This is Amendment 0002 to Solicitation 12RADA26Q0017 issued by USDA Rural Development Procurement Management Office on September 22, 2026, with an effective date of September 22, 2026. The amendment provides clarifications and answers to 16 questions regarding the demolition and site restoration project scope, pricing structure, and project requirements.

The amendment clarifies that contractors must provide one lump-sum price for the entire project with supporting breakdowns for items 0001A through 0001K, with all demolition and disposal work (Building 74 foundations, greenhouse foundations, mechanical yard slab/post bases, and miscellaneous equipment pads) included in the lump sum. Key clarifications address quantity confirmations (sidewalk quantity estimated by contractor from site plan; backfill items as separate quantities with contractor responsible for estimating total fill needed), concrete slab specifications (thicknesses and dimensions unknown; contractor to estimate from site plan), sanitary sewer removal details (pipe specifications unknown; contractor to estimate), manhole sealing procedures (two separate manholes to be sealed permanently with material matching existing construction), and transformer pad removal (located northeast of Building 74; transformer already removed and disconnected). The amendment confirms no project-specific dust control requirements exist, onsite water is available per FAR 52.236-14, restoration loam/topsoil depth to be estimated by contractor, compaction responsibility assigned to contractor per 12-inch lifts, and that a qualified working foreman may serve as onsite Project Manager while performing field duties. The prevailing wage determination number 2015-4161 Revision 35 applies. The period of performance is September 29, 2026 to November 27, 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12RADA26Q0017

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

WASHINGTON DC 20250

RD-31ME

1400 INDEPENDENCE AVE, SW

RURAL DEVELOPMENT BUSINESS CENTER

PROCUREMENT MANAGEMENT OFFICE

USDA, RURAL DEVELOPMENT

09/22/20260002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

09/22/2026

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

1. Schedule of Items / CLIN 0001: Is 0001 one lump-sum price for the entire project, with

0001A¿0001K included as a supporting breakdown, or should 0001 be priced separately and added to the lettered items? Please confirm how the Unit Cost, Total, Lump Sum, and final

TOTAL fields should be completed.

1A-Provide one lump sum for the project.

2. Main demolition scope: Where should demolition and disposal of the Building 74 foundations, greenhouse foundations, mechanical yard slab/post bases, and miscellaneous equipment pads be priced within the schedule?

2A-Provide one lump sum for the project.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

GARY D. BROWN

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12RADA26Q0017/0002

3. Item 0001H Sidewalk: Please confirm whether the listed quantity of 84 CY is correct or should be 84 SY or another quantity/unit. Contractor to provide one lump sum for the project.

3A-Contractor shall estimate quantities used

Attachment 1 Site Plan with listed dimensions.

4. Items 0001E and 0001I ¿ Backfill: Are the 54 CY and 50 CY separate, additional quantities?

Please identify the areas covered by each and confirm whether additional fill needed to restore the entire site must be included in the lump-sum price. Contractor to provide one lump sum for the project.

4A-Contractor shall estimate quantities used

Attachment 1 Site Plan with listed dimensions.

5. Existing concrete: Are slab thicknesses, footing dimensions/depths, or previous foundation drawings available?

5A-Thicknesses, dimensions, depths are unknown.

Contractor to estimate based on Attachment 1 Site

Plan.

6. Sanitary sewer removal: Please provide the pipe size, material, and burial depth.

6A-Unknown. Contractor to estimate based on

Attachment 1 Site Plan.

7. Item 0001C Sanitary manhole penetrations: Are the two penetrations in one manhole or separate manholes? Please identify their locations, opening sizes, and depths. Will sealing require manhole entry, or can it be completed from the exterior? Please confirm the required permanent sealing method and provide photographs, if available.

7A-Two separate manholes shall be sealed after the existing connecting pipe is removed. Seal shall be permanent and waterproof. Seal material shall match existing manhole construction material ( i.e. hydraulic cement-based mortar and brick).

8. Item 0001D ¿ Transformer pad: Is this the pad northeast of Building 74 identified in the PWS?

Does the listed 1 CY include all concrete, including any below-grade foundation? Please provide dimensions and photographs, and confirm whether the transformer has been removed and

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

3 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12RADA26Q0017/0002

associated electrical services disconnected.

8A - Yes, transformer pad is located northeast of

Building 74. Transformer has been removed and disconnected. The contractor is responsible for confirming utility disconnection prior to beginning work.

9. Utility caps: Please confirm the number, sizes, and materials of conduits/utilities requiring caps, the acceptable permanent closure method, and whether all affected utilities have been disconnected and verified inactive.

9A - At this point cap material and sizes quantities vary, and require closure in accordance with industry standard using material similar to existing materials.

10. Dust suppression and water: Are there project-specific dust-control requirements? Is onsite water available for contractor use, or must the contractor furnish and haul water?

10A-No dust control requirements. Contractor will be allowed use to water onsite in accordance with

52.236-14 Availability and use of Utility

Services.

11. Restoration: Please confirm the required loam/topsoil depth and anticipated restoration area. Main concern is to prevent erosion until site will undergo construction. 4-6¿ loam preferred.

11A - For restoration area, contractor shall estimate based upon Attachment 1 site plan.

12. Fill and compaction: Are there fill material specifications, required compaction percentages, or testing requirements beyond placement in

12-inch lifts? If testing is required, who provides and pays for it?

12A - The contractor is responsible for compaction after each 12 inch lift is placed.

13. Onsite Project Manager: May a qualified working foreman serve as the onsite Project

Manager while also performing field duties, provided they meet the PWS experience requirements?

13A - Yes.

14. Current site conditions: Are recent site Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

4 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12RADA26Q0017/0002

photographs or a site walkthrough available showing the remaining slabs, walls, footings, equipment pads, and utility connections?

14A - No photos are available.

15. Site protection and access: Is temporary construction fencing required? Please identify available equipment staging areas, truck access restrictions, and pavement protection requirements.

15A - Site is currently fenced off. Staging area and parking is available adjacent to work area.

16. Prevailing wages: Please confirm the applicable prevailing wage requirements and provide the wage determination number and current modification for this project. Please also confirm whether weekly certified payroll submissions are required.

16A - The prevailing wage determination number

2015-4161 Revision 35.

Period of Performance: 09/29/2026 to 11/27/2026