A04_SOW_Demolish_Structures_040725.docx

DOCX document 40 KB Posted

Attached to
Olympic NP DEMOLITION OF EXCESS STRUCTURES Federal contract opportunity
Solicitation number
140P8325R0017
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This Statement of Work (SOW) details a demolition project for the National Park Service at Olympic National Park, involving the removal of structures at three distinct sites. The base bid includes demolishing four cabins at Kalaloch Lodge, with two optional additional sites: the Webber Property in Quinault and the Allen Property at Rocky Point on Lake Ozette. The project requires comprehensive removal of above-ground and select below-ground structures, utility disconnections, site restoration, and landscape scarification, with strict environmental protection and wildlife conservation guidelines.

The solicitation (No. 140P8325R0017) is a 100% Small Business Set-Aside commercial services contract using NAICS code 238910 for Site Preparations. The project is scheduled for completion between September 2025 and October 2025, with a request for quote closing on 8/11/2025 at noon Pacific time. Contractors must be registered in the System for Award Management (SAM) and comply with detailed environmental, safety, and operational requirements, including specific work hour restrictions, equipment cleaning protocols, and waste disposal regulations. Questions about the solicitation must be submitted to Geraldine_larsen@nps.gov by 7/30/2025.

View the file

Other files for this federal contract opportunity

Other files attached to Olympic NP DEMOLITION OF EXCESS STRUCTURES, newest first.
File Type Posted
Sign_in_Sheet_0002.pdf PDF
Site_Visit_Clarifications_0002.pdf PDF
Sol_140P8325R0017_Amd_0002.pdf PDF
Sol_140P8325R0017_Amd_0001.pdf PDF
B08_Attachment_7Limitations_on_Subcontracting_Worksheet.xlsx XLSX spreadsheet
B08_Relevant_Project_Experience_Questionnaire_attachemnt_6.docx DOCX document
B08_PAST_PERFORMANCE_QUESTIONNAIRE_Attachment_5.docx DOCX document
A06_OLYM_149_80011A_Kalaloch_Concession_Water_Sewer.pdf PDF
A06_Drawings_OLYM_149_70008A_Kalaloch_Guest_Cabins.pdf PDF
B08_Price_Schedule_Sheet.docx DOCX document
Sol_140P8325R0017.pdf PDF
B08_Attachment_7Limitations_on_Subcontracting_Worksheet_1.xlsx XLSX spreadsheet
B08_Photos.docx DOCX document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

Demolish Structures in Multiple Areas Olympic National Park part 1- general information

The intent of this project is to remove all structures, above ground improvements, in-water improvements, and miscellaneous debris, and scarify the landscape, at multiple sites in Olympic National Park for the purpose of restoring the landscape to natural conditions. The contract will consist of a base bid and two options. The base bid includes removal of Cabins # 1, 4, 5 and 14 at the Kalaloch Lodge. Option #1 is for removal of improvements to the former Webber property at 413 North Shore Road in the Quinault area of the park. Option #2 is for removal of all improvements to the former Allen property, Clallam County Parcel Number 153010-330275, at Rocky Point on the eastern shore of Lake Ozette.

1.0 Description of Work

Prior to any on-site work the contractor shall provide the required 14-day notice for the specified work to the Olympic Regional Clean Air Agency.

Contracted hazardous materials surveys for all identified properties have been completed and will be provided to the selected contractor. The reports identified the following findings:

Surveys will be provided prior to start.

To the greatest extent possible, all work of the project shall remain within existing road corridors and impacted sites. The contractor shall take great care to avoid impacting any vegetation on site. The contractor will keep park roadways clear of mud, rocks and debris created associated with project work.

Between April 1 – September 23 work shall be restricted as follows:

· work shall only occur between two hours after sunrise and two hours before sunset.

· work activities shall be limited to tasks that do not produce sounds louder than ambient noise levels—such as, dismantling structures and hauling away debris.

· work such as using chainsaws, breaking up concrete, mortared or asphalt structures shall not occur (until after September 23).

· Demolition work that is planned prior to August 31 will require park inspection for presence of nesting bat colonies. If any active colonies are present at a structure, demolition of that structure will be postponed until after the breeding season ends. In the unlikely event that the contractor encounters bats with flightless young in a structure after August 31, work will be halted for not longer than four weeks.

All structures and refuse removed from the sites must be disposed of, recycled or salvaged, in accordance with federal and state regulations outside of the park’s boundaries. The method of removal may be determined by the contractor. If contractor anticipates that completion of work will impede traffic on roadways, they must provide traffic control and one-week advance notification to the park.

The Park has made every effort to identify all major elements of the project below. Contractor is responsible for verification of quantities and all miscellaneous, ancillary elements. The intent is that all above ground man-made elements and select below ground elements as described below be removed, and the landscape scarified so it may be restored to natural conditions.

Approximate quantities for removal work to be performed at each site is as follows (see attachment 1 for maps and photos):

SITE 1 (BASE BID): KALALOCH LODGE- 157151 HIGHWAY 101

Removal of the identified cabins shall be performed during the period of 09/02-10/31/2025. Cabins adjacent to the cabins identified for removal will be occupied by Lodge guests during the performance period. Work at these sites will be confined to the hours of 8:00 am- 5:00 pm, with no operation of machinery to occur until 9:00 am to minimize impacts to Lodge guests. All furnishings and serviceable fixtures have been removed from the cabins. Demolition shall be performed using mechanical equipment in accordance with OSHA 29 CFR 1926 standards. Contractor shall ensure debris is sorted for recycling or salvage where feasible in compliance with EPA Construction Waste Management Guidelines and NPS sustainability directives.

The contractor shall facilitate opportunities for interested parties to relocate any or all cabins or repurpose cabin materials at fair market value. If relocation is not self-performed, the work shall be subcontracted under all applicable contract requirements and clauses.

· Remove Cabin 1 - 321 sf.

· Remove Cabin 4 (512 sf). Take all feasible measures to retain existing shrubbery and avoid damage.

· Remove Cabin 5 (496 sf). Take all feasible measures to retain existing shrubbery and avoid damage.

· Remove Cabin 14 - 684 sf

· Remove all driveways. If necessary to prevent soft road shoulders following removal, import base material to harden road shoulder for the width of the driveway to a distance of 36 inches from the road.

· All cleared sites shall be graded level with cobbles larger than ¾” diameter removed from the surface and left suitable for seeding and mowing.

· Prior to seeding, spread a minimum 1”, maximum 2"of Cascade Bark (Brady Trucking of Sequim, WA) Pro Blend Soil or approved Equal, make even with the surrounding grassy areas, and rake into an even plane

· The park will provide sufficient seed to adequately cover the area.

· Seeding: Perform all seeding between November 1st and March 1st. Seeding may not occur if snow is on the ground. Seed shall be applied by hand or with hand seeders - evenly distributed across the area. Lightly rake the seed into the soil to a depth of ¼”. Do not smooth with the backside of the rake, light furrows in the soil are desired.

Olympic National Park Demolish Structures at Lake Crescent & Lake Quinault All cabins are connected to water, sewer and electrical systems. Water and sewer connections shall be capped at connection to the main by a certified plumber. Electrical service shall be disconnected at pedestal and the conductor severed one foot below ground on each end. Work shall be performed by a licensed electrician. Utilities plans for the Lodge will be provided. The contractor will be responsible to obtain utilities locates prior to the performance of work.

OPTION ITEMS:

SITE 02 (OPTION ITEM #1): WEBBER PROPERTY, 413 N. SHORE ROAD, QUINAULT

The Webber Property is located in the Quinault area of Olympic National Park at 413 N. Shore Road. The site contains a wood-framed cabin with basement, a carport with loft, a pumphouse, and various minor site improvements. The property is accessible by existing roadways. Work shall be planned to minimize environmental impact and comply with NPS natural resource protection standards.

· Remove 1,203 sf cabin with 265 sf basement, including all interior furnishings, fixtures, and miscellaneous items. Demolition shall be performed using mechanical equipment in accordance with OSHA 29 CFR 1926 standards. Contractor shall ensure debris is sorted for recycling or salvage where feasible in compliance with EPA Construction Waste Management Guidelines and NPS sustainability directives.

· Pump, collapse, and fill septic tank south of cabin. Fill shall consist of clean, compactable sand or gravel from a weed-seed-free, NPS-approved source. Compact in lifts to achieve a minimum of 90% of ASTM D698 standard Proctor density, verified through field density testing.

· Remove 581 sf carport and 322 sf loft. Structural steel and salvageable wood shall be separated for recycling or reuse, with disposal off-site in accordance with federal and state regulations.

· Remove 80 sf pumphouse, access path, and related improvements. All utilities shall be properly disconnected by licensed professionals prior to removal. Restore site to natural grade and ensure no utility hazards remain.

· Remove architectural improvement to stump outhouse. Dispose of all debris at approved recycling or disposal facilities in accordance with federal, state, and local regulations.

· Consult Park Botanist prior to final scarification and grading of property. Contractor shall obtain written approval following a documented site meeting before proceeding with scarification or grading activities.

· Place 4-6” of clean hog fuel on all scarified areas. Hog fuel shall be certified weed-free and pathogen-free, sourced from a park-approved supplier. Spread evenly and compact lightly to prevent erosion, as directed by the Park Botanist.

SITE 03 (OPTION ITEM 2): ALLEN PROPERTY, ROCKY POINT, LAKE OZETTE

The Allen Property is on Rocky Point on the eastern shore of Lake Ozette and is only accessible by water. The wood-framed cabin is on a post and pier foundation. The contractor shall determine the best means of access and removal within the contract parameters. Contractor shall perform a site reconnaissance to assess access routes, staging locations, and hazards due to large rocks along the shoreline and submerged in the water. All transport activities via water shall be planned to minimize environmental impacts and comply with NPS aquatic resource protection policies.

• Remove 1,053 sf cabin. Demolition shall be conducted using hand or mechanical methods appropriate for water-access sites, ensuring compliance with OSHA 29 CFR 1926. Debris shall be sorted for recycling or salvage and transported off-site for disposal in accordance with EPA and state regulations.

• Remove 81 sf storage shed. Salvage any reusable materials where feasible, and ensure debris is disposed of at approved facilities.

• Remove 26 sf outhouse. Properly dispose of any waste and structure debris per local and federal standards.

• Remove all stairs, fences, trails, and associated improvements. Ensure minimal ground disturbance and restore impacted areas to natural conditions.

• Consult Park Botanist prior to final scarification and grading of property. Contractor shall document consultation and secure written approval before scarification begins.

• Any clean concrete on site may be used to fill voids as described in Section 1.03. Ensure concrete is free of contaminants and placed to promote drainage and stabilization.

• Place 4-6” of clean hog fuel on all scarified areas. Hog fuel shall be sourced from a park-approved, certified weed-free supplier and applied evenly to achieve erosion control objectives under the direction of the Park Botanist.

THE FOLLOWING WORK DESCRIPTIONS ARE PERTINENT TO ALL SITES:

1.01 Septic Tanks: Where the location of the septic tank is undetermined, the contractor shall make a good faith effort to locate it. Tanks shall be collapsed and buried in place. If additional fill is required, it shall be weed-seed free from a park-approved source. The Park will provide the contractor with any documentation available regarding septic locations.

1.02 Below ground utilities: Identified below ground utilities shall be cut off 12 inches below ground at transition point.

1.03 Driveways: All asphalt, concrete and gravel driveways and parking areas shall be removed. Driveways and parking areas will be de-compacted and scarified. No re-contouring will be required for driveways.

1.04 Re-contour: Re-contour will involve moderate relocation of materials to smooth transition between surrounding land and previous building site. Identify areas where water may accumulate and ensure that positive drainage is established. Re-contour activities shall be under the direction of the park botanist.

1.05 Finish Work: Ensure that all project areas have been thoroughly cleaned of project debris following the removal of the specified elements, to include sweeping of each area with a magnet to ensure the removal of all nails and screws. De-compact and scarify all previous building sites, driveways and parking areas at the very end of the project.

1.06 Scarify: All areas on each property, including building sites and access roads, shall be de-compacted via scarification 6” minimum depth up to 12” maximum depth. Scarification activities shall be under the direction of the park botanist.

1.1 Dock & Piling Removal: The Contractor will avoid cutting wood (treated or untreated) over water when removing docks to minimize impacts to aquatic resources. Treated wood should be cut in a manner where the saw dust cannot reach the water. Treated material should be moved off-site as soon as practicable. The only work permitted below the ordinary high-water mark will be removal of docks, pilings and concrete bulkheads. Bulkhead removal shall be performed after September 23 while lake levels are at the lowest.

1.2 Tree Removal: The contractor must obtain approval from the park regarding any tree removal. Tree removal may be considered in cases where a tree poses a safety hazard during removal activities or where no other access route is feasible. Contractor should take action to mitigate tree damage such as limb and trunk damage. To the extent possible avoid unnecessary stress on root systems.

1.3 Equipment: The Contractor will pressure wash and/or steam clean all construction equipment, except hauling vehicles, before entering the Park to ensure that all equipment, machinery, rocks, gravel, or other materials are cleaned and weed free. Motors/engines will not be left unattended. Equipment will be free of any fluid leaks (fuel, oil, hydraulic fluid, etc.) upon arrival to the work site and will be inspected at the beginning of each shift for leaks. Leaking equipment will be removed off site for necessary repairs before the commencement of work. Equipment will be inspected by the COR prior to entry into the park. Any watercraft/ barges that will be utilized for the project will require inspection by qualified park staff for the presence of invasive aquatic species.

1.4 Location: This project is located in Olympic National Park, Port Angeles, Washington. See attachment 1 for maps of the area and project sites.

1.5 Regular Working Hours: Regular working hours at the park are from 7:00 a.m. to 5:00 p.m., Monday through Friday, excluding federal holidays. All work shall be scheduled during regular working hours. Contractor must adhere to workday restrictions imposed to protect marbled murrelet habitat as detailed in Description of Work. Contractor must adhere to alternate work hours for Kalaloch, as detailed in the Description of Work.

1.6 Notification: The Contractor shall provide a project schedule that identifies all phases of the project and includes a 72-hour window during which the park’s wildlife biologists may perform site surveys prior to project work at each site in the Quinault area.

1.7 Work Restrictions: Requests to work outside of regular working hours must be approved by the Contracting Officer (CO) through the COR one week in advance.

1.8 Waste Disposal: The contractor shall legally recycle or dispose of all project materials outside of the park boundary. Materials should be diverted away from landfills to the greatest extent possible. Tickets identifying load weight shall be provided to the Contracting Officer’s Representative (COR) for all disposed materials whether recycled or sent to a landfill.

1.9 Overnight Camping in the Park: The Contractor, subcontractors, suppliers or others directly or indirectly involved with the project will not be allowed to camp or stay overnight at the construction site.

1.10 Inspection: All work shall be inspected on an ongoing basis by NPS personnel. The Contractor shall provide for and allow complete and unobstructed access to all work areas, processes and elements of the project.

PART 2- SUBMITTALS

The Contractor shall complete and submit the following submittals in a timely fashion (as soon as feasible after award) to the NPS contacts listed below:

· Safety Plan

· Storm Water Pollution Prevention Plan

· Dry Land certificates for barges that will be utilized for the project.

The following items shall be submitted upon completion of the project work:

· Electronic copies of ORCAA notifications and responses

· Weight tickets for recycled materials and for materials sent to landfill

· Listing and approximate weights of any donated materials or supplies

· Chain of custody documentation for any hazardous material disposal

· Receipts for any septic pumping performed.