This document is a Statement of Work (SOW) for the purchase and delivery of road material needed at the Everglades Headwaters National Wildlife Refuge (Refuge) in Okeechobee County, Florida. The SOW requires the purchase and delivery of approximately 900 cubic yards (1,455 tons) of non-FDOT, roadbase material such as shell-stabilized base or equivalent, with a size range of 1.5 inches to dust. The material must meet specific environmental requirements and cannot contain asphalt mixtures.
The delivery of the material is expected to occur during the December 2024 - April 2025 timeframe, with an expected completion date of one week, weather permitting. Delivery will be to the project site, with access only available via CR-68 off Highway 98. The material will be tail-gate spread as directed by staff at the time of delivery, with up to 10 trucks accepted daily during regular working hours. The contractor is responsible for visiting the site prior to bidding to understand the existing delivery and dumping conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Clauses_4Q.pdf | ||
| Sol_140FS324Q0213.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
FWS Everglades NWR
4055 Wildlife Way, Vero Beach Florida 32963
Statement of Work for Commercial Item: Road Material
Scope of Work
Purchase and deliver road material needed at Everglades Headwaters National Wildlife Refuge (Refuge).
Purchase and deliver the following material:
Roadbase (baserock)
Need 900 cubic yards/CY (~1,455 tons) of non-FDOT, roadbase such as shell-stabilized base or equivalent. The size of the material is approximately 1.5 inches to dust. If recycled concrete aggregate is used, it must be from a source that has a Florida Department of Environmental Protection/FDEP permit per section 62-701.730 or be qualified as a clean debris source under FDEP's rules to assure that there are no toxic contaminants in the material such as asbestos or lead. Mixtures with asphalt are not acceptable.
Delivery
Delivery will be to the project site in Okeechobee County, Florida as shown on map (Lat: 27.511111°N / Long:
-81.145958°. W). Note that the only available access is via CR-68 off Hwy 98. There is no west-bound access on
NW 256st via The Vikings due to a washed-out culvert. See attached maps for access details. The material will be tail-gate spread as directed by staff at the time of delivery. Once roadbed delivery begins, approximately 10 trucks can be accepted daily (no less than 5 trucks daily), during regular working hours (7:30 AM to 3:30 PM).
Delivery will not be made when conditions are so wet that delivery will damage existing roads.
It is the contractor’s responsibility to visit the site prior to bidding and know existing delivery and dumping conditions.
Delivery of material is expected to be during the December 2024 – April 2025 timeframe. Expected completion date is one week, weather permitting.