United States Department of the Interior
BUREAU OF LAND MANAGEMENT
Fire and Aviation 3833 S Development Ave Boise, Idaho 83705-5354
3 August 2021
PROJECT PROLOGUE
NIFC Campus Power Meters Expansion
This project will add expand the existing Schneider campus energy meter system. The work will include programming power metering hardware installed by NIFC, updating the software on the existing server, as well as any patches or revisions of the existing meter firmware to the newest release. The work will occur at the National Interagency Fire Center campus (NIFC) located at 3833 S. Development Ave in Boise, Idaho in various buildings.
1. Performance Period: The period of performance for this work is 120 days from approximately August 2021 to December 2021. See contract documents for specific requirements.
2. Building Occupancy: NIFC is fully occupied and operational campus. Provide minimum 48 hours advanced notice to COR for any work that will impact normal Government operations. The buildings will be occupied during this service type project. Contractor shall have limited use of premises for work effort as defined by the Contracting Officers Representative (COR) and shall be escorted at all times while in critical areas of the campus.
3. Safety: The contractor shall provide all required barriers for protection of personnel around all work areas.
4. Hours of Work: The contractor will perform the work during regular business hours of 7:30 AM to 4:00 PM, Tuesday through Friday, excluding holidays or early release days. Schedule site visits a minimum of five (5) days in advance with the COR. Exceptions to these work hours will be provided on an as needed case-by-case basis with advanced coordination with the project COR.
5. NIFC Access: NIFC is a secure campus with a controlled security entrance.
a. Prior to commencing work, the contractor shall provide a list to the Contracting Officer containing names for all contractor personnel who will work on the NIFC campus. Changes to the list shall be provided two days in advance of visit.
b. All contractor’s personnel shall present an office US Government or State Government-issued photo identification at the security gate. ID’s will be compared to the contractor’s personnel list.
c. All the contractors’ personnel shall wear NIFC furnished visitor badges in a visible location at all times while on the facility, and shall return the badge at the end of each day, or at the completion of the project.
d. Contractor personnel shall not enter the site more than 30 minutes prior to the start of scheduled workday and must leave the facility within 30 minutes of the scheduled workday completion.
--End---image1.jpeg image2.png