A04 Cultural GIS Updates SOW 40503184.docx

DOCX document 23 KB Posted

Attached to
CULTURAL GIS DATA: FIELD COLLECTION - CCDO Federal contract opportunity
Solicitation number
140L3920Q0099
Issued by
Department of the Interior Bureau of Land Management Nevada Region

View the file

Other files for this federal contract opportunity

Other files attached to CULTURAL GIS DATA: FIELD COLLECTION - CCDO, newest first.
File Type Posted
Sol_140L3920Q0099_Amd_0002.pdf PDF
B09 Questions and Answers 140L3920Q0099_0002.docx DOCX document
Sol_140L3920Q0099_Amd_0001.pdf PDF
Sol_140L3920Q0099.pdf PDF
B03 SCA Wage Determination PR 40503184.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

CULTURAL RESOURCE GEOSPATIAL INFORMATION CORRECTION and ARCHIVING for BLM CARSON CITY DISTRICT OFFICE

Background This statement of work (SOW) involves a targeted clean-up of Bureau of Land Management (BLM) Carson City District cultural resource data files. This work will be carried out in the BLM’s Carson City District Office (CCDO).

The BLM in Nevada works to ensure that all previously recorded cultural resources and cultural resource inventories are properly archived. The Nevada BLM uses an internal geodatabase and the Nevada Cultural Resources Inventory System (NVCRIS) as the storehouse of all geospatial data regarding cultural resources on BLM-managed lands. Currently, because of legacy data, there are a large number of errors and omissions in the cultural resources data contained in the internal geodatabase and NVCRIS.

The BLM and all proponents wishing to carry out undertakings on BLM-managed lands are required to comply with Section 106 of the National Historic Preservation Act (NHPA) of 1966 (as amended), and pursuant to the State Protocol Agreement between the Bureau of Land Management, Nevada and the State Historic Preservation Officer for Implementing to National Historic Preservation Act, to take into account the effects of undertakings on historic properties.

Prior to carrying out any ground-disturbing activities on BLM-managed lands, project proponents (including the BLM) conduct a Class I existing information inventory for the purpose of identifying previously surveyed areas and previously recorded cultural resources that may be affected by the proposed project. A Class I existing information inventory is defined as a thorough review of all documents, records, files, registers, and other sources, resulting in analysis and synthesis of all reasonably available data (BLM Manual 8110.21A2). By examining records of previously conducted survey in the project area and locations of previously recorded archaeological sites, an understanding of resources in the area of the proposed undertaking can be established. The Class I inventory also helps to guide the creation of a strategy for additional research based on the proposed project.

Objectives

a) To work with data available in the analog records at the BLM-CCDO and use this information to amend records available in the internal CCDO GIS database to provide the District with a more complete record of sites recorded on Carson City District-managed lands in Churchill County (records with a Smithsonian site number prefix of 26CH). This will enable qualified individuals working on the CCD to perform faster and more reliable Class I inventory, including planning efforts at all levels of government resulting in better protection of our important cultural heritage. Accurate, verified cultural data supports various decisions and actions related to cultural resource management and includes a benefit to the planning of projects for several related programs. By increasing the quality of the data, the BLM will be better able to meet its obligation under the National Historic Preservation Act of 1966 (as amended), the State Protocol, the Federal Land Policy and Management Act of 1976, and the National Environmental Policy Act of 1969.

b) To create scanned digital copies of missing BLM site records with prefix of 26CH not currently located in CCDO’s digital database. This will provide both a secure backup of existing cultural site records, and provide easier access to information during Class I existing information surveys.

c) To compile a complete spreadsheet tracking the progress of objectives A and B, which will serve as a complete record of BLM cultural archaeological sites.

d) To verify and incorporated into GIS all data located on the CCDO’s hardcopy site and inventory maps into the internal GIS database and work with CCDO GIS specialists to print a new set of hardcopy maps containing updated GIS data.

2.1 DESCRIPTION OF PROJECT

This contract consists of four Tasks (1, 2, 3, and 4). The purpose of this contract is to 1) verify and correct GIS data, and produce new GIS data for missing records; 2) create digital scans of BLM cultural archaeological site forms with a prefix of 26CH currently missing form CCDO’s digital internal database; 3) produce a final record of all BLM-CCDO cultural archaeological sites and the status of their GIS data; and 4) digitize missing data contained on CCDO’s hardcopy inventory and sites maps into CCDO’s internal database and work with CCDO GIS specialists to print a new set of hardcopy reference maps.

All work will be completed within the BLM-CCDO building located at 5665 Morgan Mill Road, Carson City, NV. Access will be provided to the digital and analog cultural resource files of the BLM-CCDO. No records may be removed from the CCDO.

2.2 TASK 1 – VERIFYING, CORRECTING, AND ADDING BLM CULTURAL RESOURCE DATA

The project will start with assessing the accuracy of the digital representation of sites recorded on Carson City District-managed lands in Churchill County (records with a Smithsonian site number prefix of 26CH).

The geospatial data for sites in the CCDO database will be checked against source documents and corrected when necessary. Any missing attribute data will be added to the CCDO database from the source documents.

2.2.a Confirm that the existing 26CH site information is correct, enter any missing or incomplete attribute information, or correct incorrect or outdated information as necessary.

2.2.b The Project will involve updating up to approximately 3,200 site records.

2.2.c As site information is verified, corrected, or appended to the internal GIS database, it must also be recorded on a tracking spreadsheet of all completed tasks related to the clean-up project.

2.3 TASK 2 – CREATION OF ARCHIVAL-QUALITY DIGITAL SCANS OF ALL CULTURAL RESOURCE REPORTS AND ASSOCIATED DOCUMENTS 2.3.a As source documents are used to verify or correct data in the internal GIS database, the records missing from the BLM-CCDO digital archive will be scanned, using Government-furnished equipment, to create a digital record, as appropriate.

2.3.a Scans will be identified by their BLM site number, and stored on a secure government server.

2.4 TASK 3 – PRODUCE A FINAL RECORD OF ALL COMPLETED PROJECT WORK

Task 3 of this contract consists of data synthesis of the results from Tasks 1 and 2 to develop a final report in the form of a spreadsheet. The spreadsheet will serve as a record of the results accomplished during this contract.

2.4.a The format of the final record will be determined by the BLM-CCDO Project Manager.

2.4.b The final record must contain the identifying information of each archaeological site involved in the clean-up project.

2.4.c The final record will track the status in the NVCRIS database of each BLM archaeological site involved in the clean-up project.

2.4.d The final record will state whether a digital copy of each archaeological site has been created.

2.5 TASK 3 – DIGITZE AND VERIFY CCDO HARDCOPY INVENTORY/SITE MAPS

2.5.a Digitize, as necessary, and verify all data contained on CCDO’s hardcopy inventory and sites maps into CCDO’s internal database.

2.5b Coordinate with CCDO GIS specialists to print a new set of hardcopy reference maps.

2.5 GOVERNMENT FURNISHED MATERIAL

The government will make available or provide Contractor with the following:

1. Access to the BLM-CCDO cultural resource records, or other available associated documentation during regular office hours.

2. Access to hard copy topographic quadrangles.

3. Access to a computer with ArcGIS, capable of accessing the internal GIS database, and equipped with any other application deemed necessary by the CCDO Project Manager.

4. Access to a scanner capable of making digital copies of documents.

2.6 DELIVERABLES:

Data involved in the GIS project will be will be reviewed on a weekly basis by the Project Manager. This will include the most recent data as well as digital copies of any source documents appended to the internal GIS database.

The Contractor must produce the following digital work products in the course of the clean-up project:

a) GIS data—GIS data of all verified, corrected, or appended inventory and site information. The data will be submitted to, and approved or rejected by the CCDO Project Manager.

b) Project Record—the contractor must maintain a record of all work completed in the clean-up project. This record must contain:

(1) Identifying information for each report and archaeological site involved in the clean-up project.

(2) Whether a digital copy has been created of each report and archaeological site in the BLM Carson City District Office files.

c) Final hardcopy maps – the Contractor will coordinate with CCDO GIS specialist to print a set of hardcopy inventory and site maps containing all existing and corrected GIS data.

2.7 REQUIRED QUALIFICATIONS OF CONTRACT PERSONNEL

There are no minimum education qualifications. Preference is experience in GIS, and preference for those with coursework in anthropology, history, or archaeology. Preference for experience with ArcGIS.

2.8 PACKAGING AND MARKING

2.8.1 Packaging: All items furnished under this contract shall be handled in such a manner to protect them from any damage while in the possession of the Contractor. The Contractor shall prepare all digital products for transmission consistent with standard data practices to ensure digital integrity and security.

2.8.2 The contractor shall be responsible for any damages or loss caused by improper handling of materials.

2.8.4 Delivery of items required by this contract will be at the contractor’s expense.

2.9 PRE-WORK CONFERENCE

Within a week after the contract is awarded, a pre-work conference shall be held between the Contractor and the BLM-CCDO Project Manager. The date and time of the meeting shall be determined by all three parties in. The pre-work conference discussions will pertain to contract requirements and the specific responsibilities of each party.

2.10 CONFIDENTIALITY OF INFORMATION

Specific site location data, which would allow location of cultural resource sites identified during performance of this contract, shall not be released by the Contractor to anyone except to the BLM or SHPO without the written consent of BLM.

2.11 AUTHORITY

Notwithstanding any of the other provisions of this contract, the Contracting Officer shall be the only individual authorized to:

a. Accept nonconforming work

b. Waive any requirement of this contract, or

c. Modify any term or condition of this contract.

2.12 TECHNICAL DIRECTION

The BLM-CCDO Project Manager must approve any and all data clean-up methodologies and processes concerning internal data prior to the commencement of the project. The term “Technical Direction” is defined to include, without limitation, the following:

(1) The Project Manager will provide information to the Contractor which assists in the correct entry of location and/or attribute data according to CCDO procedures.

(2) The Project Manager approves adequacy of reports, site forms, and any other material submitted by the Contractor as required by the contract.

2.13 COPYRIGHT

The Contractor agrees that no copyright shall be established by the Contractor on any materials produced from this contract, and that all materials and deliverables created through this contract become the property of the government. The Contractor agrees to “indemnify” the government against any claim of copyright infringement which may result by reason or publication by the government of material in any report pertaining to the contract work submitted by the Contractor.

2.14 OWNERSHIP

The Federal Agency retains ownership of, and all rights to, all materials collected, records, data, maps, drawings, photographs, samples, artifacts, GIS products, automated databases, or other products. These items cannot be used by the contractor without written permission from the BLM.

Period of Performance:

Six months following the date of the Award

Inspection and Acceptance:

The final inspection and acceptance of all deliverables is the responsibility of the Stillwater Field Office Archaeologist:

To be determined at time of Award

Payment Schedule:

The Contractor may request payment on a quarterly basis in conjunction with a quarterly review of the progress of the project. This contract is expected to run for the course of six months, consequently two equal payments of 50% may be expected by the Contractor.