A water transport container shall be for hauling drinking water only. The container shall be plainly and conspicuously labeled ‘For Drinking Water Use Only.’”
NPS potable water hauling policy. The Contractor shall also meet the following requirements of RM-83A, Chapter 1, Section 10.0 (Reference 2):
- (10.2) Transport tanks shall be constructed of non-toxic, non-porous materials and shall never have been used for storing or hauling anything but potable water. NSF-approved containers are recommended.
- (10.5) A transport tank that has not been used for more than one day shall be flushed before it is used to haul water. The Contractor shall provide its hauling procedures to the park and the NPS public health consultant on request. Primary agency protocols shall be followed.
- (10.6) At no time during filling shall a potential for backflow exist.
- (10.7) Hoses used to fill and empty transport tanks shall be identified and used only for potable water. Hose ends shall be capped when not in use, and the caps shall be attached to the hoses.
- (10.8) All tanks, hoses, fittings, and other equipment used to store, haul, or transfer water shall be constructed of approved food-grade materials or coated with approved food-grade coatings.
- (10.9) Hoses shall be stored so that they are not subject to contamination from surface runoff, birds, rodents, and other sources.
- (10.10) All valves and fire hydrants shall be flushed before any hose is connected.
- (10.11) Bacteriological testing of transport tanks is not required under this contract, because the source is a community water system with a bacteriological monitoring program and the Government will perform bacteriological sampling of the North Rim system before returning it to potable service.
Separate system and labeling. The Contractor shall meet the following:
- The hauled water system — fill hoses and lines, pumps, transport tanks, and discharge piping — shall be separate from any other water system.
- Each transport tank shall be plainly and conspicuously labeled “For Drinking Water Use
Only” (Reference 1, subsection G). Because Arizona sets this labeling standard, its wording governs over the RM-83A wording (Reference 2, Section 10.0). Hoses shall be labeled “potable water.”
Materials. All water-contact materials and coatings, including gaskets, lubricants, and hose linings, shall be certified to NSF/ANSI/CAN 61 (Reference 11). Water-contact surfaces shall be smooth, non-corrodible, and non-absorbent. Galvanized pipe and fittings, cast-iron pumps, and petroleum-lubricated pumps shall not be used.
Transport tank construction. Each transport tank shall meet the following (Reference 9):
- It shall close to exclude foreign matter and shall be vented. Vents shall face downward and shall be protected by a 30-mesh screen of non-toxic, non-absorbent material.
- It shall have at least one roof hatch that allows interior inspection and cleaning, fitted with a watertight cover (Reference 1, subsection C).
- Its inlets and outlets shall have threaded or clamped caps tethered to the ports, in place except while water is being loaded or discharged.
- It shall have a bottom drain that allows complete drainage and cleaning (Reference 1, subsection D). No pipe carrying a non-potable liquid shall pass through the tank.
Filling and backflow. The Contractor shall:
- fill only at the source utility’s bulk water station, or at a hydrant the source utility authorizes in writing, from water under pressure;
- protect each fill against backflow, consistent with A.A.C. R18-4-215 (Reference 12), by either an air gap — the fill pipe ending at least 1 inch, or twice the fill pipe diameter, whichever is greater, above the highest water level the tank can reach (Reference 13) — or a backflow prevention assembly approved under A.A.C. R18-4-215(D), with no branch between the assembly and the tank inlet. Where the source utility requires a higher level of protection, that requirement governs; and
- use sanitary transfer techniques, keep foreign material out of the water, and never submerge a hose or pipe in a receiving vessel.
Sanitation. The Contractor shall:
- clean and disinfect transport tanks, pumps, hoses, valves, and fittings per ANSI/AWWA
C652 (Reference 14) before first use under this contract; after 72 hours or more of non-use; after any possible contamination, including open covers or caps, or entry of dust, smoke, rain, or chemicals; and after any defect appears in a seal, vent, hatch, valve, pump, or hose;
- after disinfection, drain and flush with potable water before filling;
- keep written cleaning and disinfection procedures, stating the agents, concentrations, and contact times, on each vehicle; and
- keep a sanitation and maintenance log on each vehicle that shows the method and frequency of cleaning (Reference 2, Section 10.4).
Truck inspection. Before first use under this contract, the Contractor shall present each truck for
Government inspection at a location the COR designates. The Government may require the transport tank to be empty for interior inspection. The Government will inspect items (C), (D), (E), and (G) of A.A.C. R18-4-214, and the Contractor shall furnish documentation of items (A) and (B). The Government will use the following checklist, adapted from Coconino County’s
Water Hauler Truck Inspection Information Sheet (Reference 15):
- the source is approved under Section 4.4;
- the transport tank has been used only for potable water and has never held any other product (Reference 2, Section 10.2; Reference 1, subsection G);
- the transport tank is labeled “For Drinking Water Use Only”;
- the transport tank, its coating, and every other part that contacts the water are certified to
NSF/ANSI/CAN 61;
- the transport tank has a roof hatch with a watertight cover, a screened vent, and a bottom drain;
- hoses are certified to NSF/ANSI/CAN 61, labeled, clean, in good repair, and capped when not in use;
- the truck carries chlorine certified to NSF/ANSI/CAN 60, a free chlorine test kit that reads 0.2 to 1.0 mg/L, and a pH meter or kit, and the operator shows how to use them;
and
- the truck carries the hauling log, the sanitation log, and the written cleaning and disinfection procedures.
The Government may inspect any vehicle and its records at any time.
4.9 DELIVERY AND UNLOADING OPERATIONS
Unloading point. The Contractor shall unload only at the unloading point in Section 1.2 and shall connect only to the Government-furnished 2-inch female camlock at that point (Section 5).
If changes are required to the connection point, the government will provide the details in writing with a 3-day advance notice. The Contractor shall make no other connection to park facilities.
No Contractor equipment, including pumps, meters, hoses, and backflow prevention assemblies, shall connect to park facilities until the Government approves the related submittals (Section 6).
Unloading equipment. The Contractor shall furnish pumps, hoses, and fittings that connect to the Government-furnished coupling and can fill the storage tanks. Hoses and fittings shall be certified to NSF/ANSI/CAN 61 and used only for drinking water.
Backflow protection at the unloading point. The Contractor shall:
- furnish, install, and maintain at the unloading connection a reduced pressure principle backflow prevention assembly that conforms to ASSE 1013 (Reference 16) and holds a current certificate of approval from the University of Southern California Foundation for
Cross-Connection Control and Hydraulic Research (Reference 17), or another method the park’s Cross-Connection Control Program accepts in writing;
- have the assembly tested before first use, and after any relocation or repair, by a person currently certified as a general backflow tester by the California-Nevada Section of the
American Water Works Association, the Arizona State Environmental Technical
Training (ASETT) Center, or another certifying authority ADEQ approves (Reference 12, subsection F), and submit each test report to the COR; and
- sanitize hose ends and fittings before each connection.
Metering. The Contractor shall measure every load with a totalizing meter, on the transport tank’s discharge line or at the unloading connection, that meets the tolerance for water in
National Institute of Standards and Technology (NIST) Handbook 44, Section 3.31 (Vehicle-
Tank Meters), Accuracy Class 1.5 (plus or minus 1.5 percent) (Reference 18). The Contractor shall test each meter against a volume standard traceable to NIST before first use, and when the
COR asks, and shall give the results to the COR.
Other work at the North Rim. Other contractors are restoring utilities in the North Rim developed area. The Contractor shall coordinate access, staging, and unloading times through the
COR, and shall not interfere with their work.
Contractor-furnished items. The Contractor shall furnish all water, chlorine, fuel, equipment, and personnel. Government fuel is not available.
4.10 NON-POTABLE WATER SIGNAGE
One of ADEQ’s conditions for hauling is abundant signage that states clearly that the water is non-potable. The Contractor shall:
- prepare a signage submittal (Section 6.1) that shows the sign wording, layout, symbol, size, material, quantity, locations, and mounting method; the Government will route it to
ADEQ, and no sign shall be installed until NPS and ADEQ approve it;
- furnish 3 signs reading “NON-POTABLE WATER — DO NOT DRINK,” with a “do not drink” symbol and Spanish text; off-the-shelf signs are acceptable;
- make each sign of rigid, weather-resistant and ultraviolet-resistant material, at least 12 by
18 inches;
- install the signs at the North Rim storage tanks, the unloading point, and other locations the COR designates, on existing structures, fences, or freestanding bases, without ground disturbance;
- install the approved signs before the first delivery; and
- replace any damaged or missing sign within 2 calendar days, until the final delivery.
The signs shall remain in place at completion and become Government property. The
Government will remove them when it returns the system to potable service.
4.11 PERSONNEL, PERMITS, AND DRIVER HOURS
Supervision. The Contractor shall designate one (1) supervisor and one (1) alternate, each reachable at all times when operations are active.
Drivers. Each driver shall hold a commercial driver’s license (CDL) of the class, and with the endorsements, that the vehicle requires, including the tank vehicle (N) endorsement for a tank vehicle. The Contractor and its drivers shall comply with 49 CFR Parts 382, 383, and 390 through 399 as they apply, including as Arizona adopts them for intrastate carriers (Reference
19; Reference 20).
Hours of service. Drivers shall comply with the hours-of-service rules in 49 CFR Part 395, including any exception in 49 CFR 395.1 that applies to the driver (Reference 19). Emergency hours-of-service relief is not expected to apply to this work. The Contractor shall staff and schedule drivers to meet all normal requirements.
Chlorination and testing staff. Staff who add chlorine or test water shall be trained in the
Contractor’s chlorine dosing procedure (Section 6.1). Contractor staff shall not make process control decisions for the park’s water system.
Permits and authorizations. The Contractor shall:
- obtain and maintain all permits, inspections, and certifications that apply to potable water hauling vehicles. Coconino County does not currently license or inspect water haulers
(Reference 15). If the county resumes licensing or inspection during the contract, the
Contractor shall obtain the license or inspection within 14 days of the county’s notice;
- obtain any ADOT permits that apply (Section 4.12);
- obtain a bulk water account or written authorization from each source utility; and
- keep a copy of each permit, inspection certificate, and authorization in the vehicle.
4.12 TRAFFIC, ACCESS, AND HAULING
- All delivery vehicles shall use SR 67 to reach the North Rim.
- No loaded vehicle shall exceed eighty thousand (80,000) pounds gross vehicle weight, or any lower limit posted or required on SR 67 or on park roads. Overweight permits will not be issued for this work.
- The Contractor shall follow all traffic laws and regulations.
- The Contractor shall yield to wildlife and to visitor traffic at all times.
- Engine braking shall not be used within the North Rim developed area except where required for safety.
Winter operations. The Contractor shall maintain deliveries in winter conditions, including by protecting hoses, pumps, meters, valves, and backflow prevention assemblies from freezing. The
Contractor shall notify the COR, within the time in Section 4.7 for immediate notices, when a road closure or weather condition threatens a milestone.
4.13 SAFETY
- The Contractor is responsible for the safety of its work and shall comply with 29 CFR
Part 1910 and all other Occupational Safety and Health Administration (OSHA) standards that apply (Reference 21).
- The Contractor shall submit a site-specific safety plan before the first delivery (Section
6.1). The plan shall address the safety of the public, NPS personnel, other contractors, and the Contractor’s employees, and the protection of property.
- The Contractor shall not enter any park storage tank or other confined space on park property. Any entry into a transport tank shall follow the Contractor’s permit space program under 29 CFR 1910.146 (Reference 21).
- During any work outside daylight hours, the Contractor shall provide the lighting needed to work safely, and its personnel shall wear high-visibility safety apparel that meets
ANSI/ISEA 107 (Reference 22).
- The Contractor shall store and handle sodium hypochlorite as its safety data sheet directs, shall provide eye and body flushing equipment where 29 CFR 1910.151(c) requires it, and shall give the COR a safety data sheet for every hazardous chemical before bringing it onto park property (Reference 21, §§ 1910.151(c) and 1910.1200).
- The Contractor shall carry a first aid kit on each vehicle and shall report all accidents to the COR within the time in Section 4.7 for immediate notices.
4.14 SPILL PREVENTION AND RESPONSE
- The Contractor shall submit a spill prevention and response plan addressing fuel and chlorine before the first delivery (Section 6.1).
- Each vehicle shall carry spill response materials sufficient for the largest chlorine container it carries.
- The Contractor shall report any spill or release to the COR immediately and shall submit a written incident report within 24 hours.
- The Contractor shall manage water discharged during connection, disconnection, and flushing so that it does not erode soil, damage vegetation, or enter a storm drain.
4.15 CONTRACTOR USE OF PREMISES
- Establishment of a construction camp within the park is not permitted.
- The Contractor shall conduct operations to cause the least inconvenience to the public, park staff, and other contractors.
- The Contractor shall confine operations to SR 67, park roads, the unloading point, and the staging area the COR designates (Attachment 1), and shall prevent damage to natural and cultural resources. The Contractor shall restore any damaged area to its original condition at no additional cost to the Government.
- The Government is not responsible for loss of or damage to Contractor property stored on
NPS property.
- The Contractor shall know the park’s rules and regulations and shall ensure that its workers follow them.
- Lodging and services at the North Rim are unavailable. The Contractor shall arrange lodging for its personnel off site.
4.16 STAGING AND LAYDOWN
- Staging shall be confined to the area the COR designates.
- No ground disturbance or vegetation removal is authorized.
- Vehicles awaiting unloading shall not idle more than 5 minutes, except while the engine powers the unloading pump or when idling is needed to protect equipment from freezing.
4.17 QUALITY CONTROL
- The Contractor shall inspect its own work to ensure that services meet this SOW, and shall provide supervision at all times over the work its employees perform.
- The Contractor’s quality control plan shall describe how the Contractor will meet the milestones, dose and test every load, meet the equipment and sanitation requirements, and keep records, including internal checks and corrective actions.
- The Government reserves the right to witness any fill, unloading, or test; to inspect any vehicle and its records; and to reject any load that does not meet the acceptance criteria
(Reference 8, FAR 52.246-4).
4.18 CLEANUP
- The Contractor shall remove all debris, packaging, and waste from park property daily.
- At the end of each unloading, the Contractor shall leave the unloading point clean and free of hoses and equipment, with the connection capped and secured.
- At completion, the Contractor shall remove all tools, equipment, chemicals, surplus materials, and rubbish, and shall restore any surfaces damaged by the work to their original condition.
5 GOVERNMENT FURNISHED EQUIPMENT, MATERIALS, AND SERVICES
- A Government inspector at the unloading point during delivery hours, when available, to witness off-load tests, approve unloading, and sign delivery records. The Government may omit the inspector at certain times.
- At the unloading point, a 2-inch female camlock on the storage tank fill line, with an isolation valve.
- A designated staging area at the North Rim.
- A water quality review of each source identification package by the Government’s engineer, and written approval or rejection of each source (Section 4.4).
- Routing of the signage submittal to ADEQ (Section 4.10).
- Written notice of the Government’s designated inspectors and the North Rim point of contact.
Note: The following are excluded from this contract and will be performed by the Government:
operation of the North Rim public water system; notification of, and coordination with, ADEQ during hauling; compliance monitoring, recordkeeping, and reporting under 40 CFR Part 141 and
18 A.A.C. 4; bacteriological sampling, flushing, and disinfection of the North Rim storage tanks and distribution system, and return of the system to potable service; removal of the non-potable signs; post-fire utility restoration; and repair of the Roaring Springs Pump House and the
Transcanyon Waterline. The Contractor shall furnish the records and data that support the
Government’s coordination with ADEQ.
6 SUBMITTALS
The Contractor shall submit the following items to the CO and the COR. Numbering is continuous across all subsections. The items in Section 6.1 are due not later than 2 calendar days after Notice to Proceed, and before the first delivery.
6.1 PRIOR TO FIRST DELIVERY
1. Proposed delivery schedule that meets the milestones in Section 4.2.
2. Hauling route and winter contingency plan (Section 4.11).
3. Source identification package for each source (Section 4.4).
4. Chlorine dosing procedure, with product data and the safety data sheet for chlorine certified to NSF/ANSI/CAN 60 (sodium hypochlorite shall also conform to
ANSI/AWWA B300), and product data for the free chlorine test kit and the pH meter or kit.
5. Vehicle and transport tank list, with NSF/ANSI/CAN 61 certifications, documentation of compliance with A.A.C. R18-4-214(A) and (B), pump and hose data, labeling photographs, and copies of vehicle permits.
6. Transport tank cleaning and disinfection procedures, with the disinfection record for each truck before its first use.
7. Fill backflow protection method for each source, and the product data, certificate of approval, and test report for the backflow prevention assembly at the unloading connection.
8. Meter product data and test results.
9. Non-potable water signage submittal, for NPS and ADEQ review and approval (Section
4.10).
10. Driver roster, with commercial driver’s license and endorsement verification.
11. Site-specific safety plan.
12. Spill prevention and response plan.
13. Quality control plan.
14. Emergency contacts, including the supervisor and the alternate.
15. Written notice that the insurance required by the contract has been obtained (Reference 8, FAR 52.228-5).
6.2 BEFORE USING EACH NEW SOURCE OR TRUCK
16. New source: source identification package (Section 4.4).
17. New truck: the vehicle and transport tank documentation and the disinfection record for that truck.
6.3 DURING PERFORMANCE
18. Each proposed change to the accepted delivery schedule, at least 72 hours before it takes effect, and a revised delivery schedule within 2 calendar days after the CO exercises
(CLIN 00020).
19. Daily reports, with that day’s delivery records, by 0900 the following day (Section 4.7).
20. Weekly copies of the hauling log and the sanitation log.
21. Incident reports, including the written follow-up to each immediate notice within 24 hours.
22. Backflow prevention assembly test reports and meter test results, as they occur.
6.4 CLOSEOUT
23. Complete electronic record set — all delivery records, hauling logs, sanitation logs, and field test records — in a searchable format, with the delivery data in a spreadsheet (.xlsx or .csv).
24. Summary of accepted gallons by week, compared with the milestones.
25. Certification that all Contractor equipment and chemicals have been removed from park property.
7 LIST OF ATTACHMENTS AND DRAWINGS
- Attachment 1 — Site map: SR 67 route into the North Rim, the North Rim Entrance
Station, the unloading point, and the staging area.
8 SPECIFICATIONS
8.1 REFERENCES
The references below are cited in Sections 1 through 8 as “(Reference N).” Where this SOW differs from an applicable Arizona or federal requirement, the more stringent requirement governs. Each consensus standard applies in the edition stated in this list or, where no edition is stated, in its current edition. NPS is the authority having jurisdiction for this contract; this does not limit ADEQ’s authority over the park’s public water system.
No. Citation Title Where to find it 1 A.A.C. R18-4-214 Arizona Administrative Code, Hauled Water https://www.law.cornell.edu/regulati ons/arizona/Ariz-Admin-Code-SS-
R18-4-214 2 NPS DO #83A; RM-83A NPS Director’s Order #83A, Public Health
Protection and Disease Prevention (28 April
2023), and Reference Manual 83A (20 June
2019), Chapter 1, Section 10.0 — Potable Water
Hauling https://www.nps.gov/subjects/policy/ upload/RM-83A_6-20-2019.pdf
3 ADOT ADOT to close state route SR 67 on the first
Monday of the first full week in December.
GRCA-ADOT IGA
4 A.R.S. § 1-242 Arizona Revised Statutes, Standard time https://www.azleg.gov/ars/1/00242.h tm 5 40 CFR Part 141 National Primary Drinking Water Regulations (§
141.2, definitions; § 141.151, Consumer
Confidence Reports) https://www.ecfr.gov/current/title-
40/chapter-I/subchapter-D/part-141
6 NSF/ANSI/CAN 60 Drinking Water Treatment Chemicals — Health
Effects NSF International, https://www.nsf.org 7 ANSI/AWWA B300-24 Hypochlorites American Water Works Association, https://www.awwa.org 8 FAR (48 CFR Chapter 1) Federal Acquisition Regulation, as supplemented by Department of the Interior class deviations https://www.acquisition.gov/browse/ index/far
No. Citation Title Where to find it 9 NWCG (2007) National Wildfire Coordinating Group, Potable
Water Tank Specification (March 2007) https://www.fs.usda.gov/sites/nfs/fil es/r05/publication/NWCG%20Potab le%20Water%20Tank%20Specificat ions.pdf 10 A.A.C. R18-4-213 Arizona Administrative Code, Standards for
Additives, Materials, and Equipment https://www.law.cornell.edu/regulati ons/arizona/Ariz-Admin-Code-SS-
R18-4-213 11 NSF/ANSI/CAN 61 Drinking Water System Components — Health
Effects NSF International, https://www.nsf.org 12 A.A.C. R18-4-215 Arizona Administrative Code, Backflow
Prevention https://www.law.cornell.edu/regulati ons/arizona/Ariz-Admin-Code-SS-
R18-4-215 13 A.A.C. R18-4-103 Arizona Administrative Code, definitions (air-gap separation) https://www.law.cornell.edu/regulati ons/arizona/Ariz-Admin-Code-SS-
R18-4-103 14 ANSI/AWWA C652-25 Disinfection of Water-Storage Facilities American Water Works Association, https://www.awwa.org 15 Coconino County EQ Water Hauler Truck Inspection — Information
Sheet (16 December 2022), and Online
Applications page (water hauler licensing status) https://www.coconino.az.gov/Docu mentCenter/View/54944/EQ-Hauler-
Water-Inspections-Information-
Sheet;
https://www.coconino.az.gov/2291/
Online-Applications 16 ASSE 1013-2021 Performance Requirements for Reduced
Pressure Principle Backflow Prevention
Assemblies
ASSE International, https://www.asse-plumbing.org
17 USC FCCCHR Manual, Tenth Edition Manual of Cross-Connection Control, Tenth
Edition (December 2009; fifth printing 2020).
A.A.C. R18-4-215(E) incorporates the Ninth
Edition (December 1993) for the minimum level of protection.
Foundation for Cross-Connection
Control and Hydraulic Research, University of Southern California, https://fccchr.usc.edu
18 NIST Handbook 44
(2026) Specifications, Tolerances, and Other Technical
Requirements for Weighing and Measuring
Devices, Section 3.31, Vehicle-Tank Meters https://www.nist.gov/document/2026
-nist-handbook-44-section-331
19 49 CFR Parts 382, 383, and 390–399 Federal Motor Carrier Safety Regulations https://www.ecfr.gov/current/title-
49/subtitle-B/chapter-III/subchapter-
B 20 A.A.C. R17-5-202 Arizona Administrative Code, Motor Carrier
Safety: Incorporation of Federal Regulations;
Applicability https://www.law.cornell.edu/regulati ons/arizona/Ariz-Admin-Code-SS-
R17-5-202 21 29 CFR Part 1910 Occupational Safety and Health Standards https://www.ecfr.gov/current/title-
29/subtitle-B/chapter-XVII/part-
22 ANSI/ISEA 107-2020 American National Standard for High-Visibility
Safety Apparel International Safety Equipment
Association, https://safetyequipment.org