A04_0040569628_Cosby_Water_Tank_Replace_(One)_-_SOW_4-7-2022.pdf
PDF 443 KB Posted
- Solicitation number
- 140P5322R0015
About this file
This document outlines requirements for a federal contract opportunity to replace a water tank at Cosby Campground in Great Smoky Mountains National Park. The scope of work includes installing a new water tank, associated waterlines, and appurtenances in accordance with the minimum requirements specified. The contractor must develop and submit a quality control plan with their proposal addressing surveillance methodology, response timeframes for complaints, and progress meetings. The period of performance is from August 1, 2022 to February 28, 2023, with all on-site work to be completed by the end of that period. A pre-construction meeting will be held in early August 2022 and work may commence after November 1, 2022. The solicitation number for this opportunity is 140P5322R0015 and it is being issued by the National Park Service Southeast Region for the Great Smoky Mountains National Park.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary (Section 12) provides requirements for the installation of the new tank, associated waterlines, and appurtenances that are the minimum requirements for the installation of the new water tank. The contractor's QCP shall address methods for remedying any non-compliant work. The Contractor shall develop QCP and submit with proposal package. The Contractor's QCP includes:
• Required services identified in the "Statement of Work - Requirements Summary"
• Contractor's surveillance methodology
• Method and timeframe for responding to COR or customer complaints
• Progress meetings with Government stakeholders
20. Inspection.
The Government will conduct inspections during, and upon completion of required services.
Final payment will be processed upon confirming that all noted contractor performance deficiencies have been satisfactorily corrected.
21. Schedule
The "Period of Performance" shall be from August 1, 2022 to February 28, 2023. The Cosby Campground is closed from November 1, 2022 to April 2, 2023. Pre-Construction meeting shall be scheduled the first week in August of 2022, with Notice-to-Proceed no later than September 1, 2022. Proposed on-site work shall commence any time after November 1, 2022, and all proposed work in the Campground area shall be complete by February 28, 2023. The contractor shall provide a realistic schedule for the completion of the proposed work; and notify the Park if there is not sufficient time in the schedule prior to accepting the contract. Note that trees cannot be cut down prior to November 15 due to the potential presence of the Indiana Bat. The Site Survey does not show any trees (trees are considered as any tree over 12-inches in diameter), so this should not impact the project.
22. Liquidated Damages (N/A):
23. Referenced Documents
The Design Plans and Specifications for the "Cosby Campground Water Tank and Pump Line Replacement Project". Note, the proposed project initially included a second water tank and a new pump line from the Well House to the new water tank, as well as upgrading the existing gravel drive with a new driving surface. Due to various internal issues, the proposed "Options" on the plans, including a second water tank, the pump line from the Well House, and resurfacing the entire gravel drive, will not be included with or exercised as part of this project.