A04 Performance Work Statement.pdf
PDF 338 KB Posted
- Solicitation number
- 12RADA26Q0017
About this file
This is a Performance Work Statement (PWS) for the demolition of the Grape Genetic Research Unit (GGRU) Administration Building and related structures at the USDA facility in Geneva, NY.
The project scope involves complete demolition and removal of concrete slabs, walls, footers, and equipment pads from the former GGRU Administration Building (Building No. 74), former greenhouse with surrounding sidewalk, equipment support pads (propane tanks, HVAC, generator), mechanical equipment yard, and associated utilities. Specific tasks include: removing sanitary sewer lines back to the main manhole and sealing; sealing two storm sewer lines with hydraulic cement at catch basins and installing stormwater filter socks; re-sealing or capping utilities after slab removal; filling and compacting all excavations in 12-inch lifts using existing or additional compacted gravel fill; grading and leveling disturbed earth to match surrounding elevations; topping the site with loam, fertilizer, grass seed, and mulch using either "Seedway" Tri Rye Blend or "Pennington Contractor Mix" seed or hydroseeding; safely disposing of all demolition materials off-site; and repairing any damage caused by the contractor's workforce. All work occurs at 93 Collier Drive, Geneva, NY 14456, during normal business hours (7:30 am–4:00 pm, Monday–Friday) with coordination required through the location coordinator.
The contractor must provide a proposed project plan with solicitation response and weekly status reports every Friday by 3:00 PM ET until contract expiration. The onsite Project Manager requires a minimum of five years' experience in demolition, site grading, utility sealing, landscaping, and construction safety protocols. Performance is measured through site inspections against standards for complete demolition, proper disposal, utility sealing, site grading/restoration, landscaping/erosion control, physical security, and quality standards compliance, with evaluation criteria of "Exceptional past performance" or "Marginal/Unsatisfactory." Invoices must be submitted via the Invoice Processing Platform (http://www.ipp.gov/vendors/index.htm) and include required documentation including contract number, description and quantity of services, business information, TIN/DUNS+4, and certification that funds were used solely for contract work, with final invoices clearly marked upon completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_12RADA26Q0017_Amd_0002.pdf | ||
| Sol_12RADA26Q0017_Amd_0001.pdf | ||
| A04 PWS Attachment 1 Site Plan Geneva Bldg 74.pdf | ||
| SOL 1449 _12RADA26Q0017.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Demolish Genetic Research Unit (GGRU) Administration Building Foundation
Performance Work Statement
Contents Project Title General Information
1.0 Background and Purpose
2.0 Acronyms / Definitions
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Deliverable / Schedule
5.0 Government Furnished
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Reserved
10.0Reserved
11.0 Performance Requirement Measures
12.0 Invoicing Instructions
Attachment
Project Title Demolition of Grape Genetic Research Unit (GGRU) Administration Building Foundations
General Information
1.0 Background and Purpose
The Grape Genetic Research Unit (GGRU) Administration Building at the USDA facility in Geneva, NY, has remnants of structural elements—including concrete slabs, walls, and foundations—from previous demolition activities, as well as associated infrastructure from the former greenhouse, mechanical equipment yard, and equipment pads. These materials hinder future site use and pose safety and environmental concerns. The purpose of this Performance Work Statement is to outline the requirements for complete demolition and removal of all remaining structures, ensuring safe disposal, proper site re-grading, and restoration with appropriate landscaping. This project will prepare the site for future development or research activities, aligning with USDA operational standards and supporting ongoing agricultural research needs.
2.0 Acronyms / Definitions
GGRU: Grape Genetic Research Unit USDA: United States Department of Agriculture Catch basin - A drainage structure that collects stormwater and prevents sediment from entering sewer lines.
Compacted gravel fill - Gravel used to fill excavations, compacted in layers to provide stability and match surrounding grade.
Hydroseeding - A planting process that uses a slurry of seed and mulch, sprayed over prepared ground to promote rapid grass growth.
Stormwater filter sock - A tubular filter placed around catch basins to prevent sediment runoff during construction.
Contractor Requirements
3.0 Technical Requirements / Tasks
3.1 Remove concrete slab, walls, and footers from the former GGRU Administration Building ("Germplasm Repository Building No. 74")
3.2 Remove concrete slab, walls, and footers from the former Greenhouse, including the surrounding sidewalk.
3.3 Remove all concrete slabs that formerly supported equipment (propane tanks, HVAC, generator), including the pad northeast of Building 74; cap conduits above grade.
3.4Remove slab and fence post bases from the former Mechanical Equipment yard, west of Building 74.
3.5 Remove sanitary sewer line back to the main sewer manhole; seal manhole penetrations.
3.6 Seal two storm sewer lines (formerly fed by roof drains) with hydraulic cement at catch basins; install stormwater filter sock around catch basin perimeter.
3.7 Re-seal or cap utilities as required after slab removal.
3.8 Fill and compact all excavations in 12-inch lifts; use existing excavated material or provide additional compacted gravel fill as needed.
3.9 Grade, smooth, and level disturbed earth to match surrounding elevations.
3.10 Top disturbed earth with loam, fertilizer, grass seed, and mulch (straw); use specified seed blends (“Seedway” Tri Rye Blend or “Pennington Contractor Mix”) or hydroseeding.
3.11 Safely dispose of all demolition materials off-site.
3.12 Repair or replace any damage caused by contractor’s workforce.
4.0 Deliverable / Schedule
All work will be performed at 93 Collier Drive, Geneva, NY 14456
Coordinate deliveries and work schedules with the location coordinator; comply with normal hours of operation (7:30 am–4:00 pm, Monday–Friday)
Key Deliverables Item No. Deliverable Objective Due 1 Proposed Project Plan Defining the responsibilities, timeline, risks and milestones of contract objectives.
With Solicitation Response
2 Weekly Status Report Report documenting tasks & issues weekly. Weekly, every Friday, by 3:00 PM ET until the contract expires
5.0 Government Furnished
Government Furnished access Coordinate deliveries and work schedules with the location coordinator; comply with normal hours of operation (7:30 am–4:00 pm, Monday–Friday)
6.0 Travel
All travel and transportation is responsibility of the contractor.
7.0 Contractor’s Key Personnel
Onsite Project Manager shall have a minimum of 5 years experience in demolition, site grading, utility sealing, landscaping, and construction safety protocols, as well as strong organizational and communication skills for effective coordination and compliance
8.0 Security Requirements
All work, including deliveries, must be scheduled and approved in advance with the location coordinator. Work is restricted to normal hours of operation (7:30 am–4:00 pm, Monday–Friday), ensuring controlled access and oversight during project activities
9.0 Reserved
10.0Reserved
11.0 Performance Requirement Measures
Performance Objective
Required Task or Deliverable
Performance Standard Method of Surveillance
Positive/Negative Incentive % for NOT meeting the Task
Complete Demolition of Structural Remnants
See 3.0 All concrete slabs, walls, footers, and equipment pads from the former administration building, greenhouse, mechanical equipment yard, and related areas must be fully removed. No remnants should remain on site.
Random Site Inspection
Will result in Exceptional past performance. Not meeting = Marginal/Unsatisfactory.
Proper Dispospoal of Demolition Materials
See 3.0 All demolition materials must be hauled off-site and disposed of in accordance with safety and environmental regulations. No debris or hazardous materials may be left behind.
Random Site Inspection
Will result in Exceptional past performance. Not meeting = Marginal/Unsatisfactory.
Utility Sealing and Removal
See 3.0 Sanitary sewer lines must be removed back to the main manhole and sealed; storm sewer lines must be sealed with hydraulic cement at catch basins.
Random Site Inspection
Will result in Exceptional past performance. Not meeting = Marginal/Unsatisfactory.
Utilities exposed after slab removal must be re-sealed or capped as required.
Site Grading and Restoration
See 3.0 The disturbed earth must be graded, smoothed, and leveled to match surrounding elevations.
All excavations must be filled and compacted in 12-inch lifts, using existing material or additional compacted gravel fill as needed.
Site Inspection
Will result in Exceptional past performance. Not meeting = Marginal/Unsatisfactory.
Landscaping and Erosion Control
See 3.0 The site must be topped with loam, fertilizer, grass seed, and mulch (straw), using specified seed blends (“Seedway” Tri Rye Blend or “Pennington Contractor Mix”) or hydroseeding.
Stormwater filter socks must be installed around catch basins to prevent sediment runoff.
Site Inspection
Will result in Exceptional past performance. Not meeting = Marginal/Unsatisfactory.
Physical Security and Damage Repair
See 3.0 The contractor is responsible for the safe disposal of all items and must repair or replace any damages caused by their workforce during the project.
Site Inspection
Will result in Exceptional past performance. Not meeting = Marginal/Unsatisfactory.
Adherence to Quality Standards
See 3.0 All tasks must comply with relevant demolition, disposal, site restoration, and safety standards, ensuring quality workmanship and regulatory compliance throughout the project.
Site Inspection
Will result in Exceptional past performance. Not meeting = Marginal/Unsatisfactory.
12.0 Invoicing Instructions
Invoices shall be submitted to: http://www.ipp.gov/vendors/index.htm in accordance with the "Authorized Payment Schedule" for each contract/task order. To constitute a proper invoice, the invoice must include the following information and/or attached documentation:
1. Name and address of the business concern
2. Invoice number and invoice date
3. Contract number, Delivery Order number, Purchase Order number, Task Order number, or other authorization for delivery of property or services actually delivered or rendered
4. Description, unit price, extended price, and quantity of property and services actually delivered or rendered documentation (i.e. travel receipts, etc.)
5. Shipping and payment terms
6. Name, title, phone number, and complete mailing address of responsible official to whom payment is to be sent
7. A certification statement saying that the funds have only been used for work for this contract
8. Name, title, phone number, and mailing address of person to notify in the event of a defective invoice
9. Taxpayer Identification Number (TIN) or DUNS+4; and http://www.ipp.gov/vendors/index.htm
10. Contractors MUST note FINAL INVOICE on the final invoice when submitted upon final delivery of all supplies/equipment/services or completion of the contract.
USDA and the Invoice Processing Platform (IPP) - http://www.ipp.gov/vendors/index.htm
The IPP is a government-wide secure web-based payment information service offered free of charge to government agencies and their suppliers by the U.S. Department of Treasury's Financial Management Service (FMS).
One-time enrollment in IPP means that you will receive a series of e-mails from Treasury services.
The first email will have the IPP Logon ID and link to the IPP application. A second e-mail, containing the password will be sent within 24 hours. Once you receive these emails, please login to the IPP application and complete the registration process.
Benefits of registering with IPP include the ability for your company to create invoices directly from a contract and submit them electronically, as well as:
1. e-mail notification when invoice(s) are paid
2. online payment history
3. remittance download
The e-mail notification of payment is sent when a payment is distributed to the COR when payment is distributed.
The Contracting Officer is the only person authorized to approve changes in any of the requirements of this contract. This authority remains solely with the Contracting Officer. In the event the Contractor effects any change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority, and NO adjustment will be made in the contract price to cover any INCREASE in costs incurred as a result thereof.
Attachment Attachment 1 – Drawings/Depiction of work Requirements.
| Project Title |
| General Information |
| 1.0 Background and Purpose |
| 2.0 Acronyms / Definitions |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Deliverable / Schedule |
| 5.0 Government Furnished |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Reserved |
| 10.0Reserved |
| 11.0 Performance Requirement Measures |
| 12.0 Invoicing Instructions |
| Attachment |
File details come from the government source that posted it. Updated .