This scope of work statement and federal contract opportunity describe a project to replace siding at the Arrowwood National Wildlife Refuge in North Dakota. The U.S. Fish and Wildlife Service is seeking a contractor to demolish and remove approximately 3,000 square feet of existing cement board siding and install new Smart Siding. The project is identified as #24-025 and has a timeline of eight weeks from notice to proceed. It is a 100% total small business set-aside with a NAICS code of 236220 and size standard of $45 million. Quotes are due by March 8, 2024 and must be submitted to john_ferrall@fws.gov. The award will be made using lowest price technically acceptable procedures. The contractor must comply with all applicable regulations and codes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Arrowwood_West_Front_0001.jpg | JPG image | |
| Diamond_Kote_CertainTeed_Weather_Boards_0001.pdf | ||
| Sol_140FC124R0034_Amd_0001.pdf | ||
| Arrowwood_North_Side_0001.jpg | JPG image | |
| Arrowwood_East_Back_0001.jpg | JPG image | |
| Arrowwood_South_Side_0001.jpg | JPG image | |
| Sol_140FC124R0034.pdf | ||
| WD_ND20240030_Building_Stutsman_County_01-05-2024.pdf | ||
| A06_Drawings_-_24-025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK STATEMENT
ARROWWOOD NATIONAL WILDLIFE
REFUGE PINGREE, NORTH DAKOTA
PROJECT #24-025
GENERAL:
The Arrowwood NWR Visitor Contact Station is in need of replacement of the dilapidated cement board siding with Smart Siding.
1. DEMOLITON & REMOVAL
a) Removal of approximately 3,000 square feet of existing cement board siding.
b) Proper disposal of removed siding debris and any hazardous materials.
2. INSTALLATION
a) Installation of approximately 3,000 square feet of Smart Siding.
b) Smart Siding should be installed according to manufacturer's instructions.
c) Any necessary repairs to framing or sheathing should be made prior to installation.
3. FINISHING
a) Smart Siding to come pre-painted. Color to be chosen by station personnel.
b) Application of sealant around windows, doors, and other openings as necessary to prevent water infiltration.
4. SITE CLEANUP
a) Removal of all debris and construction materials from the work area.
b) Proper disposal of all waste and debris in accordance with local regulations.
c) Restoration of the work area to its original condition.
5. PROJECT MANAGEMENT & COORDINATION
a) A project manager will be assigned to oversee the entire project.
b) Coordination with the wildlife refuge staff to ensure minimal disruption to daily operations.
c) Compliance with all local, state, and federal regulations, including safety standards and building codes.
6. TIMELINE
a) Completion of the project within 8 weeks of the notice to proceed.
7. INSPECTION & ACCEPTANCE
a) The Government reserves the right to inspect any and all phases of the work performed under this Contract and will conduct a final inspection prior to acceptance of the work. The Contractor shall notify the Technical Coordinator/Refuge Manager at least five business days prior to scheduling the final inspection. Provide all Operations and Maintenance Manuals, and training in routine maintenance to assure expected boiler service life.
8. AVAILABILITY
SCOPE OF WORK STATEMENT
ARROWWOOD NATIONAL WILDLIFE
REFUGE PINGREE, NORTH DAKOTA
PROJECT #24-025
a) Normal duty hours are Monday thru Friday 8:00 a.m. – 4:30 p.m. The Contractor shall provide emergency contact information.
b) Non-duty hours include weeknights, weekends, and Government holidays (New Year’s Day, President’s Day, Memorial Day, Fourth of July, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving, and Christmas).
c) Emergency/Miscellaneous functions may be required to be scheduled during non-duty hours due to the nature of the work or specific scheduling requirements. Emergency work is required when immediate action is necessary to correct or prevent loss or damage of Government property, or to eliminate hazards to the public, personnel, or equipment.
9. QUALITY CONTROL (QC):
a) Quality Control will be maintained in accordance with industry standards and made available to the agency upon request. Installation must comply with applicable codes including OSHA, ASME, and NFPA.
10. QUALITY ASSURANCE (QA):
a) Labor warranty for all products & equipment shall be at least one year unless an extended warranty is purchased by the Government.