A04_SOW.pdf
PDF 4 MB Posted
- Attached to
- ASPHALT REPAIR AT BIG BRANCH MARSH NWR
- Solicitation number
- 140FC125Q0009
About this file
This Statement of Work outlines requirements for asphalt repair and maintenance at the Big Branch Marsh National Wildlife Refuge headquarters in Lacombe, Louisiana. The work includes cleaning and repairing approximately 285 sq ft of damaged asphalt, filling 3,500 ft of stress cracks, applying two coats of asphalt sealer to 140,000 sq ft of roadway and parking areas, and restriping parking lines including handicapped spaces. The sealer must meet ASTM and FAA standards, while paint must meet Louisiana Department of Transportation standards.
The period of performance runs from Notice to Proceed until November 13, 2025, with project completion required within 90 days of Notice to Proceed. Work hours are 7:00 am to 4:30 pm Monday through Friday. The contractor must provide all materials, supplies, licenses, and permits, conduct weekly progress meetings, and ensure proper disposal of debris. The project supports a facility housing 25-30 employees and volunteers, managed by the U.S. Fish & Wildlife Service. Technical oversight is provided by Robert Beech as COR, with Neil Lalonde as Project Leader for site-related matters, and Sandy Moody as the Contracting Officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC125Q0009_Amd_0001.pdf | ||
| Sol_140FC125Q0009_Amd_0001_Changes_SOW_0001.docx | DOCX document | |
| Gen_Wage_Determination_LA20250011_01_03_2025.pdf | ||
| Sol_140FC125Q0009.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Sealer and Parking Lot Striping at the
Big Branch Marsh National Wildlife Refuge Drafted June 27, 2024
BACKGROUND:
The Refuge Headquarters is located Lacombe, Louisiana and it provides office space for 25-30 employees and volunteers, with the safety of our employees being of utmost importance. The asphalt driveway and parking areas are over eight (18) years old and are in need of minor repairs. All dimensions and lengths are estimated by the Government, and it is advised the contractor verify calculations.
The period of performance will be Notice to Proceed to November 13, 2025 and the prescribed work will be located on the grounds of the Southeast Louisiana Refuges Headquarters, 61389 Highway 434 Lacombe, Louisiana. The Contractor may visit the site with the FWS Project Manager at designated time and date to view the project.
GENERAL DESCRIPTION OF WORK:
General Notes:
1. Work shall consist of the following tasks:
a. Clean all asphalt surfaces on the grounds adequately to prepare for items b through e.
b. Repair six (6) areas of damaged asphalt that total approximately 285 sq ft.
c. Fill approximately 3500 ft of stress cracks with asphalt sealer.
Sealer must meet Louisiana Department of Transportation and Development standards and be on their list of approved materials.
d. Apply two (2) coats of asphalt sealer on approximately 140,000 sq ft of roadway and parking areas. Sealer shall meet or exceed requirement for ASTM D 5725, ASTM D 6945, ASTM D 3320 and FAA Engineers Brief No. 46. The sealant shall be mixed in accordance with the manufacturer recommendations and each application applied for moderate traffic rate 0.12-0.15 gal/sq.yd.
e. Re-stripe all painted lines and handicapped parking spot. Paint must meet Louisiana Department of Transportation and Development standards and be on their list of approved materials.
i. Blue handicapped parking symbols (2) and 64 feet of lines
ii. Yellow road center line- 2134 feet
iii. White parking space lines- 1000 feet
2. USFWS will trim any trees/branches if needed.
3. Contractor is responsible for all materials and supplies necessary to install system.
4. All debris or trash will become the contractor’s property and shall be removed from the site and disposed of off sight at an approved landfill.
5. No material can be left or stored on the facility during the job without prior approval.
6. Contractor will be required to meet once a week at government specified times for progress meetings for an update status meeting.
7. The Contractor will, without additional expense to the Government, be responsible for obtaining any necessary licenses, certifications, and permits and for complying with any applicable federal, state and municipal laws, codes, and regulations in regards to employment and the use of equipment necessary for the work.
8. The Contractor will provide a competent foreman or superintendent for each work crew. The supervisor must be capable of communication with the COR or designated inspector in English. The supervisor shall be with the crew at all times while they are working on the Refuge.
9. All equipment used in performing work shall be of the proper type, sufficient size, and be in such mechanical condition as to enable contractor to perform the work in accordance with these specifications and OSHA requirements. Contractor shall furnish all fuel, oil, grease, repairs, replacement parts and other expenses incidental to the operation of his equipment.
10. Upon completion of the site and prior to accepting the work as being completed, all trash, rubbish, paint and debris generated by contractor's operation shall be removed from Refuge land and disposed of in a sanitary landfill or other appropriate location designated by COR. To the extent practical, such trash or debris shall be removed and disposed of daily.
11. Smoking by contractor personnel is permitted only in cleared areas. Contractor will have on site a bucket with sand for the disposal and a 15lb fire CO2 extinguisher. Contractor will be held personally accountable for any fire caused by them.
12. The contractor shall take precautions to prevent pollution of streams, lakes, wetlands and reservoirs by fuel, oil, silt or other harmful materials. All stream courses and wetland areas shall be kept free of contractor generated debris.
13. Project will be completed in 90-days from Notice to Proceed. Any additional time will be submitted to the COR two weeks prior to designated completion date.
14. Normal working hours will be from 7:00 am through 4:30 pm, Monday through Friday. There will be no after hour, Federal Holidays or weekend work unless authorized by the COR.
PROJECT CONTACT:
Site Related and Access Questions shall be directed to:
Neil Lalonde, Project Leader U.S. Fish & Wildlife Service
Big Branch Marsh Wildlife Refuge
61389 LA-434
Lacombe, LA 70445 985/285-3335
Email: neil_lalonde@fws.gov
Technical or Project Related Questions shall be directed to:
Robert Beech
COR, NWRS Infrastructure Management Branch U.S. Fish & Wildlife Service
1875 Century Boulevard Atlanta, Georgia 30345 Phone: 404/ 226-1907
Email: robert_beech@fws.gov
Contracting Officer All Questions before award shall be directed to: Sandy Moody
U.S. Fish & Wildlife Service: Contracting Construction AE Acquisition Operations, APO, Atlanta, GA
JOINT ADMINISTRATIVE OPERATIONS
khanhthong_moody@fws.gov
Example of repair area
Example of repair area
END OF STATEMENT OF WORK