A04_SOW.pdf

PDF 206 KB Posted

Attached to
JEFF - Terrazzo Refinishing
Solicitation number
140P6226Q0003
Issued by

About this file

This is a Statement of Work (SOW) for the refinishing of terrazzo flooring at Gateway Arch National Park, contract number 140P6226Q0003, prepared by Dovie Cagle on July 31, 2026.

The project encompasses cleaning and refinishing approximately 54,000 square feet of terrazzo flooring in the museum and visitor center. The terrazzo flooring was originally installed in 2018 during a redesign of the facility. The specific work tasks include: machine cleaning terrazzo floors using a green 3M pad and EZ Clean Floor Cleaner & Degreaser by Dur-A-Flex; flushing with Neutra Rinse and final mopping; and applying four coats of Plaza Plus by Diversey followed by high-speed buffing with a 3M hogs hair pad. No optional work is identified. The Government will not furnish equipment or materials; however, power, water, and public restroom access will be provided. The National Park Service will remove all benches, tables, and objects from work areas each night.

All work must be performed during evening hours from 5:00 p.m. to 1:00 a.m., Monday through Friday, in one continuous operation phase, with all on-site work completed between February 1, 2027 and March 1, 2027. Weekend and holiday work may be acceptable with 48 hours' notice and approval from the Contracting Officer, Contracting Officer's Representative, or Park Staff. The place of performance is Gateway Arch National Park.

View the file

Other files

File Type Posted
Sol_140P6226Q0003_Amd_0002.pdf PDF
B08_-_Revised_Combined_PDF_0002.pdf PDF
Sol_140P6226Q0003_Amd_0001.pdf PDF
B08_Site_Visit_Q_A_0001.pdf PDF
A04_SOW_REVISED_19_August_2026_0001.pdf PDF
B03_Wage_Determination.pdf PDF
B08_-_Combined_PDF.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gateway Arch National Park

Statement of Work

Refinishing of Terrazzo Floor

140P6226Q0003

Table of Contents

1.0 Project Description / Summary

2.0 Objectives

3.0 Background

4.0 Specific Work / Tasks

5.0 Optional Work / Tasks

6.0 Government Furnished Equipment / Materials / Other

7.0 Special Conditions / Requirements

8.0 Place of Performance

9.0 Performance Period / Schedule Requirements

Statement of Work

Project Title: Refinish Visitors Center Terrazzo Floor

Park Unit: Gateway Arch National Park (JEFF)

Prepared By: Dovie Cagle

Date: 31 July 2026

1.0 PROJECT DESCRIPTION / SUMMARY:

This project will clean and refinish the Terrazzo Flooring in the museum and visitor center of the Gateway Arch National Park (Approx 54,000 sqft of area). The Terrazzo flooring was installed in the 2016 redesign of the museum and visitor center.

2.0 OBJECTIVES:

This project is intended to refinish the floors in Gateway Arch National Park Museum in keeping with the historic nature of the building. The refinished floor will enhance durability, safety and maintain aesthetic consistency.

3.0 BACKGROUND:

THE GATEWAY ARCH TERRAZZO FLOOR WAS INSTALLED IN 2018. SINCE THEN, WE HAVE NOT HAD THE

FLOORS REFINISHED. THERE IS APPROXIMATELY 54,000 SQUARE FEET THROUGHOUT THE MUSEUM THAT

NEEDS TO BE REFINISHED.

4.0 SPECIFIC WORK / TASKS:

• Machine clean terrazzo floors with a green 3M pad and EZ Clean Floor Cleaner & Degreaser by

Dur-A-Flex.

• Flush with Neutra Rinse and final mop.

• Apply four (4) coats of Plaza Plus by Diversey and then high speed buff terrazzo floors with 3M hogs hair pad.

5.0 OPTIONAL WORK / TASKS:

• N/A

6.0 GOVERNMENT FURNISHED EQUIPMENT / MATERIALS / OTHER:

a. Equipment-None

b. Materials- None

c. Power and Water can be provided. Public restrooms are in the vicinity.

7.0 SPECIAL CONDITIONS / REQUIREMENTS:

1. NPS WILL REMOVE ALL BENCHES, TABLES AND OR OBJECTS IN WAY OF AREA BEING WORKED EACH

NIGHT.

2. All work to be performed evening working hours, after 5:00pm, Monday through Friday, in one continuous operation/phase.

8.0 PLACE OF PERFORMANCE:

• Gateway Arch National Park

9.0 PERFORMANCE PERIOD / SCHEDULE REQUIREMENTS:

• All on-site work must be completed between 1 Febuary 2027 and 1 March 2027.

• General work hours shall be 5:00 pm to 1 am.

• Weekend and holiday work may be acceptable with 48 hours notice and approval by the CO, COR, or Park Staff.