This is a Work Statement for a Bureau of Land Management (BLM) range fence construction project located approximately 9 miles east of Orchard, Idaho. The contract requires the contractor to furnish all labor, tools, equipment, and supervision to construct approximately 99,700 linear feet of permanent 4-wire barbed wire fence with Government-supplied materials. The fence will be constructed with a maximum steel post spacing of 16.5 feet, consisting of three barbed wire strands and one smooth wire strand positioned at 10 inches (top), 6 inches (middle), 6 inches (middle), and 18 inches (bottom) from the ground. Fence structures including 34 three-post steel pipe end panels, 46 five-post steel pipe corner panels, and 64 steel pipe stress panels will be constructed. Additionally, 16 four-wire barbed wire gates will be installed. The work encompasses multiple sections spanning flat to rolling terrain with rock outcrops at elevations around 3,200 feet, accessible by 4-WD vehicles and foot traffic.

Government-furnished materials include 6,042 steel posts (5.5-foot length), 227 rolls of 12.5-gauge barbed wire, 90 rolls of 12.5-gauge barbless wire, 6,042 wire stays, 242 bags of wire fasteners, 460 steel pipe posts (2-3/8" x 7'), 316 steel pipe brace posts (1-5/8" x 8'), and associated hardware. Materials will be available for pickup at the BLM Wareyard in Boise, Idaho (3948 S. Development Avenue) Monday through Thursday, 8:00 AM to 3:30 PM, with required 24-hour advance notice for appointments. The contractor must return unused materials to the same location. All work must comply with applicable codes and standards, and specific environmental and cultural considerations apply, including avoidance of slickspot peppergrass habitat, archaeological sites, and potential ferruginous hawk nesting areas along a transmission line. Payment will be made by linear foot for fence construction and by unit count for gates and panel structures. A pre-work conference must be held prior to construction start, with final inspection required at least 3 working days before project completion.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BDO BLM ESR RANGE FENCE WORK STATEMENT

SECTION C – DESCRIPTIONS/SPECIFICATIONS

SECTION 01009 - GENERAL INFORMATION AND REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

With Government supplied materials, contract entails construction of one permanent fence. Permanent fence shall consist of a 4-wire fence constructed with t-posts and steel post structures as identified in subsequent sections and attached drawings. Permanent fence constructed shall consist of barbed top and middle wires with smooth bottom wire.

A. Description of Work: Furnish labor and equipment to construct the specified typical barbed wire fence (4-wire).

B. Location of Fence Construction and Repair Work Sites as Shown on Work Location Maps: The project site is located approximately 9 miles east of Orchard, Idaho.

1. Range – Fence is located in flat to rolling terrain with rock outcrops and/or rocky areas. Main unpaved and/or unimproved roadways provide access to the site. Site is accessible by 4-WD vehicles with entire project fence line being then accessible by 4-WD vehicle, Off Road Vehicles, and/or foot traffic.

Permanent Fence Construction: T01S R02E Sec01, 02, 03, 04, 09, 16, 21, 22, 27, 34, and 35 and T01S R03E Sec06 and 33 and T02S R02E Sec 01 and 02 and T02S R03E Sec 03, 04, 05, and 06.

Project site elevation is approximately 3,200’ with topographic variation occurring across the project unit.

C. Location of Fence Removal Work Sites as Shown on Work Location Maps:

1. None

D. Work Data Sheet: Designates the type and quantity of work required at each project location.

1.2 DEFINITIONS

A. Approvals: Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the Drawings and Specifications brought to the Contracting Officer's attention in writing. After approval of an item, submit a substitute for approval when the approved item cannot be purchased or delivered in time to avoid delay in completion of the project.

1.3 SUBMITTALS

A. Scope: Submittals include design computations, shop drawings, manufactures' literature, as built drawings, samples, and maintenance manuals.

B. Requirements: Refer to individual Specifications for submittals required. Submittals shall be delivered to the

Contracting Officer. Allow at least 5 working days for review.

C. Identification of Submittals: Completely identify each submittal by showing at least the following information:

1. Name and address of submitter, plus name and telephone number of the individual to contact for further information.

2. Name of project as it appears in these Specifications.

3. Contract number, Drawing number, and Specification section number to which the submittal applies.

4. Whether this is an original submittal or resubmittal.

5. Each item shall clearly note the manufacturer's name and address, trade name, product, lot, style, color, catalog designation or model number, and locations of use.

1.4 QUALITY ASSURANCE

A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work as listed in the individual sections of these Specifications and as shown on the Drawings.

B. Conflict: Where a conflict occurs between Reference Documents and Project Specifications, the Project

Specifications shall govern.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Delivery: Protect products incorporated into the work from damage while in transit to the site.

B. Storage: Provide temporary storage facilities for products which will protect them from damage until installation on the project and final acceptance.

C. Handling: Load and unload products protecting them from damage.

1.6 PROJECT / SITE CONDITIONS

A. Access to the work site: Vehicle traffic is permitted along proposed fence line, existing fence lines and existing roads/trails within project areas.

B. The Range fence construction project area is located in relatively flat to rolling terrain with surface rock, rock outcroppings, and subsurface rock present amongst clay soils. The use of rock drills should be expected to meet line post depth requirements. Main unpaved roads provide access to the general project area with project fence line accessible by 4-WD & Off-Road Vehicles and/or foot traffic. The Range fence construction project area is accessed by Pleasant Valley Road (County maintained roadway) and Range Road. Accessibility to and along the Range project fence line may be attained by 4-WD vehicle, Off Road Vehicle, and/or foot traffic.

C. No cross-country travel with motorized vehicles shall take place except on designated roads, trails and fence corridors. Access roads shall not be constructed along fence lines or to the job sites, however, travel along the fence line is permitted. Contractor shall repair all ruts and scarred ground created by construction, repair, or removal as directed by the Contracting Officer. No blading or scraping of the ground along the fence line or on any Bureau of Land Management administered land is permitted unless prior authorization is attained.

D. Specific areas may be flagged that designate sensitive areas due to archaeological sites, wildlife nesting areas, sensitive plants, etc. The Government may impose restrictions to vehicle travel or other operations in project areas as necessary or prudent to address and/or protect resources of concern.

E. Camping at or near the job site is permitted as long as it does not exceed a maximum of 14 days in any one location.

Camping is prohibited within 100 yards of any isolated water source springs, seeps, water troughs, windmills, small reservoirs, etc.) Toilet facility requirements shall follow all Federal and State regulations. When a camp site is no longer needed, all garbage and fence building supplies must be removed and properly disposed of. These areas shall be approved in advance by the Contracting Officer.

F. Clean-up: All trash and excess materials must be removed from the project site on completion of construction and disposed of in a manner, and at a location, approved by the Contracting Officer.

G. Fuels and Fire: The project area is located in areas of light fuels (e.g. annual grasses, rabbit brush, and sagebrush) with some areas crossing into areas that have recently burned. The contractor shall obey and enforce fire prevention measures such as spark arresters, avoidance of high fuel areas where possible and all other instructions from the Contracting Officer.

H. Cultural Considerations: Because fragile and irreplaceable culture resources may be present in the area, project activities and any other action which causes disturbance of the earth's surface shall be limited to those areas approved by the BLM. Deviations from routes flagged or shown on the drawings are not allowable without prior approval of the Contracting Officer. The Contractor shall ensure that he/she, employees, or representatives do not collect archaeological artifacts. Should the condition of the cultural resources in the area be altered during construction due to unauthorized activity by the Contractor or employees, the Contractor shall be responsible for all costs of mitigating the cultural resources involved. If deterioration of the archaeological sites is found to be occurring during the construction phase, work on the project shall be terminated until a data recovery plan is prepared and completed in accordance with the National Historic Preservation Act

1.7 SEQUENCING AND SCHEDULING

A. Work Schedule: The schedule shall be submitted at the pre-work conference. When requested, submit an updated schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the estimate.

PART 2: MATERIALS/SPECIFICATIONS/DESCRIPTIONS

A. Contractor Returned Materials

1. Returned materials: All new construction materials provided by the Government not able to be used on the construction project as stipulated herein, in addition to other materials as outlined under Part 5- Work Data Sheet, will be bundled accordingly and returned to Government.

2. Location: Government property will be returned to the Bureau of Land Management Wareyard at 3948 S.

Development Avenue, Boise, Idaho 83705.

3. Time: Property return will be available Monday through Thursday from 8:00 am to 3:30 pm except on holidays. A pre-scheduled appointment with 24-hour advanced notice is required to assure that a warehouseman is available. A contact list for scheduling appointments will be provided to contractor at the pre-work meeting.

B. Fence Removal Specifications

1. None

PART 3 - EXECUTION

3.1 PROJECT MEETINGS

A. Pre-Work Conference:

1. Will be held prior to the start of work on each Order. The Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.

2. The Contractor, subcontractors and persons responsible for coordination of the work shall be present at the meeting.

3. Be prepared to summarize and explain procedures planned for the project.

B. Progress Meetings:

1. To be held at the project site, or as determined by the Contracting Officer.

2. May be called by either the Contracting Officer or the Contractor. The request shall state who should attend and include an agenda.

C. Final Inspection:

1. To be held at the project site, or as determined by the Contracting Officer.

2. Notify the Contracting Officer in writing at least 3 working days before the completion date so the

Government can schedule final inspection.

3. The Contractor or the Contractor's authorized representative shall be present during this inspection.

3.2 PREPARATION

A. Work Layout: The Government will set flags or fence posts within site distance to give the Contractor lines and angles necessary for the work executed under the Contract. Where new fences are to replace existing fences, corners, gates, and end panels shall be located in the same place as the existing fence. Stress panels shall be located as specified for each type of fence.

3.3 SALVAGEABLE ITEMS

A. Requirements: N/A

3.4 DISPOSAL OF DEBRIS

A. Requirements: Items or debris not designated as salvage for the Government shall become the property of the

Contractor. Disposal of materials in a legal manner and payment of fees required is the Contractor's responsibility.

Burning of removed materials is not permitted on the work site.

PART 4 - MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT

A. Units: The work described in this Section will not be measured for payment.

4.2 BASIS OF PAYMENT

A. Payment: No direct payment for the work described under this Section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.

END OF SECTION 01009

SECTION 01019 - GOVERNMENT-FURNISHED PROPERTY

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes fencing materials to be furnished by the Government and their locations.

1.2 DELIVERY, STORAGE, AND HANDLING

A. Location: The Government-furnished property will be provided by the Bureau of Land Management at the BLM

Wareyard at 3948 S. Development Avenue, Boise, Idaho 83705.

B. Time: Property will be available Monday through Thursday, from 8:00 am to 3:30 pm except on holidays. An appointment is required to assure that a warehouseman is available. Appointments are made by calling the phone number listed on each Order a minimum of 24 hours prior to intended pickup time.

C. Return of Unused Property: Return unused materials to the same place as they were picked up unless the

Contracting Officer states otherwise.

D. Loading, Offloading and Transporting Property: The Contractor is responsible for providing the necessary material-handling equipment to load and offload materials at the work site. The Contractor shall transport materials to the work site. Unless otherwise noted, a Government forklift and operator will be available at the Wareyard.

PART 2 - PRODUCTS

2.1 MATERIALS

A. All materials for the project will be furnished by the Government:

Estimated Fence Materials QUANTITY UNIT Steel Posts 5.5' 6042 EACH Barbed Wire 12.5 ga 227 ROLL Barbless Wire 12.5 ga 90 ROLL Wire Stays 36" 6042 EACH Wire Fasteners (Clips) 100/pkg 242 BAG Wood Stays (Gate Sticks) 80 EACH Steel Pipe Posts 2 3/8" x 7' 460 EACH Steel Pipe Brace Posts 1 5/8" x 8' 316 EACH Galvanized Post Caps 460 EACH Rebar #4 2' 380 EACH Galvanized Brace Band Clamp 2 3/8" w/ nuts and bolts 1012 EACH Brace Rail Connector 632 EACH Staples 1.5" (70/lb) 8 LB

PART 3 - EXECUTION

(There are no applicable requirements.)

4.1 METHOD OF MEASUREMENT

A. Units: The work described in this Section will not be measured for payment.

4.2 BASIS OF PAYMENT

A. Payment: No direct payment for the work described under this Section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.

END OF SECTION 01019

SECTION 02824 - WIRE FENCES AND GATES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes installing with Government-Furnished property, barbed wire and woven wire fences, and repair of existing fences.

B. Furnish all labor, tools, equipment, supervision, and any other resources necessary to complete fence projects.

C. Related Sections:

General Information and Requirements Section 01009.

PART 2 - PRODUCTS

2.1 GOVERNMENT-FURNISHED MATERIALS (as applicable to project requirements)

A. Barbed Wire: A strand of two 12-1/2 gauge galvanized wires twisted together with 2-point barbs of 14-gauge wire spaced 4 inches apart. Wire and barbs shall be zinc-coated steel, with a zinc coating of at least 0.3 oz/ft2 of coated surface area. The minimum breaking strength of each wire shall be 950 lb force. The barbed wire shall conform to

ASTM A 121.

B. Barbless Wire: A strand of two 12-1/2 gauge galvanized wires twisted together. Wire shall be zinc-coated steel wire of at least 0.3 oz/ft2 of coated surface area. The minimum breaking strength of each wire shall be 950 lb force. The barbless wire shall conform to ASTM A 121.

C. Brace Wires: Four wires of 9-gauge smooth, galvanized wire or 2 wires of galvanized, 12-1/2 gauge barbless wire. The minimum weight of zinc coating for 9-gauge wire shall be at least 0.4 oz of zinc/ft2 of coated surface area; for 12-1/2 gauge wire at least 0.3 oz of zinc/ft2 of coated surface area.

D. Clip-Type Wire Fastener: Galvanized wire, 8-gauge.

E. Mechanical Gate Closures: Assembly must include the following salient features:

1. A rigid steel strap or 9-gauge smooth wire loop 6 inches from the ground securely connected to the gate post and shaped so the gate stay will be securely held in place.

2. An adjustable cable or chain, or rigid steel strap fastened to a cam lever device located 6 inches from the top of the gate post. The closer shall be capable of securely holding the gate stay in place.

3. Gate latch by Toland & Sons, P.O. Box 1970, Winnemucca, NV 89446, or approved equal.

F. Miscellaneous Wire: Wire for ties, gate loops and fastening wood stays shall be 9 or 12-1/2 gauge galvanized wire.

G. Staples: Bright-finish or galvanized 9-gauge with slash-cut points 1-3/4 inches long.

H. Wood Gate and Fence Stays: Sound and straight pieces, 1-1/2 to 3-1/2 inch diameter of the species pine or fir

(with bark removed), honey locust, western red cedar (full stem with bark removed), juniper, osage orange, and white oak. Treatment with preservative is not required. Stays shall be of uniform length sufficient to touch the ground. Total length shall be 4'-0".

I. Steel Pipe: ASTM F 1083 SS40. Post pipe shall be 2-1/2 inch (2.375 inch O.D., 3.12 lb/ft); brace pipe, 1-5/8 inch, (1.66 inch O.D., 1.84 lb/ft). Brace clamps and fittings shall be galvanized.

OR

Steel Pipe: ASTM A 53 or F 1083. Post pipe shall be 2 inch, schedule 40 (2.375 inch O.D., 3.65 lb/ft); brace pipe shall be 1.25 inch, schedule 40 (1.66 inch O.D., 2.27 lb/ft). Brace clamps and fittings shall be galvanized.

J. Easy Fence Panels & Braces: Constructed of 1” square tubular steel with .065 wall (16 gauge). Weight of panel is

20 lbs. with Brace weight is 9 lbs.

K. Easy Fence Rock Jack: Constructed of steel angle iron. When assembled with hardware, final structure dimensions shall meet those as specified in attached technical drawings.

PART 3: EXECUTION

3.1 INSTALLATION

A. Drive steel fence posts into the ground to the depth shown on the Drawings or until the anchor plate is slightly below the ground surface. Posts shall be driven plumb. When rock formations prevent driving remove anchor plate and drill holes a minimum of 18 inches deep and slightly smaller than the diameter of the post. Drive posts solidly into the holes.

B. Wire: Stretch tightly and staple to wood posts or securely attach to steel posts with standard wire clips. Wire is properly stretched when it is springy to the touch. Drive staples into wood until the staple comes in contact with the wire against the post, but not so tight as to crimp the wire. Do not drive staples parallel to the grain of the wood. Terminate wire at each end post, gate post, corner post, or stress panel by wrapping wire around the post two times and tie off by uniformly wrapping the incoming wire a minimum of four times.

C. Brace Wires: All panels shall be wrapped with two complete wraps of barbless wire and twisted tight with a tensioning device (wood stay stick, rebar or digger link). Leave one end of the tensioning device long enough to fasten behind the horizontal brace to prevent wire from unwinding.

D. Corner Panel, Stress Panel, and End Panel Assemblies: Construct as shown on the Drawings or as staked in the field. Construct stress panels on crests of hills, and a maximum of 1320 feet center-to-center for barbed wire. In addition, stress panels are required at points between which wire is to be stretched. Construct end panels at the end of fence runs and on each side of a gate unless shown otherwise on the Maps or Drawings.

E. Rock Jacks: With the approval of the Contracting Officer, steel rock jacks may be used in lieu of steel end panels, corner panels, and stress panels where rock formations prevent dug holes. Rock jacks will be paid for at the same unit price as the substituted item. Construct as shown on the Drawings. Figure fours shall not be used in place of line posts.

F. Gates: Shall be installed according to the Work Data Sheet and the Drawings. Fulcrum-type gate openers shall be installed on all gates using 4 foot long wood stays, or as approved by the Contracting Officer. Wire Gates: Shall be constructed of smooth wire, wood stays, and wire stays. Gate should be constructed to a width of 14’ unless otherwise noted by flagged area at project site.

G. Wood Stay Installation: Shall be installed at the spacing and quantities as shown on the Work Data Sheet. Stays shall be secured with 1.75” staples. Drive staples into wood until the staple comes in contact with the wire against the stay, but not so tight as to crimp the wire.

H. Items or debris (including layout flags), not designated as salvage for return to the government, shall become the property of the Contractor. The Contractor is responsible for the disposal of materials in a legal manner and the payments of all disposal fees. Burning of removed materials is not permitted on the work site.

I. Steel Pipe Assemblies: Steel pipe panels shall be constructed in accordance with the Drawings and will include galvanized pipe caps on the tops of the structures. If loose soil conditions cause corner panels to lift when the fence wire is stretched, a steel post shall be driven parallel and adjacent to the corner pipe a minimum of 2'-6" deep and wired to the panels. When rock formations prevent driving pipe, drill holes 18 inches deep and the same diameter as the pipe. Drive pipe solidly into the holes.

4.1 METHOD OF MEASUREMENT

A. Units: The work described in this Section will be measured and paid for by the linear foot for each type of fence constructed or repaired as measured along the ground surface next to the completed fence or as measured with GPS as indicated in the Order, including distance across gate openings; end, stress, and corner panels; and drainage crossings. The quantities of end, stress, and corner panels, gates, rock cribs, and stiles to be paid for will be the actual number of these items. Note: Gates do not include adjacent end or corner panels. These are separate items.

4.2 BASIS OF PAYMENT

A. Payment: Prices and payment will be full compensation for the work described in this Section. Payment will be made under:

Item No.

Description Permanent Fence Construction – Range

Estimated Quantity

Units

4-wire Fence Construction 16.5’ Spacing (Feet)

99,700 Feet

2 Barbed Wire Gate (4-Wire) 16 Each

3 3-Post Steel Pipe End Panel 34 Each

4 5-Post Steel Pipe Corner Panel 46 Each

5 Steel Pipe Stress Panel 64 Each

END OF SECTION 02824

PART 5 – WORK DATA SHEETS

DATA WORKSHEET

FOR

SECTION 02824 WIRE FENCES AND GATES

5.1 PERMANENT FENCE CONSTRUCTION (Range)

Fence Type: 99,700 feet of 4-wire fence, 3 strands barbed wire, and 1-strand smooth wire with 16.5' max steel post spacing. Posts spacing will be such that consistent wire spacing is maintained in variable terrain. Fence structures (ie corners, end panels, stress panels, rock jacks) will be of steel pipe construction.

Type of Top Wire: 12 ½ gauge barbed

Type of Intermediate Wire: 12 ½ gauge barbed

Type of Intermediate Wire: 12 ½ gauge barbed

Type of Bottom Wire: 12 ½ gauge smooth

Wire locations/dimensions in inches (typical spacing):

10" (Top)

6" (Middle) 6" (Middle)

18" (Bottom)

Line Post Spacing (L): 16.5’ feet maximum. Posts spacing will be such that consistent wire spacing is maintained in variable terrain.

Stay Spacing: None.

Length of steel line post: 5 foot 6 inches

Depth of 5’6” steel line post in ground: 1 foot 6 inches

Depth of 7’0” Steel Post in ground: 2 foot 6 inches

SPECIAL CONSIDERATIONS

Permanent fence project segments have been flagged on steel posts. Red flags indicate structures (corners, gates).

White flags indicate fence line between structures. Stress panel locations are not flagged or depicted on the map(s), see Section 3.1 for additional information on stress panel location requirements.

Construction along the transmission line could potentially disturb nesting ferruginous hawks. NCA wildlife staff will survey the transmission prior to construction activity to determine any nesting activity/occupied nests and coordinate with ESR staff.

5.2 NEW PERMANENT FENCE

Fence Type: 4-wire

5.3 EXISTING TEMPORARTY FENCE REMOVAL

Fence Type: None

PART 6 - SPECIAL CONSIDERATIONS

6.1 SPECIAL CONSIDERATIONS

A. New fence project segments have been flagged on steel posts. Red flags indicate structures (corners, rock jacks, gates). White flags indicate fence line between structures. Stress panel locations are not flagged or depicted on the map(s), see Section 3.1 for additional information on stress panel location requirements. Contractor and Project Inspector will work together in assuring the items can be identified on the ground.

B. Construction along the transmission line could potentially disturb nesting ferruginous hawks. NCA wildlife staff will survey the transmission prior to construction activity to determine any nesting activity/occupied nests and coordinate with ESR staff.

C. Slickspot peppergrass (Lepidium papilliferum) is a special status plant species. Slickspot peppergrass habitat and plants exist near the proposed project area. Very few slick spots of any condition were found immediately along the proposed fence line. Slick spots will be pointed out to the contract crew prior to construction by the contract COR and/or PI. Fence posts will not be driven into slick spots, and equipment will not be parked in slick spots.

Construction vehicles will avoid slick spots as much as feasible. The one known occupied slick spot in the area is 335 feet south of the proposed fence and will be flagged for avoidance. Fence construction vehicles should use existing roads where possible for fence building operations. Clearing sagebrush along the fence line is allowed as necessary. Off road or cross-country travel by all vehicles will be avoided whenever possible.

D. Only rocks within the immediate proximity of the fence line will be used in the construction or repair of rock jack structures. Rocks near land survey markers of any kind shall not be disturbed for the construction or repair of any fence segments.

ATTACHMENT 2 - DRAWING INDEX

Work Location Map - General (Actual map(s) will be included in quoters package.)

Work Location Map - Project Area(s) (Actual map(s) will be included in quoters package.)

Drawing No. 02824-2 - Barbed Wire Fence (3-Wire) Drawing No. 02824-1 - Barbed Wire Fence (4-Wire) Drawing No. 02824-6 - Wire Gates Drawing No. 02824-11 - Mechanical Gate Closer Drawing No. 02824-9 - Corner Panels Drawing - 4 - Post Corner Panels Drawing – Easy Panel Typical Construction Drawing No. ID-02824-13 - Steel Pipe Corner Panels Drawing No. ID-02824-14 - Steel Pipe End Panels Drawing No. ID-010-02833-1 - Metal Prefabricated Fence Panels Drawing No. 02836-1- Fence-Drainage Crossing Type - A Drawing No. 02836-2 - Fence-Drainage Crossing Type - B Drawing No. 02824-5 - Figure Four & Rock Jack

NOTE: DRAWINGS ARE ATTACHED AS A SEPARATE FILE