This is a Scope of Work (SOW) for an exterior cyclic staining and painting project at Cumberland Gap National Historical Park in Middlesboro, Kentucky.
The project involves cleaning, preparing, and applying stain coatings to the exterior wood surfaces of the Headquarters Building (3,120 SF) and IT Building (378 SF), totaling 3,498 SF. The work is classified as cyclic preventative maintenance intended to extend the service life of existing exterior wood finishes and does not include major repairs, substrate replacement, or full restoration. Work must be completed within 60 calendar days after Notice to Proceed, with an estimated on-site duration of 8–12 working days, performed Monday–Friday from 7:00 AM to 3:30 PM ET, excluding federal holidays. The contractor must furnish all labor, materials, equipment, supervision, and incidentals. Specific tasks include low-pressure washing not exceeding 500 psi, hand scraping and sanding of loose stain per SSPC-SP 2 and SSPC-SP 3 standards, application of two coats of Sherwin-Williams Intellectual Gray SW 7045 exterior solid color wood stain to building siding, and primer plus two coats of Sherwin-Williams Analytical Gray SW 7041 to exterior doors. Application methods may include brush, roller, or spray with mandatory back-brushing. The contractor must protect adjacent surfaces and vegetation using drop cloths, masking, and plastic sheeting, and comply with OSHA 29 CFR 1926, EPA regulations, ASTM D16 standards, and National Park Service environmental protection requirements, including wildlife and cultural resource protection protocols. The contractor must provide Workers' Compensation per Kentucky law, General Liability Insurance with certificates prior to Notice to Proceed, a Quality Control Plan with daily inspections, and submit product data, a Safety Plan/Accident Prevention Plan, work schedule, and equipment list. The Contracting Officer's Representative is Tony King, and the contractor must provide a qualified on-site supervisor throughout the work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B04_ATTACHMENT_003_-_PAST_PERFORMANCE.docx | DOCX document | |
| B04_ATTACHMENT_004_-_Construction_Contract_Administration.docx | DOCX document | |
| B03_ATTACHMENT_002_Wage_Rate_Determination.pdf | ||
| Sol_140P5326R0026.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUMBERLAND GAP NATIONAL HISTORICAL
PARK (CUGA)
MIDDLESBORO, KY
Prepare and Paint Headquarters and IT Buildings
Scope of Work (SOW)
April 1, 2026
NATIONAL PARK SERVICE
INTERIOR REGION 2, SOUTH ATLANTIC GULF
NORTH MAJOR ACQUISITION BUYING OFFICE
DIVISION 1 – GENERAL
REQUIREMENTS
CUMBERLAND GAP NATIONAL HISTORICAL PARK
PREPARE AND STAIN HEADQUARTERS & IT
BUILDINGS (EXTERIOR)
ITEM 1 – BACKGROUND
Cumberland Gap National Historical Park (CUGA) encompasses over 24,000 acres across Kentucky, Tennessee, and Virginia. The Headquarters Building and IT Building serve as critical operational facilities and require cyclic exterior maintenance staining to preserve wood substrates and protect against environmental degradation including ultraviolet exposure, moisture intrusion, and biological growth.
This project is a cyclic preventative maintenance staining project intended to extend the service life of existing exterior wood finishes. This project does not include major repairs, substrate replacement, or full restoration work. Work is limited to cleaning, minor surface preparation, and application of new exterior stain coatings.
ITEM 2 – PROJECT IDENTIFIERS
• Project Title: Exterior Cyclic Staining – Headquarters & IT Buildings
• PIMS Number: 305459
• Estimated Area: 3,498 SF o Headquarters Building: 3,120 SF o IT Building: 378 SF
ITEM 3 – PLACE OF PERFORMANCE
• Location: 91 Bartlett Park Rd, Middlesboro, KY 40965
• Work shall occur within building perimeters and immediate surrounding work areas required for access, ladders, and staging.
ITEM 4 – PERIOD OF PERFORMANCE
• Contractor shall complete all work within 60 calendar days after Notice to Proceed
(NTP).
• Estimated on-site work duration is approximately 8–12 working days.
• Work hours: 7:00 AM – 3:30 PM (ET), Monday–Friday, excluding federal holidays.
• Work outside these hours requires prior approval from the CO and COR.
ITEM 5 – SCOPE OF WORK
The Contractor shall furnish all labor, materials, equipment, supervision, and incidentals necessary to perform exterior cleaning, preparation, and staining of exterior wood surfaces on both buildings.
Work Includes:
• Mobilization and staging
• Installation of safety controls per OSHA 29 CFR 1926
• Cleaning of exterior wood surfaces using water and approved washing agents
• Light surface preparation including scraping and sanding of loose stain
• Application of two coats of exterior-grade solid wood stain
• Painting of exterior doors (primer plus two coats)
• Protection of adjacent surfaces and vegetation
• Final cleanup and demobilization
• Compliance with ASTM D16, EPA, OSHA, and NPS standards
This project is maintenance staining only and assumes surfaces are generally in serviceable condition.
ITEM 6 – TASK REQUIREMENTS
6.1 Surface Cleaning
• Perform low-pressure washing not exceeding 500 psi to prevent damage to wood fibers.
• Remove dirt, mildew, chalking, pollen, and surface contaminants.
• Use biodegradable cleaning agents only if approved by COR.
• Prevent runoff contamination per EPA Clean Water Act.
6.2 Surface Preparation
• Remove loose or failing stain using hand scraping and sanding per SSPC-SP 2 and
SSPC-SP 3.
• Feather edges of remaining stain for smooth transition.
• No power sanding or abrasive blasting permitted.
• Allow surfaces to dry to manufacturer moisture content before staining.
6.3 Stain Application
• Apply two coats exterior solid color wood stain (Sherwin-Williams Intellectual Gray
SW 7045).
• Apply primer + two coats Sherwin-Williams Analytical Gray SW 7041 to all exterior doors.
• Application methods may include brush, roller, or spray with mandatory back-brushing.
• Follow manufacturer coverage rates and drying times.
• Ensure uniform finish with no streaks, runs, lap marks, or missed areas.
6.4 Protection of Adjacent Surfaces
Contractor shall protect:
• Vegetation
• Soil
• Concrete walkways
• Roof surfaces
• Windows and doors
• Mechanical equipment
Protection methods include drop cloths, masking, plastic sheeting, and temporary barriers.
6.5 Cleanup
• Remove debris, masking, and materials daily.
• Dispose of waste off-site in accordance with federal and state regulations.
• Leave site in original condition.
ITEM 7 – GENERAL WORK REQUIREMENTS
• Contractor shall coordinate all work with COR.
• Maintain continuous site supervision while work is in progress.
• Protect Government property at all times.
• Contractor shall submit:
o Product data for stain and cleaning agents o Safety Plan / Accident Prevention Plan o Work schedule o Equipment list
ITEM 8 – MANAGEMENT
• Contractor shall provide a qualified on-site supervisor at all times during work.
• Sequence work to minimize disruption to park operations.
• Provide progress updates to COR.
• Maintain project schedule and coordination with park staff.
ITEM 9 – SAFETY AND ENVIRONMENTAL
COMPLIANCE
Contractor shall comply with:
• OSHA 29 CFR 1926
• EPA regulations
• National Park Service environmental protection requirements
• US Fish and Wildlife Service wildlife protection requirements
Environmental Requirements Include:
• Protect vegetation and soil from stain, cleaners, and runoff.
• Stop work if wildlife, nests, bats, or cultural resources are discovered.
• Prevent contamination of soil, drains, or waterways.
• Equipment must be free of dirt and invasive species before entering park.
• No ground disturbance unless approved.
• Replacement-in-kind only; no changes to building materials.
ITEM 10 – INSURANCE
Contractor shall provide:
• Workers’ Compensation per Kentucky law
• General Liability Insurance
• Certificates of Insurance prior to Notice to Proceed
ITEM 11 – CONTRACTOR USE OF SITE
• Limit operations to designated work areas.
• Do not damage vegetation, utilities, sidewalks, or buildings.
• Restore any damaged areas at no cost to Government.
• Contractor staging area to be coordinated with COR.
ITEM 12 – EXECUTION
12.1 Mobilization
• Deliver materials and equipment.
• Set up ladders, staging, and safety controls.
• Conduct safety briefing.
12.2 Environmental Protection Setup
• Install vegetation protection, masking, and containment for cleaning operations.
12.3 Cleaning Operations
• Perform low-pressure washing.
• Allow surfaces to dry.
12.4 Surface Preparation
• Hand scrape and sand loose stain.
• Inspect surfaces prior to coating.
12.5 Staining – Coat 1
• Apply first coat of stain with back-brushing.
• Prime and apply first coat to doors.
12.6 Staining – Coat 2
• Apply second coat of stain.
• Apply final coat to doors.
12.7 Final Cleanup
• Remove masking, barriers, and equipment.
• Clean site and dispose of waste.
12.8 Final Inspection
• Contractor and COR perform final walkthrough.
• Correct any deficiencies before acceptance.
ITEM 13 – QUALITY CONTROL
• Contractor shall submit a Quality Control Plan.
• Perform daily inspections of surface prep and coating application.
• Ensure compliance with manufacturer instructions and ASTM standards.
• Maintain inspection logs.
ITEM 14 – INSPECTION AND ACCEPTANCE
• COR will conduct interim and final inspections.
• Contractor shall correct deficiencies before final acceptance.
ITEM 15 – GOVERNMENT-FURNISHED PROPERTY
• None.
ITEM 16 – SECURITY
• Government reserves the right to remove contractor personnel for safety or security concerns.
ITEM 17 – TRAVEL
• Site visit and field measurements are strongly recommended prior to bidding.
ITEM 18 – FOOD STORAGE & WILDLIFE
PROTECTION
• Follow NPS food storage and wildlife protection requirements.
• Dispose of food and trash in approved containers.
ITEM 19 – PROJECT PERSONNEL
• COR: Tony King
• Contractor shall provide Project Supervisor and qualified staining crew.
| DIVISION 1 – GENERAL REQUIREMENTS |
| CUMBERLAND GAP NATIONAL HISTORICAL PARK |
| PREPARE AND STAIN HEADQUARTERS & IT BUILDINGS (EXTERIOR) |
| ITEM 1 – BACKGROUND |
| ITEM 2 – PROJECT IDENTIFIERS |
| ITEM 3 – PLACE OF PERFORMANCE |
| ITEM 4 – PERIOD OF PERFORMANCE |
| ITEM 5 – SCOPE OF WORK |
| Work Includes: |
| ITEM 6 – TASK REQUIREMENTS |
| 6.1 Surface Cleaning |
| 6.2 Surface Preparation |
| 6.3 Stain Application |
| 6.4 Protection of Adjacent Surfaces |
| 6.5 Cleanup |
| ITEM 7 – GENERAL WORK REQUIREMENTS |
| ITEM 8 – MANAGEMENT |
| ITEM 9 – SAFETY AND ENVIRONMENTAL COMPLIANCE |
| Environmental Requirements Include: |
| ITEM 10 – INSURANCE |
| ITEM 11 – CONTRACTOR USE OF SITE |
| ITEM 12 – EXECUTION |
| 12.1 Mobilization |
| 12.2 Environmental Protection Setup |
| 12.3 Cleaning Operations |
| 12.4 Surface Preparation |
| 12.5 Staining – Coat 1 |
| 12.6 Staining – Coat 2 |
| 12.7 Final Cleanup |
| 12.8 Final Inspection |
| ITEM 13 – QUALITY CONTROL |
| ITEM 14 – INSPECTION AND ACCEPTANCE |
| ITEM 15 – GOVERNMENT-FURNISHED PROPERTY |
| ITEM 16 – SECURITY |
| ITEM 17 – TRAVEL |
| ITEM 18 – FOOD STORAGE & WILDLIFE PROTECTION |
| ITEM 19 – PROJECT PERSONNEL |