A04_Scope_of_Work_Sand_Fly_Dock.pdf

PDF 135 KB Posted

Attached to
CONSTRUCTON, REPLACE SANDFLY DOCK, EVER Federal contract opportunity
Solicitation number
140P5422R0005
Issued by
Department of the Interior National Park Service Southeast Region

View the file

Other files for this federal contract opportunity

Other files attached to CONSTRUCTON, REPLACE SANDFLY DOCK, EVER, newest first.
File Type Posted
Questions_140P5422R0005_Replace_Sandfly_Dock_in_Everglades_National_Park_0002.docx DOCX document
Sol_140P5422R0005_Amd_0002.pdf PDF
2021_07_23_Permit_FDEP_397769-001_0002.pdf PDF
2021_02_26_Permit_USACE_SAJ-2021-00234_0002.pdf PDF
B03_Updated_Wage_Rates_0001.pdf PDF
Sol_140P5422R0005_Amd_0001.pdf PDF
Clauses_0001.pdf PDF
B03_DBA_Wage_Rates.pdf PDF
Sol_140P5422R0005.pdf PDF
A06_Sand_Fly_Drawings.pdf PDF
B09_QUESTIONNAIRE.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPLACE SAND FLY KEY DOCK SCOPE OF WORK-1

SCOPE OF WORK—REPLACE SAND FLY KEY DOCK

GENERAL

1.1 SUMMARY

A. This work consists of providing all labor, materials, and equipment to remove an existing dock and install a new dock on Sand Fly Island in the Gulf Coast area of Everglades National Park.

B. The work site is on Sand Fly Island and is only accessible by boat. The site is about 2 and 1/2 miles west of Everglades City, Florida. GPS Coordinates of the site are North 25.8231° Latitude, West 81.3998°Longitude.

C. NPS drawing number 160/174,982 (Replace Sandfly Dock) is part of this scope of work.

1.2 PERMITS

A. The Government has secured permits for this project from the USACE and Florida DEP.

B. The Contractor shall follow all conditions required in these permits including preparing and submitting all follow up paperwork required by the permits. This paperwork including but not limited to the USACE “Commencement Notification” Form and the USACE “Self-Certification Statement of Compliance” form.

C. The paperwork shall be files within the deadlines required in the permit. The Contractor shall provide the Contracting Officer copies of all paperwork at the time it is submitted to the agencies.

1.3 USE OF PREMISES AND WORK RESTRICTIONS

A. Use of Site: Limit use of the premises to the area immediately adjacent to the work site. Do not disturb the site beyond the work area.

B. Preservation of Natural Features: Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

C. Preservation of Cultural Resources:

1. The shallow water area from the MHHW to 25’ water side of the MHHW is a shell mound. The new dock was designed to bridge over this area. Limit activity in this area to removal of the existing piles. Work over and on the land side of this area is expected to be done by equipment that can reach over this area from the water side.

2. Other than the shell mound, no known archeological resources are in this area of this construction. If previously unknown archeological resources are discovered during the work of this project, the Contractor shall immediately stop work in the area of discovery and notify the Contracting Officer. An equitable adjustment will be made in accordance with the Changes clause of the contract.

D. Start of Work Notification: At least two weeks prior to the start of on-site work, the Contractor shall notify the Contracting Officer of the intended start date. This will allow Government personnel to conduct a final review the work site for any issues prior to the start of construction.

REPLACE SAND FLY KEY DOCK SCOPE OF WORK-2

E. Threatened, Endangered and Species of Concern: The following threatened, endangered, and species of concern could be encountered in the project area: Sawfish, Manatees, and Sea Turtles.

1. All work shall be done in daylight hours.

2. All sightings of these species shall be reported to the Contracting Officer.

3. When a threatened or endangered species is present or observed on the work site, work shall be postponed until the individuals leave the area.

4. The Permittee shall comply with the “Standard Manatee Conditions for In-Water Work – 2011”.

5. The Permittee shall comply with National Marine Fisheries Service's “Sea Turtle and

Smalltooth Sawfish Construction Conditions,” dated March 23, 2006.

6. At the start of the project, all on-site employees shall receive training to identify threatened and endangered species which maybe encountered on the site.

F. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday. Requests for any work outside those hours, including weekends and holidays, must be submitted for approval at least 48 hours in advance.

G. Hurricanes: The Government requires closing of operations between 48 and 72 hours of anticipated landfall of a tropical storm or hurricane as determined by the National Park Service. All project materials shall be adequately secured or removed from the site before the closure.

1.4 PRECONSTRUCTION CONFERENCE:

A. Before start of construction, the Contracting Officer will arrange a meeting with the Contractor. The meeting agenda will include the following as a minimum: correspondence procedures, designation of responsible personnel, payments to the Contractor, park rules and regulations, construction schedule, submittals, and project closeout requirements.

1.5 SUBMITTALS

A. All submittals shall be transmitted electronically in PDF or MS Word format.

B. Pre-Construction Submittals:

1. Submit a Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each phase of the work.

2. Submit a Schedule of Values showing the breakdown of the Contract. This breakdown shall include administrative costs, general condition costs, overhead, and profit in the work breakdown items and not as separate items. The Schedule of Values will also form the basis for progress payments.

3. Submit a safety plan per the accident prevention paragraph of this section. The safety plan shall include methods to follow the CDC guidelines to minimize exposure to COVID-19 for workers and the public.

C. Material Submittals:

1. Submittals are required for the following items:

a. Samples: Fiberglass Decking.

b. Manufactures Literature: Fiberglass Decking and Concrete Piles.

c. Warranty: Provide manufacture's written warranty for:

1) Fiberglass Decking.

2) Aluminum Dock Structure.

d. Shop Drawings: Provide shop drawings of the aluminum deck structure and decking.

2. All material submittals shall be transmitted using National Park Service form DSC-1(CS). No action will be taken on a submittal item unless accompanied by the transmittal form.

REPLACE SAND FLY KEY DOCK SCOPE OF WORK-3

3. Provide submittals to the Contracting Officer at least 21 days before need for approval.

4. The Government will return the submittals either approved, approved with notations, or disapproved.

D. Periodic Submittals:

1. Provide quality assurance reports per the quality assurance paragraph of this section.

2. On a weekly basis, provide the Contracting Officer with a two-week look ahead schedule of his intended activities. This schedule can be an informal handwritten paper copy.

E. Post Construction Submittals:

1. Project Record Drawings: Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue.

1.6 ACCIDENT PREVENTION

A. Before on-site work begins, submit a written accident prevention plan containing the following:

1. Identification of personnel responsible for safety at both corporate and project level including on-site personnel.

2. Emergency Response Plan including site specific emergency contact information and location of the nearest emergency room.

3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.

B. The Contractor shall follow all federal, state, and local safety and health requirements

C. The Contractor shall report all accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

D. First Aid Facilities: Provide adequate facilities for the number of employees and the type of construction at the site.

E. Personnel protective equipment: Meet requirements of NIOSH and ANSI.

1.7 QUALITY ASSURANCE

A. The Contractor shall keep daily reports of the construction activity. The form of the report is up to the Contractor, but the report shall include the following information:

1. Date

2. Project Title and Contract Number

3. Contractor’s name and On-site Superintendent’s name

4. General description of weather and ground conditions

5. Number of employees (including sub-contractors) working on-site. Employees shall be listed by job categories.

6. List of equipment working on-site.

7. Description of work performed

8. Any issues arising including disputes, unforeseen circumstances, differing site conditions, delays, accidents, etc.

B. Reports shall be e-mailed to the Contracting Officer on a weekly basis.

REPLACE SAND FLY KEY DOCK SCOPE OF WORK-4

1.8 CONSTRUCTION MATERIALS:

A. All materials shall be Contractor furnished from outside the park.

1.9 DISPOSAL

A. All removed material becomes the property of the Contractor and shall be disposed of outside the park, in accordance with all Federal, State, and local regulatory guidelines

1.10 FIELD VERIFICATION:

A. Field verify all new and existing dimensions affecting the work of this contract before ordering materials. Any discrepancies between construction drawings, construction specifications, and field conditions shall be brought to the attention of the Contracting Officer before work is to be performed. Any work that is performed without notifying the Contracting Officer shall be done at the Contractor's own expense.

PRODUCTS

2.1 PRESTRESSED CONCRETE PILES

A. Material:

1. Type II, Type V, or Type III (with a maximum tricalcium aluminate (C3A) content of 8 percent and low alkali) cement, a minimum cementitious materials content of 658 pounds per cubic yard and a maximum water to cementitious materials ratio of 0.40.

2. Use seven-wire strand conforming to ASTM A416, Grade 270. Use prestressing steel free of grease, oil, wax, paint, soil, dirt, and rust. Do not use prestressing strands or wire having kinks, bends, or other defects. Use 2-1/2 inch minimum cover, including the chamfered corners

3. Concrete Mix Design: Compressive strength shall be 5000 psi at 28 days. A minimum cementitious materials content of 658 pounds per cubic yard and a maximum water to cementitious materials ratio of 0.40.

4. Inspect the product for conformance with the product dimension tolerances shown in Appendix B of PCI Manual MNL-116 (Manual for Quality Control for Plants and Production of Structural Precast Concrete Products).

B. Pile Layout:

1. The pile layout is approximate. The contractor can adjust the exact pile location to fit the design of the aluminum dock structure.

2. Interior piles shown on the drawings can be eliminated if the design of the aluminum structure can bridge over those piles without overloading the remaining piles.

2.2 ROUND WOOD PILE AND PILE WRAP

A. Use of wood piles shall be limited to the pivot pile shown on the drawings.

B. ASTM D25, natural taper. Sizes given are based on tip diameter.

C. Treatment: Chromated Copper Arsenate (2.50 pcf).

REPLACE SAND FLY KEY DOCK SCOPE OF WORK-5

D. Sheeting Wrap: 60 mil polyethylene.

E. Reflective Tape for Wood Piles: High Intensity Reflective Tape, ASTM D4956 Type III, Class 1 pressure-sensitive adhesive, white, 6-inch wide roll.

F. Pile Cap for Wood Piles: PVC cap, size to fit piles.

G. Nails: 316 stainless steel roofing nails.

2.3 ALUMINUM DOCK STRUCTURE

A. The Contractor shall provide a dock structure to the dimensions shown on the plans and designed to meet the following criteria:

1. Live Load: 100 psf (pounds per square foot)

2. Dead Load: Per Contractors Design.

3. Winds Loads:

a. Lateral pressure applied to the side of structure: 90 psf. This load only applies to parts of the structure above the top of the deck.

b. Uplift of deck: 60 psf

c. Downward on deck: 60 psf

4. Lateral Wave Load to side of structure: 230 psf. This load only applies to parts of the structure below the top of the deck.

5. The Contractor shall be responsible for the design of the connection to the concrete piles.

6. The Contractor deck structure shall not cause loadings on the piles that exceeds the limits of the

Government provided design as listed in these specifications.

7. The structure shall support the grating so under the live design load, the maximum deflection of the grating is less than the Span Length divided by 180.

B. Design of the piles is provided by the Government. When installed as shown and specified, the dock designer can assume each pile can be loaded to the following limits:

1. Vertical Pile Load: 20,000 pounds

2. Vertical Pile Uplift: 10,000 pounds

3. Horizontal lateral load at the top of the pile: 3,000 pounds

C. Materials: 6061 T6 Marine Grade Aluminum and 316 Stainless Fasteners.

D. Fabrication: The aluminum structure shall be manufactured by welders certified by the American Welding Association and fabricated under strict guidelines set forth by ISO 9001.

E. Warranty: The Manufacturer/Fabricator shall provide a 10-year limited warranty against defects in the dock structure.

F. Details:

1. The exterior frame of the aluminum structure shall be made with rectangular sections or c-channels with the flat side facing out, so the side of the structure has a flat vertical face.

2. The aluminum frame shall have a lip approximately the height of the grating depth to cover the outer edge of the grading.

3. The railings on the 40-foot gangway and all other railing locations shown on the drawings, shall have handrails meeting Architectural Barriers Act accessibility standards.

G. The manufacture of the deck structure shall be Golden Marine Systems, LLC, North Fort Myers, Florida or approved equal.

REPLACE SAND FLY KEY DOCK SCOPE OF WORK-6

2.4 FIBERGLASS DECKING

A. Fiberglass grating with a minimum 60% open area for light transmittance. Open area calculation must include both load and cross bars.

B. Must be ADA compliant with a maximum open space between load bars of 1/2 inch.

C. Gating shall be manufactured with a barefoot friendly aqua-grit (sugar grit) to the top surface of each bar providing slip resistance.

D. Load/Deflection: Maximum deflection of 0.167 inches with a uniform distributed load of 100 pounds per square foot at 30-inch clear span.

E. All finished surfaces of fiberglass items shall be smooth, resin-rich, free of voids and without dry spots, cracks, crazes or unreinforced areas. All glass fibers shall be well covered with resin to protect against their exposure due to wear or weathering.

F. All mechanical grating clips shall be manufactured of Type 316SS (stainless steel).

G. Manufacturer’s 3-year limited warranty against defects in materials and workmanship.

H. Manufacturer shall be certified to the ISO 9001 standard.

I. Ecograte 62 Molded Grating as manufactured by Fibergrate Composite Structures or approved equal.

2.5 HARDWARE

A. Hardware including bolts, nuts, anchors, washers, screws, and nails shall be 316 stainless steel.

2.6 LADDER

A. Welded marine grade aluminum construction, U-shaped railings that extends above the deck, 4 steps, 2” deep flat rungs with nonslip surface. 18” minimum width, and 500 lbs. minimum load rating.

2.7 PORTABLE TOILET

A. Government Provided. Savage and Store the existing portable toilet. Reinstall on the new dock.

EXECUTION

3.1 DEMOLITION

A. The existing dock shall be cut up into removable pieces and transported for disposal as required in the disposal section of these specifications. The existing piles shall be pulled and removed.

3.2 ROUND WOOD PILE AND PILE WRAP

A. Install piles to the depth shown on the drawings.

REPLACE SAND FLY KEY DOCK SCOPE OF WORK-7

B. Piles shall be installed plumb to within 1 inch in 10'.

C. Piles shall be installed without splices.

D. In rock, the pile shall be installed in a pre-drilled hole not greater that the pile diameter.

E. Attached pile cap with a minimum of (4) #10 x 3/4” stainless steel screws or stainless steel roofing nails. The cap shall fit the piling naturally without having to modify the pile cap in any fashion to forcefully fit the pile diameter (e.g. splitting a cap to fit a larger diameter piling than the pile cap was designed to fit).

F. Install pile wrap from the mud line to 1’ above MHHW. Overlap seams a minimum of 6 inches.

Connect to the pile with stainless steel roofing nails spaced at 2-inch on center along all edges and seams.

3.3 CONCRETE PILES

A. Prior to driving piles, cut off and patch embedded lifting loops using materials and methods as recommended by the manufacturer.

B. Piles shall be installed to the depth shown on the drawings by driving into per-drilled holes. The pre-drilled hole diameter shall not be greater than 90 percent of the average cross-sectional dimension of the pile.

C. The pile shall be plumb to within 1 inch in 10'.

D. Piles shall be installed without splices.

3.4 BOLTS

A. Bolt holes shall be a minimum of 1/32" to a maximum of 1/16" larger that the diameter of the bolt.

B. When installed and tightened, at least 2 full threads shall be exposed beyond the nut.

3.5 DECKING

A. Install decking in accordance with manufacturer's instructions.

B. All field fabricated grating cuts shall be coated by the contractor in accordance with the manufacturer's instructions and approved sealers.

C. Field cut and drill fiberglass reinforced plastic products with carbide or diamond tipped bits and blades. Panels shall be installed in as large of pieces as available to minimize seams.

D. Panels shall be attached to the structure with a minimum of two clips at each end. If the panel is more than 4 feet long, intermediate rows shall be added so the spacing between rows is less than 4 feet.

REPLACE SAND FLY KEY DOCK SCOPE OF WORK-8

3.6 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish.

At the time of final inspection, project shall be thoroughly clean and ready for use.

B. Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.

C. If the project is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.

D. After all deficiencies have been corrected, a Letter of Acceptance will be issued.

END OF SCOPE

PART 1 - GENERAL
1.1 SUMMARY
A. This work consists of providing all labor, materials, and equipment to remove an existing dock and install a new dock on Sand Fly Island in the Gulf Coast area of Everglades National Park.
B. The work site is on Sand Fly Island and is only accessible by boat. The site is about 2 and 1/2 miles west of Everglades City, Florida. GPS Coordinates of the site are North 25.8231 Latitude, West 81.3998 Longitude.
C. NPS drawing number 160/174,982 (Replace Sandfly Dock) is part of this scope of work.
1.2 PERMITS
A. The Government has secured permits for this project from the USACE and Florida DEP.
B. The Contractor shall follow all conditions required in these permits including preparing and submitting all follow up paperwork required by the permits. This paperwork including but not limited to the USACE “Commencement Notification” Form and the...
C. The paperwork shall be files within the deadlines required in the permit. The Contractor shall provide the Contracting Officer copies of all paperwork at the time it is submitted to the agencies.
1.3 USE OF PREMISES AND WORK RESTRICTIONS
A. Use of Site: Limit use of the premises to the area immediately adjacent to the work site. Do not disturb the site beyond the work area.
B. Preservation of Natural Features: Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
C. Preservation of Cultural Resources:
1. The shallow water area from the MHHW to 25’ water side of the MHHW is a shell mound. The new dock was designed to bridge over this area. Limit activity in this area to removal of the existing piles. Work over and on the land side of this area is...
2. Other than the shell mound, no known archeological resources are in this area of this construction. If previously unknown archeological resources are discovered during the work of this project, the Contractor shall immediately stop work in the are...
D. Start of Work Notification: At least two weeks prior to the start of on-site work, the Contractor shall notify the Contracting Officer of the intended start date. This will allow Government personnel to conduct a final review the work site for an...
E. Threatened, Endangered and Species of Concern: The following threatened, endangered, and species of concern could be encountered in the project area: Sawfish, Manatees, and Sea Turtles.
1. All work shall be done in daylight hours.
2. All sightings of these species shall be reported to the Contracting Officer.
3. When a threatened or endangered species is present or observed on the work site, work shall be postponed until the individuals leave the area.
4. The Permittee shall comply with the “Standard Manatee Conditions for In-Water Work – 2011”.
5. The Permittee shall comply with National Marine Fisheries Service's “Sea Turtle and Smalltooth Sawfish Construction Conditions,” dated March 23, 2006.
6. At the start of the project, all on-site employees shall receive training to identify threatened and endangered species which maybe encountered on the site.
F. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday. Requests for any work outside those hours, including weekends and holidays, must be submitted for approva...
G. Hurricanes: The Government requires closing of operations between 48 and 72 hours of anticipated landfall of a tropical storm or hurricane as determined by the National Park Service. All project materials shall be adequately secured or removed fro...
1.4 PRECONSTRUCTION CONFERENCE:
A. Before start of construction, the Contracting Officer will arrange a meeting with the Contractor. The meeting agenda will include the following as a minimum: correspondence procedures, designation of responsible personnel, payments to the Contrac...
1.5 SUBMITTALS
A. All submittals shall be transmitted electronically in PDF or MS Word format.
B. Pre-Construction Submittals:
1. Submit a Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each phase of the work.
2. Submit a Schedule of Values showing the breakdown of the Contract. This breakdown shall include administrative costs, general condition costs, overhead, and profit in the work breakdown items and not as separate items. The Schedule of Values will ...
3. Submit a safety plan per the accident prevention paragraph of this section. The safety plan shall include methods to follow the CDC guidelines to minimize exposure to COVID-19 for workers and the public.
C. Material Submittals:
1. Submittals are required for the following items:
a. Samples: Fiberglass Decking.
b. Manufactures Literature: Fiberglass Decking and Concrete Piles.
c. Warranty: Provide manufacture's written warranty for:
1) Fiberglass Decking.
2) Aluminum Dock Structure.

d. Shop Drawings: Provide shop drawings of the aluminum deck structure and decking.

2. All material submittals shall be transmitted using National Park Service form DSC-1(CS). No action will be taken on a submittal item unless accompanied by the transmittal form.
3. Provide submittals to the Contracting Officer at least 21 days before need for approval.
4. The Government will return the submittals either approved, approved with notations, or disapproved.
D. Periodic Submittals:
1. Provide quality assurance reports per the quality assurance paragraph of this section.
2. On a weekly basis, provide the Contracting Officer with a two-week look ahead schedule of his intended activities. This schedule can be an informal handwritten paper copy.
E. Post Construction Submittals:
1. Project Record Drawings: Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue.
1.6 ACCIDENT PREVENTION
A. Before on-site work begins, submit a written accident prevention plan containing the following:
1. Identification of personnel responsible for safety at both corporate and project level including on-site personnel.
2. Emergency Response Plan including site specific emergency contact information and location of the nearest emergency room.
3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.
B. The Contractor shall follow all federal, state, and local safety and health requirements
C. The Contractor shall report all accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
D. First Aid Facilities: Provide adequate facilities for the number of employees and the type of construction at the site.
E. Personnel protective equipment: Meet requirements of NIOSH and ANSI.
1.7 QUALITY ASSURANCE
A. The Contractor shall keep daily reports of the construction activity. The form of the report is up to the Contractor, but the report shall include the following information:
1. Date
2. Project Title and Contract Number
3. Contractor’s name and On-site Superintendent’s name
4. General description of weather and ground conditions
5. Number of employees (including sub-contractors) working on-site. Employees shall be listed by job categories.
6. List of equipment working on-site.
7. Description of work performed
8. Any issues arising including disputes, unforeseen circumstances, differing site conditions, delays, accidents, etc.

B. Reports shall be e-mailed to the Contracting Officer on a weekly basis.

1.8 CONSTRUCTION MATERIALS:
A. All materials shall be Contractor furnished from outside the park.
1.9 DISPOSAL
A. All removed material becomes the property of the Contractor and shall be disposed of outside the park, in accordance with all Federal, State, and local regulatory guidelines
1.10 FIELD VERIFICATION:
A. Field verify all new and existing dimensions affecting the work of this contract before ordering materials. Any discrepancies between construction drawings, construction specifications, and field conditions shall be brought to the attention of the ...
PART 2 - PRODUCTS
2.1 PRESTRESSED CONCRETE PILES
A. Material:
1. Type II, Type V, or Type III (with a maximum tricalcium aluminate (C3A) content of 8 percent and low alkali) cement, a minimum cementitious materials content of 658 pounds per cubic yard and a maximum water to cementitious materials ratio of 0.40.
2. Use seven-wire strand conforming to ASTM A416, Grade 270. Use prestressing steel free of grease, oil, wax, paint, soil, dirt, and rust. Do not use prestressing strands or wire having kinks, bends, or other defects. Use 2-1/2 inch minimum cover, in...
3. Concrete Mix Design: Compressive strength shall be 5000 psi at 28 days. A minimum cementitious materials content of 658 pounds per cubic yard and a maximum water to cementitious materials ratio of 0.40.
4. Inspect the product for conformance with the product dimension tolerances shown in Appendix B of PCI Manual MNL-116 (Manual for Quality Control for Plants and Production of Structural Precast Concrete Products).
B. Pile Layout:
1. The pile layout is approximate. The contractor can adjust the exact pile location to fit the design of the aluminum dock structure.
2. Interior piles shown on the drawings can be eliminated if the design of the aluminum structure can bridge over those piles without overloading the remaining piles.
2.2 ROUND WOOD PILE AND PILE WRAP
A. Use of wood piles shall be limited to the pivot pile shown on the drawings.
B. ASTM D25, natural taper. Sizes given are based on tip diameter.
C. Treatment: Chromated Copper Arsenate (2.50 pcf).
D. Sheeting Wrap: 60 mil polyethylene.
E. Reflective Tape for Wood Piles: High Intensity Reflective Tape, ASTM D4956 Type III, Class 1 pressure-sensitive adhesive, white, 6-inch wide roll.
F. Pile Cap for Wood Piles: PVC cap, size to fit piles.
G. Nails: 316 stainless steel roofing nails.
2.3 ALUMINUM DOCK STRUCTURE
A. The Contractor shall provide a dock structure to the dimensions shown on the plans and designed to meet the following criteria:
1. Live Load: 100 psf (pounds per square foot)
2. Dead Load: Per Contractors Design.
3. Winds Loads:
a. Lateral pressure applied to the side of structure: 90 psf. This load only applies to parts of the structure above the top of the deck.
b. Uplift of deck: 60 psf
c. Downward on deck: 60 psf
4. Lateral Wave Load to side of structure: 230 psf. This load only applies to parts of the structure below the top of the deck.
5. The Contractor shall be responsible for the design of the connection to the concrete piles.
6. The Contractor deck structure shall not cause loadings on the piles that exceeds the limits of the Government provided design as listed in these specifications.
7. The structure shall support the grating so under the live design load, the maximum deflection of the grating is less than the Span Length divided by 180.
B. Design of the piles is provided by the Government. When installed as shown and specified, the dock designer can assume each pile can be loaded to the following limits:
1. Vertical Pile Load: 20,000 pounds
2. Vertical Pile Uplift: 10,000 pounds
3. Horizontal lateral load at the top of the pile: 3,000 pounds
C. Materials: 6061 T6 Marine Grade Aluminum and 316 Stainless Fasteners.
D. Fabrication: The aluminum structure shall be manufactured by welders certified by the American Welding Association and fabricated under strict guidelines set forth by ISO 9001.
E. Warranty: The Manufacturer/Fabricator shall provide a 10-year limited warranty against defects in the dock structure.
F. Details:
1. The exterior frame of the aluminum structure shall be made with rectangular sections or c-channels with the flat side facing out, so the side of the structure has a flat vertical face.
2. The aluminum frame shall have a lip approximately the height of the grating depth to cover the outer edge of the grading.
3. The railings on the 40-foot gangway and all other railing locations shown on the drawings, shall have handrails meeting Architectural Barriers Act accessibility standards.

G. The manufacture of the deck structure shall be Golden Marine Systems, LLC, North Fort Myers, Florida or approved equal.

2.4 FIBERGLASS DECKING
A. Fiberglass grating with a minimum 60% open area for light transmittance. Open area calculation must include both load and cross bars.
B. Must be ADA compliant with a maximum open space between load bars of 1/2 inch.
C. Gating shall be manufactured with a barefoot friendly aqua-grit (sugar grit) to the top surface of each bar providing slip resistance.
D. Load/Deflection: Maximum deflection of 0.167 inches with a uniform distributed load of 100 pounds per square foot at 30-inch clear span.
E. All finished surfaces of fiberglass items shall be smooth, resin-rich, free of voids and without dry spots, cracks, crazes or unreinforced areas. All glass fibers shall be well covered with resin to protect against their exposure due to wear or wea...
F. All mechanical grating clips shall be manufactured of Type 316SS (stainless steel).
G. Manufacturer’s 3-year limited warranty against defects in materials and workmanship.
H. Manufacturer shall be certified to the ISO 9001 standard.
I. Ecograte 62 Molded Grating as manufactured by Fibergrate Composite Structures or approved equal.
2.5 HARDWARE
A. Hardware including bolts, nuts, anchors, washers, screws, and nails shall be 316 stainless steel.
2.6 LADDER
A. Welded marine grade aluminum construction, U-shaped railings that extends above the deck, 4 steps, 2” deep flat rungs with nonslip surface. 18” minimum width, and 500 lbs. minimum load rating.
2.7 PORTABLE TOILET
A. Government Provided. Savage and Store the existing portable toilet. Reinstall on the new dock.
PART 3 - EXECUTION
3.1 DEMOLITION
A. The existing dock shall be cut up into removable pieces and transported for disposal as required in the disposal section of these specifications. The existing piles shall be pulled and removed.
3.2 ROUND WOOD PILE AND PILE WRAP
A. Install piles to the depth shown on the drawings.
B. Piles shall be installed plumb to within 1 inch in 10'.
C. Piles shall be installed without splices.
D. In rock, the pile shall be installed in a pre-drilled hole not greater that the pile diameter.
E. Attached pile cap with a minimum of (4) #10 x 3/4” stainless steel screws or stainless steel roofing nails. The cap shall fit the piling naturally without having to modify the pile cap in any fashion to forcefully fit the pile diameter (e.g. split...
F. Install pile wrap from the mud line to 1’ above MHHW. Overlap seams a minimum of 6 inches. Connect to the pile with stainless steel roofing nails spaced at 2-inch on center along all edges and seams.
3.3 CONCRETE PILES
A. Prior to driving piles, cut off and patch embedded lifting loops using materials and methods as recommended by the manufacturer.
B. Piles shall be installed to the depth shown on the drawings by driving into per-drilled holes. The pre-drilled hole diameter shall not be greater than 90 percent of the average cross-sectional dimension of the pile.
C. The pile shall be plumb to within 1 inch in 10'.
D. Piles shall be installed without splices.
3.4 BOLTS
A. Bolt holes shall be a minimum of 1/32" to a maximum of 1/16" larger that the diameter of the bolt.
B. When installed and tightened, at least 2 full threads shall be exposed beyond the nut.
3.5 DECKING
A. Install decking in accordance with manufacturer's instructions.
B. All field fabricated grating cuts shall be coated by the contractor in accordance with the manufacturer's instructions and approved sealers.
C. Field cut and drill fiberglass reinforced plastic products with carbide or diamond tipped bits and blades. Panels shall be installed in as large of pieces as available to minimize seams.
D. Panels shall be attached to the structure with a minimum of two clips at each end. If the panel is more than 4 feet long, intermediate rows shall be added so the spacing between rows is less than 4 feet.
3.6 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. At the time of final inspection, project shall be thoroughly clean and ready for use.
B. Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.
C. If the project is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.
D. After all deficiencies have been corrected, a Letter of Acceptance will be issued.