This document is a Statement of Work (SOW) for the construction of a gabion wall to form a weir in Rio Bonito near the existing Titsworth Ditch diversion structure. The objective is for the contractor to construct a gabion weir that is approximately 3 feet thick, 7 feet high, and 40 feet wide. The work is to be performed on government-owned property located 1 mile west of Lincoln, NM in Lincoln County, with a period of performance of 90 calendar days after issuance of the notice to proceed. The contractor shall construct the facilities in compliance with the provided Technical Specifications and Plans. Key deliverables include submittals for the geotextile fabric and gabion basket and stone fill, which must be approved by the Contracting Officer's Representative (COR) prior to installation. The government will not furnish any equipment for this project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

TITSWORTH DITCH GABION BASKET WEIR

1.0 SCOPE

1.1 Background

The Bureau of Land Management's mission is to sustain the health, diversity, and productivity of public lands for the use and enjoyment of present and future generations. In furtherance of the

Bureau’s mission, BLM has produced plans and specifications to enhance water flow to an irrigation diversion structure serving Titsworth Ditch.

1.2 Objective

The contractor shall construct a gabion wall to form a weir in Rio Bonito near the existing

Titsworth Ditch diversion structure. The gabion weir will be approximately 3 feet thick, 7 feet high (including underground and underwater portions), and 40 feet wide.

1.3 Tasks

Please see Standard Construction Specifications and Construction Plans for Titsworth Ditch

Gabion Basket Weir.

1.4 Inherently Governmental Functions

No contractor shall perform any inherently governmental functions. No function described in this SOW is inherently governmental as defined in FAR 2.101 and FAR 7.5. If any provision of the SOW conflicts with this term, this prohibition shall take precedence.

2.0 Applicable Documents

The following documents form a part of this SOW.

Statement of Work

Titsworth Ditch Gabion Basket Weir Standard Construction Specifications

Titsworth Ditch Gabion Basket Weir Construction Plans

3.0 Deliverables

Submittals Required After Award:

Spec Reference Due

Geotextile Fabric 312000 Must be approved by

COR Before Installation

Gabion Basket and

Stone Fill

313600 and

Specifications

Appendix A

Must be approved by

COR Before Installation

4.0 General Requirements

Contractor shall construct facilities in compliance with Technical Specifications, Plans, and other requirements of Solicitation. All work is considered non-severable as each of work outlined in the technical specifications document is aligned. The period of performance is 90 calendar days after issuance of notice to proceed.

5.0 Place of Performance

The construction identified within this contract will be performed at government-owned property located 1 mile west of Lincoln, NM in Lincoln County. The site is on the north side of US HWY 380, access is from La Cuesta Lane. 33°30'25.6"N 105°24'03.5"W

The site is not access-controlled. No ID badges or security clearances are necessary to access the site or perform work. There is a 10 MPH speed limit on La Cuesta Lane.

6.0 Period of Performance

90 days after issuance of Notice to Proceed.

7.0 Work Schedule

The Contractor shall perform work during normal working hours. Normal working hours are usually from 0700 to 1700 each Monday through Friday (except on legal holidays). Any deviation from normal working hours shall be at the sole discretion of the government and shall require prior written approval.

The contractor will be allowed to store project-related equipment and materials in locations approved by Contracting Officer’s Representative (COR) or Contracting Officer (CO).

Storage shall be at contractor’s own risk.

8.0 Holidays

The Government observes the following holidays:

• New Year's Day, January 1

• Martin Luther King's Birthday, the third Monday in January

• President's Birthday, the third Monday in February

• Memorial Day, the last Monday in May

• Independence Day, July 4

• Juneteenth Day, June 17

• Labor Day, the first Monday in September

• Columbus Day, the second Monday in October

• Veteran's Day, November 11

• Thanksgiving Day, the fourth Thursday in November

• Christmas Day, December 25

The contractor is permitted to observe the above Holidays in accordance with its corporate policy. In the event any of the above holidays occur on a Saturday or Sunday, then such holiday shall be observed in accordance with COR direction.

9.0 Key Personnel

The contractor shall establish a single management focal point to accomplish this contract's administrative, managerial, and financial aspects. This individual will be identified to the COR and

CO as the focal point for all programmatic issues. Within 7 days of the Notice to Proceed, the contractor shall submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities, list cellular telephone numbers and e-mail addresses. Provide names and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.

10.0 Government Furnished Equipment

None.