This document is a Statement of Work (SOW) for interior repairs of a campground bathroom facility at Craters of the Moon National Monument in Arco, Idaho (PMIS Number 337258). The project scope includes comprehensive interior renovations involving floor leveling, epoxy coating replacement, toilet stall partition replacement, and fixture upgrades. Specific requirements include installing 4 new sinks, 3 toilets, and 1 urinal, applying slip-resistant epoxy coatings on floors and walls, and correcting uneven concrete flooring, all while adhering to ADA accessibility standards, OSHA safety regulations, and local building codes. The project is solicited under Solicitation Number 140P8325R0009 by the Department of the Interior National Park Service Southeast Region, with specific deliverables including fully resurfaced flooring, new epoxy coatings, installed partitions, operational fixtures, and a site cleaned of debris, subject to final inspection by the Contracting Officer Representative.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P8325R0009_Amd_0002.pdf | ||
| Sol_140P8325R0009_Amd_0001.pdf | ||
| A07_Plans_CRMO_131_3119_A_0001.pdf | ||
| Sol_140P8325R0009.pdf | ||
| Construction_Contract_Administration.docx | DOCX document | |
| B08_Photos_1.docx | DOCX document | |
| B03_Davis-Bacon_Act_WD___ID20250004.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT A – SCOPE OF WORK
Project Title: Interior Repair of Campground Bathroom Facility Location: Craters of the Moon National Monument Arco, Idaho PMIS Number: 337258
1. Project Overview The Contractor shall furnish all labor, materials, equipment, supervision, and incidentals necessary to complete the interior repairs and improvements to the campground bathroom facility as described herein. The intent of this project is to restore and improve the functionality, safety, and cleanliness of the facility to meet applicable public use, accessibility, and durability standards.
2. Scope of Work
2.1 Floor Leveling
· Identify and assess all areas of uneven or deteriorated concrete flooring.
· Remove any coatings, debris, or obstructions to access substrate.
· Apply self-leveling compound or suitable method to correct uneven surfaces.
· Allow adequate curing time before proceeding with additional treatments.
2.2 Epoxy Coating Replacement
· Remove existing epoxy coatings from all designated floor and wall surfaces.
· Properly prepare all surfaces to receive new epoxy materials.
· Furnish and apply new commercial-grade, slip-resistant epoxy coating system on:
· All interior bathroom floors
· Wall surfaces up to 6 feet high, or as specified by the Contracting Officer
· Provide epoxy materials rated for high-moisture environments with antimicrobial and chemical-resistant properties.
2.3 Toilet Stall Partition Replacement
· Demolish and remove existing partitions.
· Supply and install new partitions in the existing stall layout, including all hardware.
· Materials shall be solid plastic or powder-coated steel, corrosion-resistant, with vandal-resistant hardware.
· Installation shall meet ADA and accessibility code requirements.
2.4 Fixture Replacement
Sinks (4 Units)
· Remove 4 existing sinks and associated fixtures.
· Furnish and install 4 new commercial-grade sinks with:
· Faucet assemblies (manual or sensor-based, as approved)
· Plumbing connections
· Mounting hardware or vanities as applicable Toilets (3 Units)
· Remove 3 existing toilets.
· Furnish and install 3 new high-efficiency, commercial-grade toilets, including:
· Wax rings, seals, and anchor bolts
· Supply lines and necessary mounting Urinal (1 Unit)
· Remove 1 existing urinal.
· Furnish and install 1 new wall-mounted urinal, with:
· Water-efficient flush valve system
· Secure wall mounting and drainage connection
3. Deliverables The Contractor shall provide the following upon completion:
· Fully leveled and resurfaced concrete flooring
· New epoxy coatings on all specified floor and wall surfaces
· Installed toilet stall partitions in accordance with specifications
· 4 new sinks, 3 toilets, and 1 urinal installed and operational
· Site cleaned and free of debris
· Final inspection and walkthrough with Contracting Officer Rep (COR)
4. Compliance Requirements All work shall conform to:
· Local and state building codes
· ADA accessibility standards
· OSHA workplace safety standards
· All other applicable federal, state, and local regulations
· [Agency-specific standards, such as Department of the Interior Facilities Guidelines, if applicable]
5. Project Schedule
· Notice to Proceed: [Insert date]
· Substantial Completion: [Insert date]
· Final Completion: [Insert date or within X calendar days from NTP] Time is of the essence. Delays must be communicated in writing and approved by the Contracting Officer.
6. Contractor Responsibilities
· Provide all tools, equipment, supervision, materials, and labor necessary to complete the work.
· Maintain a clean, safe, and secure jobsite during construction.
· Coordinate all utility interruptions or facility access with the Project Manager.
· Obtain necessary permits, if not otherwise provided.
7. Exclusions This contract does not include:
· Structural modifications to the building
· Electrical system upgrades beyond fixture replacements
· Exterior renovations, landscaping, or drainage improvements
· Pest control or environmental remediation unless otherwise directed
8. Acceptance of Work Final acceptance is subject to:
· Completion of all deliverables as defined
· Compliance with all codes and standards
· Successful inspection by the Contracting Officer or authorized representative
Authorized Signatures Contracting Agency / Owner:
Signature: _________________________ Name: ____________________________ Title: _____________________________ Date: _____________________________ Contractor:
Signature: _________________________ Name: ____________________________ Title: _____________________________ Date: _____________________________
File details come from the government source that posted it. Updated .