Section C – Description/Specifications/Work Statement Summary

This is a Statement of Work (SOW) for an emergency boiler replacement project at Big Stone National Wildlife Refuge in Odessa, Minnesota, operated by the U.S. Fish & Wildlife Service under the Department of the Interior. The vendor must replace an existing Prestige Solo 399 S/N PT0008203 condensing water boiler with a KNIGHT Fire Tube Wall Mount Boiler Model WHB399L 121 or an approved equivalent. The existing boiler has experienced multiple "explosions" over eight years, manifesting as loud "bang" sounds, blown-off cover plates and condensate drains, and visible blue flames. The work scope includes disconnecting and reconnecting all associated piping systems (vent outlet, combustion air inlet, boiler supply and return, and condensate drain), disposing of the old boiler, integrating the new unit with existing controls, and performing system testing. The vendor must reuse existing fittings and pipe unless replacements are required.

The contractor must visit the site immediately upon award to meet staff and assess conditions, with a target completion timeline of thirty (30) days including lead times, boiler procurement, installation, and testing, though the total contract period depends on boiler lead times to be coordinated with FWS. Deliverables include the new water boiler unit, the owner's manual, and warranty information. The Contracting Officer's Representative is Gerrick Prine (U.S. Fish and Wildlife Service Division of Engineering, Bloomington, MN), with site contacts including Refuge Manager Michael Budd and Maintenance Supervisor Cody Teske. The Government will provide headquarters building plumbing plans, TriangleTube Prestige Solo 399 manual and specifications, and KNIGHT boiler specifications. Payment consists of a single final payment submission by the vendor upon completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Big Stone Emergency Repair – Boiler Replacement – April 17, 2026 1

SECTION C- DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C.1.0 GENERAL: Department of the Interior (DOI); U. S. Fish & Wildlife Service (FWS), Big Stone National Wildlife Refuge, Odessa, MN.

Project: HQ Building and Maintenance Shop – Emergency repair – Boiler Replacement

C.1.1 FACILITY BACKGROUND INFORMATION

C.1.1.1 The Government headquarters and maintenance shop are using a combined HVAC system, and the condensing water boiler has had multiple “explosions” over the last 8 years but has been getting worse. It appears that when the boiler kicks in there is a loud “bang” and the boiler’s cover plate and condensate drain get blown off. On one occasion the staff saw visible blue flames coming off the top of the boiler. There have been multiple repairs to the boiler from other contractors but after a few months it appears the same thing happens again.

C.1.2 PROJECT DESCRIPTION

C.1.2.1 FWS requires Vendor services to replace the existing Prestige Solo 399 S/N PT0008203

Condensing Water Boiler with the KNIGHT Fire Tube Wall Mount Boiler Model WHB399L 121 or an approved equal. Work will also include disconnecting and reconnecting existing vent outlet piping, combustion air inlet piping, boiler piping for supply and return, condensate drain, and all other connections and fittings. When installing the new water boiler reuse the existing fittings and pipe unless new ones are required.

C.2.0 LOCATION OF WORK

C.2.1 Big Stone National Wildlife Refuge 44843 687th Avenue Odessa, MN 56276 Ph. 320-273-2191

C.3.0 DEFINITIONS

C.3.1 Contracting Officer (CO): The Officer signing the contract on behalf of the Government.

The Contracting Officer has overall responsibility for the contract and is the only one

Big Stone Emergency Repair – Boiler Replacement – April 17, 2026 2 who has the authority to terminate a contract, to authorize changes or modifications, and to issue a final decision.

C.3.2 Contracting Officer's Representative (COR): The Government Engineer who will have the following authority under the Task Order:

Represent the Contracting Officer for all technical matters that may arise under the contract.

Shall remain cognizant of the Vendor’s technical efforts and progress and discuss these matters with him as appropriately.

Respond to the Vendor’s inquiries on purely technical aspects of the contract.

Review payment requests from the Vendor.

C.4.0 DESIGNATED PROJECT PERSONNEL

C.4.1 Contracting Officer (CO):

TBD

C.4.2 The Contracting Officer’s Representative (COR):

Gerrick Prine U.S. Fish and Wildlife Service Division of Engineering 5600 American Blvd West, Suite 990 Bloomington, MN 55437-1458 Phone: (612) 544-0536 Gerrick_prine@fws.gov

C.4.3 Site Contacts:

Michael Budd – Refuge Manager Big Stone National Wildlife Refuge

44843 687th Avenue Odessa, MN 56276 Ph. 320-292-4367

Cody Teske – Maintenance Supervisor 320-287-3926

Big Stone Emergency Repair – Boiler Replacement – April 17, 2026 3

C.5.0 GOVERNMENT-FURNISHED PROPERTY/ITEMS

C.5.1 The Government will provide the following documents:

Headquarters Building Plumbing Plans

TriangleTube Prestige Solo 399 Manual and Specifications

KNIGHT Fire Tube Wall Mount Boiler Model WHB399L 121 Specifications

Any other documents requested by the vendor.

C.6.0 SCOPE OF WORK OF VENDOR

C.6.1 Review scope of work information, coordinate any questions with Government.

C.6.2 Visit site to review in-place physical conditions of equipment, status of building’s existing boiler and replace the Prestige with the KNIGHT Fire boiler or equivalent boiler.

Vendor will take care of disposing of the old boiler and make sure the replacement unit is tied into the existing controls and test to make sure it works properly.

C.6.3 Provide summary of findings, recommendations for immediate improvements by the

Government.

C.7.0 DELIVERABLES

C.7.1 Vendor to provide new water boiler, owner’s manual of the new boiler and any warranty information.

C.8.0 ANTICIPATED PROJECT SCHEDULE

C.8.1 Immediately upon award visit site to meet staff and review condition assessment.

C.8.2 As soon as possible, contractor will have thirty (30) days to include lead times for the new boiler, installation, and testing.

C.8.5 Total contract period of performance of work depends on boiler lead times. Vendor will coordinate time requirements with FWS.

C.9.0 PAYMENT

Big Stone Emergency Repair – Boiler Replacement – April 17, 2026 4

C.9.1 The Vendor shall submit for final payment.