STATEMENT OF WORK
Inspect, Repair, Service and Monitor Security and Fire Alarm Systems at SEMO, TUAI, TUIN
May 5, 2023
1. Introduction The Selma to Montgomery National Historic Trail commemorates the 54-mile journey by Civil Rights advocates as they marched from Selma, AL to Montgomery, AL along U.S. Highway 80.
This march led to the passage of the Voting Rights Act on August 6, 1965. In August 1995, the State of Alabama designated U.S. Highway 80 between Selma and Montgomery as a National Scenic Byway to recognize its historical significance.
In January 1996, the Alabama Department of Transportation (ALDOT) recommended that this route receive an All- American Road designation from the Federal Highway Administration (FHWA). In 1996, the U.S. Congress designated this route as a National Historic Trail and identified the NPS as the manager of this Trail. The Trail was established to: Commemorate the events, people, and route of the Selma to Montgomery Voting Rights March of 1965, as a reminder of the right and responsibility of all Americans to participate fully in the election process and the maintenance of vigilance in protecting the right to vote. Identify, preserve, and protect the historic route and resources that inform the world about the Selma to Montgomery Voting Rights March of 1965.
The parks’ mission is to protect, preserve, and interpret the natural, cultural, and historical resources in its care for the benefit and inspiration for present and future generations.
2. Background The Fire and Alarm Security Systems at these sites are not working properly.
It is the Park’s intention to keep the monitoring of the fire and security system locally. The contractor will need to work closely with the designated Contracting Officer’s Representative
(COR).
3. Objectives The objectives of this project are as follows:
• Inspect the existing fire alarm systems associated with all four (4) SEMO buildings.
• Inspect and test the existing security systems in all four (4) SEMO buildings.
• Make any needed repairs to the fire alarm systems and make fully operational in all four
(4) SEMO buildings. All recommended repairs shall be submitted to the CO & COR for approval prior to performing repairs.
• Make any needed repairs to the security systems to make fully operational in all four (4) SEMO buildings. All recommended repairs shall be submitted to the COR & COR for approval prior to performing repairs.
2 |
• Meet all applicable requirements for a fully compliant fire Alarm system in accordance with the 2016 edition of NFPA 72 – National Fire Alarm and Signaling Code.
• Establish a service agreement to have one-year annual inspections and five-year system flush services.
• Establish local fire and security monitoring services for Dallas, and Lowndes County Sheriff’s Department, the City of Selma Police and Fire Departments, City of Montgomery Police & Fire Departments, Alabama State University Campus Police, and White Hall Volunteer Fire Department.
• Repair and replace inoperable/obsolete fire system equipment at four (4) TUIN buildings:
The Curatorial Building, the Maintenance Shop, the Headquarters Building, and the Booker T. Washington Home.
4. Scope of Work.
Services include but are not limited to the performance of inspection, testing, preventive maintenance, and repair of a variety of fire alarm systems, equipment and components such as manual alarm devices, smoke and heat detectors, remote and graphic annunciators, main fire alarm panel and components, speakers and horns and other audible and visual devices, wiring circuits and junctions, all other alarm, detection and control and ancillary devices, and emergency power operations. The system(s) shall be inspected and tested per current NFPA 72 (2016 edition).
The Fire and Security Systems shall be inspected and made fully operational so that they will notify the proper authority in case there is a break-in, fire, or any issue with the system that needs to be corrected. The Fire and Security Systems are to be made fully operational for all the buildings listed under this contract. Contractor shall ensure that all the features are inspected and operating properly. Contractor shall ensure that the systems are correctly reporting to the monitoring station as follows:
Alarm Security System
• Intrusion
• Zone data correctly
• Has ongoing power source
• Trouble system
• Correct phone line
• Once all work has been completed and everything is updated, the system is to be tested for proper operation
Fire Alarm System
• Fire and/or smoke detection
• Has ongoing power source
• Zone data correctly
• Daily periodic testing
• Trouble system
• Correct phone line
3 |
• Once all work has been completed and everything is updated, the system is to be tested for proper operation
Contractor shall provide three (3) bid proposals for annual services:
1. Inspect/Monitor/Service Alarm and Fire System at SEMO – Annual
2. Inspect/Monitor/Service Fire System at TUAI – Annual
3. Inspect/Monitor/Service Fire System at TUIN – Annual
Contractor shall provide three (3) bid proposals for 5-year services:
1. Inspect/Test Sprinkler at SEMO – 5-Year
2. Inspect/Test Sprinkler at TUAI – 5-Year
3. Inspect/Test Sprinkler at TUIN – 5-Year
Contractor shall provide one (1) bid proposals to repair systems at:
1. Upgrade/Repair Fire Alarm System at 4 TUIN Buildings
5. DEFINITION OF BID ITEMS
GENERAL DESCRIPTION
A. The intent of this section is to explain, in general, what is and what is not included in a bid B. If no bid items exist for a portion of the work, include the cost in related bid item.
BID ITEM NO. 1 – Inspect/Monitor/Service Alarm and Fire System at SEMO – Annual (Include up to 4 option years) BID ITEM NO. 2 – Inspect/Monitor/Service Fire System at TUAI – Annual (Include up to 4 option years) BID ITEM NO. 3 – Inspect/Monitor/Service Fire System at TUIN – Annual (Include up to 4 option years) BID ITEM NO. 4 – Inspect/Test Sprinkler at SEMO – 5-year BID ITEM NO. 5 – Inspect/Test Sprinkler at TUAI – 5-year BID ITEM NO. 6 – Inspect/Test Sprinkler at TUIN – 5-year BID ITEM NO. 7 – Upgrade/Repair Fire Alarm System at four (4) TUIN Buildings
6. Requirements
• All fire protection design work shall be completed and stamped by a Fire Protection
Engineer (FPE) or minimum NICET Level III certification in Fire Alarm Systems.
• All work shall be in accordance with applicable sections of: National Fire Protection Association (NFPA) codes and standards NPS Reference Manual (RM) 58
4 |
• All work shall be in accordance with the Inspection Guidance: 5400 Electrical System of the National Park Service.
• Final Delivery of Manual or Documents At a minimal, the final documents shall be inclusive of all work elements identified in the scope and consist of the following:
System Demonstration, Provide manufacturers’ operation and maintenance manual or binder.
7. Contractor Responsibilities:
• Contractor will provide necessary labor, equipment, materials, insurance, permits, etc., to perform work.
• Contractor will be NICET certified for all fire protection work. The fire alarm system installation supervisor shall be qualified and experienced in the design of fire alarm systems in accordance with the 2016 edition of NFPA 72. This supervisor shall be trained and certified by the manufacturer of the equipment that is installed. There must be a minimum of one NICET Level II, Fire Alarm System technician on-site throughout the installation of the fire alarm system.
8. Safety & Environmental Compliance
• The contractor shall comply with pertinent provisions of the Occupational Safety and Health Act (OSHA), state, and local safety laws and regulations.
• The contractor shall comply with pertinent local, state, and federal environmental protection laws and regulations.
• The Park safety officer has the authority to issue restraint or cease-and-desist orders to the contractor when violations or unsafe acts are present and threaten Government and contractor employees or damage to Government property.
• The contractor shall be responsible for the safety of his employees and equipment, and for any injury or damage done to or by them from any source or cause. He shall save and hold the United States free from all claims for damages to any and all persons and (or) property arising from the execution of the work covered by these specifications.
• The contractor shall immediately report to the COR all accidents resulting in employee injury or death or damage to property while performing this contract.
• Contractor agrees to accept the sole responsibility for complying at all times with local, County, State or other legal requirements including but not limited to full compliance with the terms of the applicable O.S.H.A. Safety Orders, so as to protect all persons, including employees from foreseeable injury, or damage to property.
• It shall be the Contractor's responsibility to inspect and identify any conditions that render any portion of the maintenance area unsafe, as well as any unsafe practices occurring thereon. The NPS COR shall be notified immediately of any unsafe condition.
5 |
9. PUBLIC CONVENIENCE AND SAFETY
Contractor acknowledges and agrees that public safety is of utmost importance, and Contractor agrees that during the progress of the Work, Contractor shall constantly protect and preserve the safety of the public. Contractor shall not unnecessarily cause inconvenience to the public during the progress of the Work and shall minimize the inconvenience caused by Contractor’s operations. Such operations include, but are not limited to, work performed on or adjacent to the Work site, traffic lane and pedestrian closures and deliveries of material and equipment.
10. Definitions and terms
• CO – Contracting Officer
• COR – Contracting Officer’s Representative
• FPE – Fire Protection Engineer
• NEC – National Electrical Code
• NICET – National Institute for Certification in Engineering Technologies
• NFPA – National Fire Protection Association
• NPS - National Park Service
• OSHA – Occupational Safety and Health Administration
• RSFMO – Regional Structural Fire Management Officer
• SEMO-Selma to Montgomery National Historic Trail
• TUIN - Tuskegee Institute National Historic Site
• TUAI – Tuskegee Airmen National Historic Site
• MIC- Montgomery Interpretive Center
• LIC-Lowndes Interpretive Center
• SIC- Selma Interpretive Center
• SERO – Southeast Regional Office
11. Security Park hours are from 9:00 AM until 5:00 PM. The Contractor can plan to work on site from 7:30 AM to 4:00 PM. Contractor cannot work outside of these hours, without prior approval from the SEMO Facility Manager.
12. Other Unique Requirements Close coordination with the Park staff and COR is essential to maintain the park for visitor enjoyment during work to the greatest extent possible. Visitor safety is of paramount concern.
Barricades, cones, etc. and all safety equipment must be in place prior to the start of work and during all work on site. Facility Manager is the final authority for closure of any park facilities.
13. Quality Assurance Requirement The contractor shall develop and maintain a quality program to ensure services are performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. As a minimum the contractor shall develop quality control procedures addressing the critical areas identified in this statement of work. The government will periodically evaluate the contractor’s performance in accordance with the statement of work.
6 |
| 1. Introduction |
| 2. Background |
| 3. Objectives |
| Contractor shall provide three (3) bid proposals for annual services: |
| Contractor shall provide three (3) bid proposals for 5-year services: |
| 6. Requirements |
| 8. Safety & Environmental Compliance |
| 9. PUBLIC CONVENIENCE AND SAFETY |
| 10. Definitions and terms |
| 11. Security |
| 12. Other Unique Requirements |
| 13. Quality Assurance Requirement |