A04_SOW.docx

DOCX document 30 KB Posted

Attached to
WELLS FS FURNACE REPAIR
Solicitation number
140L3924Q0145
Issued by

About this file

This document is a Statement of Work (SOW) for the repair of the furnace serving the Bureau of Land Management (BLM) Wells Fire Station Operations Building in Wells, Nevada. The SOW provides details on the scope of services required, including the replacement of the furnace flue, and any additional repairs needed to return the furnace to working order. It specifies that the work must be performed in accordance with the 2021 International Existing Building Code and any other applicable codes. The SOW includes information on the contract's period of performance, payment terms, and site access requirements. The related federal contract opportunity is a solicitation (Solicitation Number: 140L3924Q0145) for the furnace repair, issued by the Department of the Interior Bureau of Land Management Nevada Region.

View the file

Other files

File Type Posted
A06_Specifications.pdf PDF
Sol_140L3924Q0145.pdf PDF
A06_Manual.pdf PDF
B03_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

SCOPE OF WORK

WELLS FIRE STATION FURNACE REPAIR

Elko District Office (EDO) Wells, Nevada

I. General Project Statement A. The furnace serving Operations building at the Bureau of Land Management (BLM)’s Wells Fire Station Operations Building has stopped functioning & requires repair.

B. All work performed shall be in accordance with all applicable codes.

C. The Wells Fire Station is located on Airport Road in Wells, NV. Drawing showing building location is attached.

II. Scope of Services A. Furnace Repair

a. Furnace Information

i. Furnace model is Nordyne M1MC 056A BW.

ii. Gas valve and control board were replaced in April of 2024.

b. Flue shall be replaced as per furnace manufacturer’s recommendations.

i. Attached are furnace specifications & manual along with pictures.

ii. Flue shall be five (5) inches in diameter & aluminized steel. Total flue length is unknown, however it is less than five (5) feet.

iii. Contractor shall repair roof as needed should any damage occur during repair activities.

iv. Should additional services beyond flue replacement be required to return furnace to working order, contractor shall submit quote for further service for repair to Contracting Officer’s Representative.

1. Should any additional parts require replacement, they shall be replaced with parts as specified in manufacturer’s literature (see attached for furnace installation manual and specifications).

III. Requirements A. All work performed shall be in accordance with 2021 International Existing Building Code and any other applicable codes.

B. The BLM will evaluate contractors on Past Performance and Price.

IV. Contractual A. Period of Performance

a. It is anticipated that the work for this task shall occur as soon as possible. Total time of performance shall be 45 calendar days from the date of award.

B. Fee and Payment:

a. All services, supplies, materials, labor, superintendence, and travel necessary to perform the work required under this contract are to be included in the lump sum price of this contract.

b. Payment shall be made upon completion of furnace repair.

C. Use of Premises:

a. Site is currently occupied & accessible.

b. Site can be accessed during normal business hours (8 am – 5 pm, M-F) by contacting COR & arranging a time for access. Any site visit shall be arranged at least one (1) working day in advance.

c. The Contractor and his sub-contractor(s) shall have full use of premises for preparatory work. Contractor’s use of premises is limited only by Government right to perform work.

d. Work schedules shall be 7:30 am to 5:00 pm, Monday through Friday. Any alternative work schedule shall be approved by Contracting Officer’s Representative prior to commencing.

e. Schedule and sequence preparatory operations necessary to complete the work. Schedule work in such manner as to avoid delays.

f. The Contractor shall contact in writing and have the approval of the Contracting Officer two (2) working days in advance prior to any preparatory operations to be conducted on the premises.

File details come from the government source that posted it. Updated .