A04_312237-MuWo_SHE-Prjct_Manual-wo_Apps-2022-10-27_1.pdf
PDF 2 MB Posted
- Attached to
- SALMON HABITAT RESTORATION GOGA NRA MUWO
- Solicitation number
- 140P8623R0002
About this file
This document is a sources sought announcement for a salmon habitat restoration project at Muir Woods National Monument. The National Park Service is seeking information from small businesses regarding their capability and availability to perform earthwork, install large woody debris structures, and establish three water diversion systems while meeting downstream flow and environmental requirements. Interested parties should submit a capability statement of no more than ten pages by the specified date to the email address provided. The work requires removing rock slope protection from banks, grading banks, installing rock in tie-backs, and removing an asphalt trail using engineered drawings. Access is slow and restricted, and many protections are needed for sensitive resources like endangered species and vegetation. The agency contemplates issuing an RFP for this work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
INCLUDING TECHNICAL SPECIFICATIONS
FOR
CONSTRUCTION
FOR THE
NATIONAL PARK SERVICE
SALMON HABITAT ENHANCEMENT
AT MUIR WOODS, PHASE 2
100% Construction Documents
PMIS-GOGA 312237
October 2022
Civil Engineers and Geomorphologists:
Northern Hydrology and Engineering
PO Box 2515 McKinleyville, CA 95519
PH/FAX: (707) 839-2195
GOGA – 312237 1 Table of Contents
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 27 00 Definition of Contract Line Items
01 31 00 Project Management & Coordination
01 32 16 Construction Schedule
01 33 23 Submittal Procedures
01 33 23 List of Submittals
01 35 13 Archeological Protection
01 35 23 Safety Requirements
01 40 00 Quality Requirements
01 42 00 References
01 45 00 Environmental Protection
01 51 00 Temporary Services
01 52 13 Field Offices and Sheds
01 54 00 Traffic Control
01 56 00 Barriers
01 57 23 Storm Water Pollution Prevention
01 71 23 Field Engineering
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
DIVISION 02 – SELECTIVE DEMOLITION AND WOODY DEBRIS
02 41 13 Selective Demolition
02 93 50 Woody Debris
DIVISION 03 to DIVISION 30
Sections not used.
DIVISION 31 – EARTHWORK
31 05 15 Rock Work
31 20 00 Earth Moving
31 25 00 Erosion and Sediment Control
APPENDICES – Bound Separately
A – U.S. Fish and Wildlife Service Biological Opinion, Aug. 10, 2022.
B - National Marine Fisheries Service, Biological Opinion, Sept. 20, 2017.
C - U.S. Army Corps of Engineers Nationwide Permit 27, Section 404, July 13, 2022.
D - Regional Water Quality Control Board, Clean Water Act Section 401 Water Quality Certification, E – State Historic Preservation Office, Memorandum of Agreement, July 2018.
F - Storm Water Pollution Prevention Plan, draft Oct. 2022
GOGA – 312237 2 Table of Contents
GOGA - 312237 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK –GENERAL
1.0 SUMMARY
A. This Section includes the following:
1. Work Covered by the Contract Documents.
2. Actions Integral to the Work: Access and Sequencing
3. Permissible Work Windows
4. Work by Others under other contracts.
5. Government Furnished Materials.
6. Contractor use of Premises and Staging Areas
7. Public use of site.
8. Work Restrictions.
9. Special Construction Requirements.
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Muir Woods National Monument, Marin County, within the Golden Gate National Recreation Area (GGNRA), a unit of the National Park Service (NPS). Muir Woods is a protected old-growth redwood forest.
B. Most of the work is within the channel of Redwood Creek and on the channel banks.
C. The site supports multiple species named on the federal endangered species list: coho salmon, steelhead trout and Northern spotted owl, with the potential for the marbled murrelet and California red-legged frog to occur. Regulatory permits apply to their protection during the work.
D. This Project is a composite of one drawing set, Salmon Habitat Enhancement at Muir Woods, Phase 2, October 2022, and a single set of Division 1, Division 2 and Division 3 specifications.
E. Site Access: Access to the staging area for the Contractor shall be the entrance to the main visitor parking lot at Muir Woods National Monument, Muir Woods Road, Mill Valley, California 94941.
F. The Work occurs in three segments of the creek (Areas 5, 6 and 7), as follows:
1. In Area 7, the most downstream Work Zone, adjacent to the entrance Plaza:
a. Install water diversion system for Area 7 and maintain dewatered work zone.
b. Remove two segments of rock slope protection (RSP) from channel banks (Segments L1 and R1). Dispose of RSP as follows:
· Reuse some RSP in two tie-backs on the left bank, per designs.
· Off-haul excess RSP from Area 7 to Conlon stockpile site.
c. Grade channel bank. Dispose of soils as follows:
· Off-haul excess soil from staging area to Conlon stockpile site or, GOGA - 312237 01 11 00 - 2
· If Bid Option A is awarded, off-haul some or all soil from staging area to landfill in lieu of hauling to Conlon stockpile site.
d. Grade channel bed and toes of banks.
e. Remove obsolete sewer line in left bank and dispose.
f. Install Large Woody Debris structures. Use both existing and imported logs, provided by NPS, and pin logs provided by NPS. Install Small Woody Debris posts, provided by NPS.
g. If Bid Option E is awarded, salvage, store and replant the specific number of native plants in the award.
2. In Area 6, upstream of Bridge 1:
a. Install a water diversion system for Area 6 and maintain dewatered work zone
b. Remove three segments of RSP from channel banks (Segments L2, R2/R2B and R3). Dispose of RSP through three actions:
· Haul some RSP to Area 5 for reuse, as needed
· Place some RSP as grade control in segment of removed trail
· Bury excess RSP in channel, per designs, or
· If Bid Option B is awarded, off-haul some or all excess RSP to the staging area and then to the Conlon stockpile site in lieu of burying RSP in channel.
c. Grade right bank at one location, left bank “alcove” at one location.
d. Grade channel bed and toes of banks.
e. Remove segment of asphalt trail, including:
· Remove base rock and asphalt and off-haul to recycling/landfill facility.
· Remove wooden footbridge and dispose.
§ Place soil where void occurs after trail removal and grade per designs; haul soil from Area 5 for use.
f. Install Large Woody Debris structures, per designs. Use existing logs. Install pin logs provided by NPS. Haul pin logs from Plaza staging area. Install Small Woody Debris posts, provided by NPS.
g. Salvage and replant a mature azalea on the right bank. Salvage a second azalea from left bank for replanting by NPS.
h. If Bid Option D is awarded, salvage, store and replant the specific number of native plants in the award.
GOGA - 312237 01 11 00 - 3
3. In Area 5, upstream of Bridge 2 and the most-upstream Work Zone:
a. Install a water diversion system for Area 5 and maintain dewatered work zone.
b. Remove one segment of RSP from right bank (Segment R6). Dispose of RSP as follows:
· Bury RSP in left bank, per designs. Sequence work with intervening placement of large log in channel by Others.
c. Grade one segment of right bank. Dispose of soil as follows:
· Haul to Area 6 for use in regrading void where asphalt was removed.
4. Grade channel bed and toes of banks per designs.
5. Install Large Woody Debris structures per designs. Use existing logs. Install pin logs provided by NPS. Haul pin logs from Plaza staging area. Install Small Woody Debris posts, provided by NPS.
6. If Bid Option C is awarded, salvage, store and replant the specific number of native plants in the award.
G. All the items shown in these specification and drawings will be constructed under a single prime contract.
H. Items which are integral to this contract are described below:
1. Access Management and Protections
a. The Plaza staging area is accessible to Contractor vehicles.
b. The only road suitable to import excavators on oversized vehicles is via State Hwy
1. Caltrans has restrictions and requirements for oversized vehicles on a segment of this road. Caltrans may require a permit and California Highway Patrol escorts for an oversized vehicle, both of which require substantial advance submittals and scheduling. The Contractor shall apply to Caltrans for a permit, if needed, as soon as reasonably possible after contract award to avoid delays in the Work and to enable completion of the work within the permissible work window (Section 01 54 00 Traffic Control).
c. A separate water diversion system is required for each channel Work Zone.
Equipment may not enter a channel Work Zone until it is dewatered by the Contractor, with fish removed by NPS (Section 01 45 00 Environmental Protection).
d. The two upstream Work Zones, Areas 5 and 6, are accessible to equipment only by first completing the dewatering in Area 7, adjacent to the Plaza staging area.
e. Access from Area 7 to Area 6 requires preparation of an access route through a vegetated terrestrial area, temporary removal of a boardwalk segment at the downstream end of Area 6, and protection of a segment of asphalt trail.
f. Access from Area 6 to Area 5 is via an asphalt trail, which shall be protected, and requires crossing a narrow tributary where a small wooden footbridge shall be protected, modified or temporarily removed to support heavy equipment.
GOGA - 312237 01 11 00 - 4
g. The Contractor shall use equipment suitable for access routes shown on drawings.
h. Each Work Zone has access restrictions and requirements, per drawings. A required pre-construction submittal for an Access Plan shall follow drawings and propose supplemental details (Section 01 45 00 Environmental Protection).
2. Work Window
a. The work items in this Contract shall be carefully sequenced and managed by the Contractor to complete the project in the permissible construction window.
b. The permissible work window for equipment in the channel or on creek banks is June 15 to Oct. 31. An extension of the work window past Oct. 31 is possible only if rains have not initiated the salmon spawning season and regulatory agencies provide approval to continue work. Work scheduling shall not assume an extension will be available.
c. Equipment work in the Plaza Staging Area and Conlon stockpile site and hand work on channel banks is permissible after October 31.
d. Substantial rains have occurred in September and October and could temporarily prevent work in the creek during such events. The Contractor shall leave leeway for possible temporary delays in the initial project schedule.
3. Sequencing
a. This project requires careful advance sequencing and on-going attention to sequencing of on-site actions.
b. The layout of water diversion pipes requires careful planning to avoid or minimize the need to relocate the diversion pipe during work because actions and/or access routes occur on both banks in all Work Zones, per drawings. See Section 01 45 00, Environmental Protection, Subsection 3.1 H, Pipe Layout in Relation to Work Activities.
c. Some actions in one Work Zone are integrated with actions in a different Work Zone, per drawings, such as:
· The Area 7 channel must be dewatered before equipment can access the upstream work zones, Areas 5 and 6.
· Some installed LWD structures in Area 7 will obstruct the access route to upstream work zones. Therefore, full removal of equipment from upstream work zones must be completed before final installation of LWD in Area 7.
· Materials to be off-hauled from upstream work zones, such as asphalt, or imported to upstream work zones, such as pin logs, must be transported through the Area 7 channel access.
· Some materials are transferred from Area 6 to Area 5 and vice-versa. Some Area 6 RSP is hauled to Area 5 for reuse, and soil from Area 5 is hauled to Area 6 for reuse.
d. Work at Area 5 requires careful sequencing in relation to closures of the main trail.
The main trail upstream of Bridge 2 shall not be closed on both sides of the creek at the same time.
GOGA - 312237 01 11 00 - 5
· Equipment access to Area 5 uses the main trail on the west side (right bank) of the creek. When the west side trail is closed, the east side must always remain open to visitors.
· The burial of RSP in the left bank will require closure of the main trail on the east side (left bank) of the creek. The west side trail must remain open when the east side trail is closed.
· When work is conducted by Others to relocate the large log from the left bank, the trail at the top of the left bank (east side) will be closed, and the Contractor may not use the west side of the trail upstream of Bridge 2 at the same time.
e. Other sequencing issues pertain to:
· Coordinating delivery of pin logs by the Government so they are available for the Contractor to haul and install in upstream work zones as needed (see Section 02 93 50 Woody Debris).
· Work by Others during the Contract Period to relocate a large log in Area 5 after some earthwork by the Contractor but before completion of the Contractor’s earthwork (see Section 31 20 00 Earthmoving).
· To replant salvaged vegetation, if awarded per Bid Options C, D and/or E, sequence work in relation to LWD placement to retain equipment access to planting areas to the extent possible but planting by hand is permissible.
4. Environmental Protections
a. Environmental protections of the channel bed and banks, water quality, downstream flows, ground surface, endangered species, vegetation, trees, and trails are a critical component of all aspects of this work (Section 01 45 00 Environmental Protection).
b. Environmental protections are required as an on-going component of the work.
5. Work by Others During Contract Period
a. A large log (Log No. L1012) on the left bank in Area 5 will be relocated into the channel by Others, who will use cables and grip hoists to move the log. See Section 31 20 00 Earthmoving for interaction of Work by Others with earthmoving by the Contractor.
b. Work may be conducted by Others near the Conlon long-term stockpile site during the work period.
c. Work may be conducted by Others in other locations within Muir Woods during the work period.
GOGA - 312237 01 11 00 - 6
1.2 GOVERNMENT-FURNISHED MATERIALS
A. Government will furnish products indicated.
Contractor is responsible for protecting Government-furnished items from damage during unloading, storage and handling
B. Government-Furnished Products:
1. All pin logs, including delivery to the staging area. The Contractor shall unload deliveries (See Section 02 9350 Woody Debris).
2. All large logs to be imported for use as LWD in Area 7, including delivery to the staging area. The Contractor shall unload deliveries (see Section 02 9350 Woody Debris).
3. Piles of Small Woody Debris to be placed near Work Zones for use under Large Woody Debris (see Section 02 9350 Woody Debris).
4. Posts for Small Woody Debris structures. Posts are stockpiled on a dirt road referred to as the “Admin Road” uphill from the visitor center.
5. A SWPP and associated inspections, per Section 01 57 23.
1.3 CONTRACTOR USE OF PREMISES, STAGING AREA AND ROADS
A. General: Contractor shall have full use of the areas identified in construction documents, with strict limits to the boundaries of disturbance for construction operations. The Contractor shall only use areas identified in drawings for staging, access, ramps, stockpiling, equipment storage and any other work activities unless additional areas are identified in an approved Access Plan.
B. Staging Area:
a. The primary staging area shall be at the Muir Woods Entrance Plaza, typically used by visitors as a gathering and waiting area.
b. The area of the Plaza available for staging shall be per drawings, with modifications as proposed in an approved in a Pre-Construction Access Plan Submittal (Section 01 45 00 Environmental Protection and Section 01 56 00 Barriers).
c. The Contractor shall establish Security fencing around the Plaza Staging Area so as to accommodate daily visitor access as follows:
· Allows a visitor route approximately 15 feet wide from the main lot to the Visitor Center and does not require pedestrian use of the adjacent ADA parking area.
· Retains area for lines of people in the area closest to the Visitor Center, approximately between the watershed model and the Visitor Center.
· Retains access to the Plaza restrooms.
· Allows room for lines of people waiting for shuttle pick-ups on the east side of the restrooms.
· Avoids impacts to the watershed model in the plaza.
GOGA - 312237 01 11 00 - 7
· Anticipates opening of Security Fence gates in a manner to safely control pedestrian traffic (Section 01 56 00 Barriers).
d. Vehicular access to the Plaza staging area entails driving through the main visitor parking lot of Muir Woods. Contractor actions for safety, pedestrian and traffic management and communications are required during use (Section 01 45 00 Traffic).
f. Traffic back-ups at the entrance to the main lot can be avoided by arriving before visitor hours. The Contractor may access the site outside of visitor hours, but use of artificial lighting is prohibited.
C. Supplemental Staging Areas
a. Small staging areas specific to the two upstream Work Zones, Areas 5 and 6, shall be per drawings. They consist largely of paved trails that will be closed to visitors during the work.
b. The Contractor shall review drawings and propose modifications as part of a Pre- Construction Access Plan Submittal (Section 01 45 00 Environmental Protection).
c. Contractor employee parking and other supplemental staging is available at the Nursery Lot, about 0.3 miles down Muir Woods Road from the main entrance. The Contractor does not have exclusive use of the Nursery Lot (Section 01 54 00 Traffic Control).
d. Turn-outs along Panoramic Highway may be available for material transfers or similar uses if the Contractor obtains an encroachment permit from the Marin County Department of Public Works.
e. If turn-outs are to be used, use only turn-outs on the east side of Panoramic Highway, adjacent to NPS property, between Highway 1 and Muir Woods Road.
D. Existing Utilities
a. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs to a utility, repair utility at no additional expense to the Government.
b. If damage occurs to an unknown utility, repair utility.
c. Protect Water Supply Line under Main Trail in Area 5 and remove a connected decommissioned branch under the creek prior to RSP removal or earthwork (Section 02 41 13 Selective Demolition Subsection 3.3).
Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
Do not proceed with utility interruptions without Contracting Officer’s written permission.
E. Nonsmoking Site: Smoking is not permitted at the project site.
F. Construction Camp: Establishment of a camp within the park will not be permitted.
G. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment. The Contractor shall identify and follow all pertinent Caltrans and/or Marin County requirements for large vehicles and hauling on Highway 1 and Muir Woods Road. During movement of its vehicles on the roads, the Contractor is responsible for providing safe conditions for other drivers.
GOGA - 312237 01 11 00 - 8
H. Any waste generated shall be removed daily from the work zone within Muir Woods. The Contractor shall keep all waste and contaminants contained at the staging area and shall use wildlife-proof trash receptacles with lids. Uneaten human food and trash shall not remain exposed in the work zone or staging area. The Contractor shall ensure that all workers dispose of food scraps, paper wrappers, food containers, cans, bottles, and other trash are deposited in covered or closed trash containers. The trash containers will be removed from the project site at the end of each working day.
1.6 PUBLIC USE OF SITE
A. The park will be open to visitors at 8 AM seven days per week during the work period, including holidays.
B. Visitors reserve and pay for parking spaces, including those in the main lot, in the ADA/EV parking areas adjacent to the Plaza Staging Area, and the Conlon lot.
C. Shuttle buses drop off visitors at the main lot adjacent to the Plaza restroom area during summer months. Commercial buses park on the west side of the main lot, closest to the creek.
D. Visitation rates are typically highest during summer months. The lowest visitation rates during the work period are typically Tuesdays and Wednesdays after Labor Day.
E. Visitor vehicular traffic often backs up on Muir Woods Road at the entrance to the main lot and the nearby annex parking lot, where contracted parking attendants check parking reservations.
F. Trail closures in the work areas shall follow designs. NPS will not close trails near the work zone unless such closure is needed for public safety or to minimize frequent disruptions to the work
G. NPS will not be responsible for managing pedestrian or vehicular traffic (Section 01 54 00 Traffic). However, NPS will provide staff on site to communicate to the public about the work and route visitors away from trail closures.
1.7 WORK RESTRICTIONS
A. On-Site Work Hours:
Work shall be performed during daylight working hours Monday through Friday or on weekends.
Weekend and Federal Holiday Work is permitted. Show planned weekend or holiday work on schedules and, if planned on short notice, provide advance notice to the COR.
1.8 SPECIAL CONSTRUCTION REQUIREMENTS
A. NPS will be responsible for biological, archeological, and Tribal monitoring required in specifications and regulatory permits. No persons working for the Contractor shall handle, harass, GOGA - 312237 01 11 00 - 9 capture, or disturb federally listed salmonid or frog species. These actions are defined as “take” in the Biological Opinions and are prohibited, per Section 01450, Environmental Protection.
B. The Contractor shall be aware that representatives of regulatory agencies are likely to visit the site throughout the period of construction. Regulatory personnel are permitted on the site at all times without advance notice.
C. The Contractor shall be aware that representatives of the Press or other media may be visit during the work.
D. The Contractor shall be held responsible for fines or civil liabilities imposed by Regulatory Agencies as a result of the Contractor’s actions.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
Section 01 27 00
GOGA - 312237 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 001 – Mobilization and Demobilization (Lump Sum)
1. Pre-construction submittals and meetings.
2. Set-up and removal of staging area.
3. Import and export of equipment and materials.
4. Caltrans Permit and California Hwy Patrol escorts, as needed, for oversized vehicles on
Hwy 1.
5. On-site meetings and submittals during construction.
6. Trail closure management and coordination with NPS for closures.
7. Traffic management.
8. SWPP actions.
9. Close out.
10. Measurement for payment will be percent complete.
11. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 002 – Install and Operate Dewatering and Water Diversion Systems
(Lump Sum)
1. Install and operate water diversion systems in three separate channel work zones (Areas 5, 6 and 7) to maintain a dewatered channel during the work.
2. Operate the Area 7 water diversion system concurrently with one or, as needed, both of the others.
3. Coordinate with NPS for fish removal and fish protections.
4. Monitor, document and report turbidity and water levels.
5. Manage discharge of turbid water from work zones during the work, as necessary.
6. Remove all materials and equipment for water diversions after the work.
7. Measurement for payment will be percent complete.
8. Payment will be made at the contract lump sum price.
GOGA - 312237 01 27 00 - 2
C. Contract Line Item No. 003 – Selective Demolition, Earthmoving and Rock Work in Areas 5, 6 and 7 (Lump Sum)
1. Conduct access and protection measures both at and between work zones and to conduct work in the creek, per requirements, and remove/repair after work.
2. Remove six segments of Rock Slope Protection (RSP) from channel banks in three Work
Zones: Segment R6 (Area 5); Segments L2, R2/R2B, and R3 (Area 6), and Segments L1, and R1 (Area 7).
3. Conduct exploratory trenching for toe rock at RSP segments and remove, if present, except where limits are specified.
4. To dispose of RSP:
a) At Area 7, reuse some RSP in two tie-back installations in the left bank. Off-haul excess RSP to Conlon stockpile site.
b) At Area 6, reuse some RSP in one tie-back installation and haul some to Area 5 for reuse as needed. Bury excess RSP in channel per designs. (See Bid Option for alternative to burial in channel.)
c) At Area 5, reuse RSP to place in left bank buried wall.
• Accommodate work by Others to relocate large log No. 1012 on left bank before completing downstream end of buried wall.
5. Grade some channel banks:
a) At Area 7, terrace one segment of left bank.
b) At Area 6, grade one segment of right bank after removal of RSP and footbridge and install about 18 LF of erosion control fabric near tie-back. Grade one small backwater channel on the left bank.
c) At Area 5, grade a segment of the right bank after RSP removal.
6. To dispose of soils from excavations:
a) At Area 7, reuse some soils as needed to refill sewer line trench and to mix with RSP at tie-back installations. Off-haul excess to Conlon stockpile site. (See Bid Option
A for alternative to hauling to Conlon).
b) At Area 6, reuse soil to fill and grade alignment where trail is removed.
c) At Area 5, haul soil from bank excavations to Area 6 for fill placement in trail removal alignment. Off-haul excess from either Area 5 or 6 to Plaza staging area and then to Conlon stockpile site. (See Bid Option A for alternative to hauling to
Conlon).
7. Grade channel bed in each Work Zone.
8. At Area 6, demolish asphalt trail and base rock and wooden footbridge, off-haul and dispose.
9. At Area 6, salvage and replant a mature azalea bush; and salvage a second smaller azalea bush for replanting by NPS.
10. At Area 7, remove segment of obsolete sewer line and dispose.
11. Place and winterize stockpiled materials at Conlon stockpile site.
12. Establish grading stakes for earthmoving, rock work, and RSP burial.
GOGA - 312237 01 27 00 - 3
13. Measurement for payment will be percent complete.
14. Payment will be made at the contract lump sum price.
D. Contract Line Item No. 0004. Install Woody Debris (Lump Sum)
1. Install Large Woody Debris structures, per designs, as follows:
a) In Area 7, install both existing logs and logs imported by NPS.
b) In Area 6, install existing logs.
c) In Area 5, install existing logs, not including log No. 1012 to be relocated by Others.
2. Unload large logs imported by NPS and coordinate delivery schedule with NPS.
3. Unload Pin Logs imported by NPS and coordinate delivery schedule with NPS.
4. Haul Pin Logs to work sites and install per designs.
5. Install Posts for Small Woody Debris, provided by NPS.
6. Place Small Woody Debris under each Large Woody Debris structure, per designs.
7. Establish layout stakes for large wood structures and sequence installation, per specifications.
8. Measurement for payment will be percent complete.
9. Payment will be made at the contract lump sum price.
3.2 LIST OF BID OPTIONS
A. Bid Option A. Haul soils to landfill (per Cubic Yard)
1. Haul soils to landfill from the Plaza staging area in lieu of hauling soils to the Conlon stockpile site.
2. This bid option pertains to soils generated from any work zone but does not include hauling from the work zone to the Plaza Staging Area because that is included in CLIN 3.
3. NPS will identify the maximum quantity of material to be stockpiled at the Conlon stockpile site, if any. Quantities in excess of the quantity to be stockpiled shall be off-hauled to a landfill per this Bid Option.
4. Measurement for payment will be based on tickets from landfill.
5. Payment will be made at the Bid Unit price.
B. Bid Option B. Off-Haul Excess RSP from Area 6 to the Conlon Stockpile Site, in lieu of RSP
Burial in Area 6 Channel (per Cubic Yard)
1. In lieu of burying excess RSP in the channel in Area 6, as shown in CLIN 3, off-haul up to 188 CY of RSP from Area 6 to Plaza staging area and then to Conlon Stockpile Site.
2. Does not include RSP from Area 6 shown on Table 4, Sheet G7 for definite off-haul to
Conlon stockpile site or for reuse.
3. Includes all sizes of rock removed from channel banks.
4. Use alternative channel bed grading plan on Sheet C4-B for Bid Option B if all RSP is off-hauled. If only a portion of RSP is off-hauled, channel bed grading plan will partially follow Bid Option B Sheet, with final grading plan to be provided by NPS.
5. Maximum quantity for potential off-haul instead of burial is shown on Table 4, Sheet G7.
6. Measurement for payment will be based on truckloads from staging area to Conlon, per specifications.
GOGA - 312237 01 27 00 - 4
7. Payment will be made at the Bid Unit price.
C. Bid Option C. Salvage, store and replant native plants in Area 5 (per Plant)
1. Salvage, store and replant up to 118 plants identified for salvage from channel banks in
Area 5 (Sheet G6).
2. Actions may be conducted by equipment or by hand.
3. Replanting by hand after channel is rewatered is permissible after the October 31 end of work period in the channel, but plants shall be maintained until planted.
4. Salvaging will be considered 40% complete; replanting will be considered 100% complete.
5. Measurement for payment will be percent complete.
6. Payment will be made at the Bid Unit price.
D. Bid Option D. Salvage, store and replant native plants in Area 6 (per Plant)
1. Salvage, store and replant up to 231 plants identified for salvage from channel banks in
Area 6 (Sheet G6).
2. This Bid Option does not include salvage of two azaleas or replanting of one azalea because those actions are included in CLIN 3.
3. Actions may be conducted by equipment or by hand.
4. Replanting by hand after channel is rewatered is permissible after the October 31 end of work period in the channel, but plants shall be maintained until planted.
5. Salvaging will be considered 40% complete; replanting will be considered 100% complete.
6. Measurement for payment will be percent complete.
7. Payment will be made at the Bid Unit price.
E. Bid Option D. Salvage, store and replant native plants in Area 7 (Lump Sum)
1. Salvage, store and replant up to 136 plants identified for salvage from channel banks in
Area 7 (Sheet G6).
2. Actions may be conducted by equipment or by hand.
3. Replanting by hand after channel is rewatered is permissible after the October 31 end of work period in the channel, but plants shall be maintained until planted.
4. Salvaging will be considered 40% complete; replanting will be considered 100% complete.
5. Measurement for payment will be percent complete.
6. Payment will be made at the Bid Unit price.
F. Bid Option E. Prepare As-Built Drawings
1. Conduct topographic surveys of finish grade in all areas of work in the channel and on banks, including placed wood, buried rock, sewer line removal, trail removal area and
Conlon stockpiles.
2. Show extent of removals (RSP, trail) and extent of buried rock, tie-backs and similar.
3. Follow specifications for surveying and presentation requirements.
4. Prepare draft and final versions.
5. Survey work may be conducted after the October 31 end of work period in the channel but must precede substantial rain events after that time.
6. Final submittal is due within 6 weeks of substantial completion.
7. Measurement for payment will be percent complete.
8. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
GOGA - 312237 01 31 00 - 1
050512 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Construction Coordination.
2. Sequencing Planning
3. Requests for Information (RFIs).
4. Project meetings.
5. Environmental Coordination.
B. Related Requirements:
1. Section 01 32 16 Construction Schedule for preparing and submitting Contractor’s construction schedule.
2. Section 01 45 00 Environmental Protection for submittals, access and sequencing
3. Section 01 54 00 Traffic Control
4. Section 01 71 23 Engineering and Layout for procedures for layout, documentation and review of earthwork and Large Wood
5. Section 01 73 00 Execution for procedures for coordinating general installation
6. Section 01 74 19 Construction Waste Management
7. Section 01 77 00 Closeout Procedures for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction actions in sequence required to obtain the best results where one part of the Work depends on a different part of the Work.
2. Coordinate Work actions to retain access for equipment in each part of a Work Zone and to complete actions with minimal areas of impact.
3. Make adequate provisions to accommodate work actions scheduled for later in the construction period.
4. Where availability of space is limited, coordinate sequence of actions to allow an efficient progression of activities and access for related installation, construction, earthwork or other activities.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, construction schedules, and list of attendees at meetings.
GOGA - 312237 01 31 00 - 2
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Master Contractor's Construction Schedule and subsequent Weekly Construction Schedules.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences
7. Scheduled deliveries, especially by oversized vehicles
8. Project closeout activities.
9. Securing of necessary permits and compliance reporting with regulatory requirements.
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference, unless timing of submittal is otherwise specified. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Baseline Schedule.
3. A comprehensive breakdown of the Schedule of Values, incorporating cost breakdowns by
Contract Line Items and specific categories as requested by the CO
4. A list of Subcontractors and their roles for this project.
5. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
6. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
7. Site-Specific Accident Prevention Plan.
8. A draft and final Dewatering and Water Diversion Plan (per Section 01450)
9. Draft and Final Access Plan.
10. Quality Control Plan.
11. Traffic Management Plan
12. Copy of Caltrans permit application for oversized vehicles, if needed
13. Waste Management Plan
14. The signature page from the SWPPP with the Contractor’s signature demonstrating that the SWPPP has been read and accepted for this work.
15. Copies of letters notifying subcontractors of SWPPP requirements and SWPPP signature pages from each subcontractor demonstrating that the SWPPP has been read and accepted for this work.
16. Spill Prevention and Refueling Plan.
17. Billing Information and Meter Readings on Electrical Panels at Muir Woods, if to be used
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held.
GOGA - 312237 01 31 00 - 3
C. Some items listed shall be provided in draft for review by NPS prior to the Pre-Construction Conference, with a final revised version due before the Pre-Construction Conference. See Table 1 Section 01 33 23 List of Submittals.
D. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website or other electronic method, as indicated by the CO. The Contractor shall provide notice to the CO and COR via email when an RFI has be submitted on the SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Submit RFI’s by email to a designated contact as follows:
1. Enter the project name and RFI No in the header.
2. Enter the details of the question and attach related documents.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.
CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs:
GOGA - 312237 01 31 00 - 4
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.5 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Liquidated damages.
12. Contractor Performance Evaluation.
13. Notice to proceed.
14. Correspondence procedures.
15. Environmental requirements
16. Interactions with NPS Biologists (Fish, Vegetation, Bio-Monitor)
17. Interactions with archeologist
18. Interactions with Work by Others
19. Visitor Access Management
20. Acceptance/rejection of work.
21. Progress meetings.
22. Submittal procedures.
23. As-constructed drawings
24. Saturday, Sunday, and holiday work.
25. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All
GOGA - 312237 01 31 00 - 5
participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Meeting minutes. The Contractor shall prepare minutes of weekly minutes and distribute them in draft form a minimum of two days before the next weekly meeting.
3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of delivery schedules.
d. Construction Schedule update (provide updated CPM).
e. Work in progress and projected, including
1) Advance review of access before entering new Work Zone
2) Advance review of technical requirements for earthwork
3) Advance review of layout and installation sequence of Large Wood
4) Advance communications for traffic control and trail closures
f. Inspections of work in progress and projected
g. Requests for information (RFI) and other issues.
h. Modifications.
i. Status of Project Record Drawings.
j. Other business relating to work.
C. Pre-Work Conferences: Conduct a pre-work conference at Project site before each construction activity that requires on-site coordination with the COR and/or Project Engineer.
1. Attendees: Contractor and representatives of COR, NPS Fish Biologist(s), Vegetation Manager, Biological Monitor and/or Project Engineer involved in dewatering, layout, grading, excavation, large woody debris installation, review of access routes, plant salvage or biological monitoring. Advise COR of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Submittals
d. Related RFIs.
e. Related Change Orders.
f. Purchases.
g. Deliveries.
h. Possible conflicts.
i. Compatibility requirements.
j. Time schedules.
k. Weather limitations.
l. Compatibility of materials.
m. Acceptability of substrates.
n. Temporary facilities and controls.
o. Space and access limitations.
GOGA - 312237 01 31 00 - 6
p. Regulations of authorities having jurisdiction.
q. Testing and inspecting requirements.
r. Coordination with other work.
s. Protection of adjacent work.
t. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with work if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
1.6 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Ensure all relevant work is coordinated with biological monitoring at the appropriate time.
c. Implementation of the Storm Water Pollution Prevention Plan (SWPPP).
d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.
e. Training for Contractor personnel in accordance with their position requirements.
f. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Noise & Acoustics Management.
4. Protection of creek water quality and water levels
5. Protection of listed species at the site
6. Storm Water Pollution Prevention
7. Construction Waste Management.
C. Contractor’s Environmental Training Program: In addition to an NPS training for workers, per Section 01 4500, the Contractor shall conduct an environmental training for workers performing work on the project site. Training shall include the following:
GOGA - 312237 01 31 00 - 7
1. Overview of environmental issues related to the Project, including endangered species, turbidity control, measures to prevent equipment from spreading weed seeds and others.
2. Review of site specific procedures and management plans:
a. Noise & Acoustics Management.
b. Dewatering and Water Diversion
c. Access Plan
d. Spill Prevention
e. Refueling and Equipment Repairs
f. Temporary Storm Water Pollution Prevention.
g. Protection of plants.
h. Traffic Management
i. Visitor Access Management
3. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR employee training records upon request of Contracting Officer.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
GOGA 312237 SECTION 01 32 16 -1
CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Quality Assurance and On-Site Preconstruction Meetings
2. Schedule coordination for:
a. Caltrans permit application submittal for oversized vehicles, if to be used
b. Work by Others in Area 5
c. Log Import by NPS
3. Schedule of Values
4. Construction Schedule Requirements.
5. Construction Schedule Updates.
6. Time Impact Analysis.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
C. The park will open to visitors at 8 AM daily, seven days per week and on federal holidays throughout the work period. The park closes to visitors at approximately sunset, which is 8 PM in summer months, 7 PM after Labor Day, 6 PM in October 1, and 5 PM in November. The Contractor may have access to the site outside of visitor hours, subject to restrictions for noise and lighting (Section 01 45 00 Environmental Protection).
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
GOGA 312237 SECTION 01 32 16 -2
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Float: The measure of leeway in starting and completing an activity.
1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
1.3 SUBMITTALS
A. Electronic and Hard Copies: All schedules and reports submitted shall be submitted to NPS in the native electronic file format. In addition, hard copies shall be provided at each weekly meeting to project team members who will be present.
B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and three weeks before the Pre- Construction conference, submit a draft baseline schedule, large enough to show entire schedule for entire construction period. Submit a revised Construction Baseline Schedule addressing NPS comments one week days before Pres-Construction Meeting. Submit schedules in an electronic format.
D. CPM Reports: Format for each activity in reports shall contain activity number, activity description, resource loading, original duration,…