This solicitation is for a rehabilitation and painting project at Jerry F. Costello Lock and Dam. The work includes rehabilitating, blasting, and applying paint systems to two tainter gates and the monorail crane bridge. The Department of the Army Corps of Engineers Engineering District St Louis is the agency issuing this solicitation. Offerors must furnish all necessary equipment, supplies, materials, and labor to complete the work. The solicitation includes specifications for the required work and materials. The response deadline and award date are not specified in this document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers St. Louis District Building Strong

Jerry F. Costello Lock and Dam – Tainter Gate and Monorail Rehab and

Painting

Specifications

For

Solicitation

Jerry F. Costello Lock and Dam, Modoc, Illinois

St. Louis District Office, Mississippi Valley Division

January 2023

Prepared by:

US Army Corps of Engineers

St. Louis District

PROJECT TABLE OF CONTENTS

DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS

00 08 00 SPECIAL CONTRACT REQUIREMENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 30 ENVIRONMENTAL PROTECTION

01 13 20 PROJECT SCHEDULE

01 15 00 TEMPORARY CONSTRUCTION FACILITIES

01 22 00 MEASUREMENT AND PAYMENT

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)

01 78 00 CLOSEOUT SUBMITTALS

DI VI SI ON 05 - METALS

05 50 15 CIVIL WORKS FABRICATIONS

05 52 00 METAL RAILINGS

05 59 20 FABRICATION OF HYDRAULIC STEEL STRUCTURES

DI VI SI ON 09 - FI NI SHES

09 97 02 PAINTING: HYDRAULIC STRUCTURES

DI VI SI ON 26 - ELECTRI CAL

26 42 13.00 20 CATHODIC PROTECTION BY GALVANIC ANODES

DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON

35 01 70.13 WIRE ROPE CONNECTION AND TENSIONING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 08 00

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 WORK AREAS

1.2 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS

1.3 DAMAGE TO WORK.

1.4 QUANTITY SURVEYS

1.5 PARTIAL PAYMENT

1.6 CERTIFICATES OF COMPLIANCE

1.7 PURCHASE ORDERS

1.8 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1

1.9 ACCIDENT INVESTIGATIONS AND REPORTING

1.10 ACCIDENT PREVENTION PROGRAM

1.11 DAILY INSPECTIONS

1.12 ENVIRONMENTAL LITIGATION

1.13 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.14 RIVER STAGE LIMITATIONS

1.15 SUBCONTRACTS

1.16 REQUIRED INSURANCE

1.17 PROTECTION OF MATERIAL AND WORK

1.18 CONTAMINATION OF WATER

1.19 COMMERCIAL WARRANTY

1.20 ORDER AND COORDINATION OF WORK

1.21 SUBMITTALS

1.22 MEANS OF ESCAPE FOR PERSONNEL QUARTERED OR WORKING ON FLOATING

PLANT

1.23 EMERGENCY ALARMS AND SIGNALS

1.24 USE OF MECHANIZED EQUIPMENT ON FLOATING PLANT

1.25 OBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991) DFARS 252.236-7002

1.26 SIGNAL LIGHTS

1.27 INSPECTION FACILITIES

1.28 CONTRACTOR PERFORMANCE EVALUATIONS

1.29 SECURITY REQUIREMENTS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

DOCUMENT 00 08 00 Page 1

SECTION 00 08 00

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 WORK AREAS

In accordance with the Contract Clause entitled, "Operations and Storage Areas", and subject to the approval of the Contracting Officer and the restrictions imposed by SECTION 01 11 30 - ENVIRONMENTAL PROTECTION, of the Technical Provisions, the Contractor will be allowed use of Government-controlled land within the construction limits shown on the drawings or as specified herein.

1.2 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS

a. Unless otherwise specified, shown on the drawings, or stated in writing by the Contracting Officer, the Contractor shall not move or disturb any public utilities or private improvements. Such removals, alterations, and/or relocations, where necessary, will be made by others. The locations shown on the drawings for underground utilities are approximate only. The exact locations of such utilities shall be determined by the Contractor in the field prior to commencing construction operations in their vicinity.

b. The attention of the Contractor is directed to the possibility that public utilities or private improvements may be encountered within the construction limits, some of which may be buried, and the existence of which is presently not known. Should any such utilities or improvements be encountered, the Contractor shall immediately notify the Contracting Officer so that a determination may be made as to whether they shall be removed, relocated, or altered. After such determination is made, the Contractor shall, if so directed by the Contracting Officer, remove, relocate, or alter them as required and an equitable adjustment will be made. In the event the Contracting Officer arranges for such removals, alterations, or relocations to be performed by others, the Contractor shall cooperate with such others during the latters' removal, alteration, or relocation operations.

1.3 DAMAGE TO WORK.

The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause entitled "Permits and Responsibilities." However, if in the judgment of the Contracting Officer any part of the permanent work performed by the Contractor is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or job prices as fixed and established in the contract. If in the opinion of the Contracting Officer there are no contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to the Contract Clause entitled, "Changes," of the contract will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), DOCUMENT 00 08 00 Page 2 utilities, materials, equipment, and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

1.4 QUANTITY SURVEYS

The Contractor shall have a Professional Land Surveyor registered in the state the work is being accomplished conduct original and final earthwork surveys. Surveys shall be performed in the presence of the Contracting Officer and all field survey notes be initialed by the Government Representative and furnished to the Government within 24 hours unless directed otherwise by the Contracting Officer.

1.5 PARTIAL PAYMENT

At the discretion of the Contracting Officer, partial payment will be made for equipment delivered and stored on site or off site providing such storage is in accordance with the provisions of these specifications and the Contractor furnishes satisfactory evidence that title to such equipment has been acquired and that it will be utilized on the work covered by these specifications. Partial payment is defined as the invoice amount plus shipping costs. If the equipment is stored off site, the Government shall have the right to inspect the equipment.

1.6 CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall include the signature and title of an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from responsibility for furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

1.7 PURCHASE ORDERS

Purchase orders for other than stock materials showing the firm names and addresses and list of material shall be furnished to the Contracting Officer or an authorized representative as soon as issued.

1.8 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1

The Safety and Health Requirements Manual EM 385-1-1 forms a part of these specifications. EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil/USACEPublications/Engineer-Manuals/ .

Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.

1.9 ACCIDENT INVESTIGATIONS AND REPORTING

Refer to EM 385-1-1, Paragraph 01.D. Accidents, involving contractor and/or subcontractor employees performing any work or related work on a USACE project, shall be investigated and reported immediately to the

DOCUMENT 00 08 00 Page 3

Contracting Officer or authorized Contracting Officer's representative.

This reporting requirement applies to on-site or off-site accidents. Upon receipt of the initial accident report notification, the Contracting Officer shall issue additional guidance concerning continuing project operations which may include a "cease work" directive. If a cease work directive is issued, the Contractor will not be allowed to resume work related to the accident until all conditions of the "cease work" directive are met. After the initial notification, the Contractor shall ensure a formal investigation is conducted and reports are completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or an authorized representative within one working day after the accident occurs. The accident Investigation report shall be made on ENG Form 3394.

1.10 ACCIDENT PREVENTION PROGRAM

Refer to Contract Clause FAR 52.236-13 entitled, "Accident Prevention".

Within 15 days after receipt of Notice to Proceed of the contract, and at least 7 days prior to the prework conference, the original and one copy of the Accident Prevention Program shall be submitted to the Contracting Officer for review. See EM 385-1-1 Appendix A (2014 Edition) and checklist included at the end of this section for guidance in creating the Accident Prevention Plan.

The program shall also include a copy of company policy statement of accident prevention and any other guidance statements normally provided new employees. Each company employee shall be required to sign the company policy statement of accident prevention to verify that all employees have been informed of the safety program, and such signed statements shall be maintained at the project site.

When marine plant and equipment are in use under this contract, the requirements of EM 385-1-1, Section 19 shall be met.

The Contractor shall not commence physical work at the site until the program has been reviewed and found acceptable by the Contracting Officer, or an authorized representative. The Contractor shall submit for approval the Activity Hazard Analysis for each phase of construction prior to the beginning of work in each phase. Also refer to Section 1 of EM 385-1-1.

1.11 DAILY INSPECTIONS

The Contractor shall perform daily safety inspections and record them in RMS. Reports of daily inspections shall be maintained at the job site.

The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:

a. Phase(s) of construction underway during the inspection.

b. Locations of areas inspections were made.

c. Results of inspection, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

1.12 ENVIRONMENTAL LITIGATION

a. If the performance of all or any part of the work is ordered by a court of competent jurisdiction to be suspended, delayed, or

DOCUMENT 00 08 00 Page 4 interrupted as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a Subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the Contract Clause entitled "Suspension of Work".

b. The term "environmental litigation", as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

1.13 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled, "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

b. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The delay must be beyond the control and without the fault or negligence of the Contractor. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous day), be calculated chronologically from the first to the last day of each month, and be recorded as full days. The Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a time extension modification in accordance with the FAR Clause 52.249-10 entitled "Default (Fixed Price Construction)".

1.14 RIVER STAGE LIMITATIONS

The Contractor should be aware that high river levels may cause work delays. The Contractor is responsible for becoming familiar with expected flow rates and river stages, and should monitor river forecasts and weather forecasts. If river levels are forecasted such that they are expected to impact work, the Government will direct the Contractor to stop work and/or remove floating plant from site and moor plant off site. For

DOCUMENT 00 08 00 Page 5 such occurrences, an equitable adjustment to the contract will be made in accordance with the Contract Clause entitled "Suspension of Work" as determined by the Contracting Officer. In the event of a significant rise in river stages, the Contractor should do all they can to protect completed works and prevent damage.

1.15 SUBCONTRACTS

In accordance with the Contract Clause entitled "Subcontracts", the Contractor shall, within seven days after the award of any subcontract by the Contractor or a Subcontractor, deliver to the Contracting Officer an electronic copy of a completed Standard Form 1413 with the original signatures of both parties.

1.16 REQUIRED INSURANCE

a. As required by the Contract Clause entitled "Insurance-Work on a Government Installation", the Contractor shall within 15 days after receipt of Notice of Award and prior to the commencement of work, furnish to the Contracting Officer, a written statement of required insurance as evidence of the following minimum insurance:

(1) Workmen's Compensation . Amounts required by applicable jurisdictional statutes.

(2) Employer's Liability Insurance . $100,000

(3) Comprehensive General Liability Insurance .

Bodily Injury - $500,000 per occurrence

(4) Comprehensive Automobile Insurance .

Bodily Injury - $200,000 each person $500,000 each accident Property Damage - $ 20,000 each accident

b. Statements of required insurance shall be submitted electronically or to the following address:

Department of the Army St. Louis District, Corps of Engineers Southern Area Office, CEMVS-EC-CS 113 West Main Street, Suite 3 Jackson, Missouri 63755

1.17 PROTECTION OF MATERIAL AND WORK

The Contractor shall at all times protect and preserve all materials, supplies, and equipment of every description (including property which may be Government-furnished or owned) and all work performed. All reasonable requests of the Contracting Officer to enclose or specially protect such property shall be complied with. If, as determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payments due to the Contractor.

DOCUMENT 00 08 00 Page 6

1.18 CONTAMINATION OF WATER

In addition to the requirements set forth in SECTION 01 11 30, paragraph Protection of Water Resources, the Contractor shall take positive protective measures to prevent spillage of potential pollutant materials such as fuel, emulsion materials, chemicals etc., from storage containers or equipment, into lakes or tributary waters. Such positive protective measures may include, but are not limited to, the following:

(1) A berm enclosure of sufficient capacity to contain such materials.

(2) Security measures to prevent acts of vandalism which could result in spillage of such materials (fences, guards, etc.).

(3) Storage of such materials in an area where the terrain would preclude leakage into lake or tributary waters.

(4) Utilization of secure Government storage areas if the Contracting Officer indicates such space is available. No storage past immediate needs (2 days) without the consent of the Contracting Officer.

The Contractor shall submit its proposals for implementing the above provisions in accordance with SECTION 01 11 30, paragraph Environmental Protection Plan.

1.19 COMMERCIAL WARRANTY

The Contractor agrees that the standard commercial equipment furnished under this contract shall be covered by the most favorable commercial warranties the manufacturer gives to any customer for such equipment, and that the rights and remedies provided herein are in addition to and do not limit any rights afforded to the Government by any other clause of this contract. The Contractor shall furnish an electronic copy of the warranties to the Contracting Officer.

1.20 ORDER AND COORDINATION OF WORK

The Contractor may start and complete the work in such order and sequence as desired subject to compliance with the following paragraphs:

a. The Contractor shall develop a detailed written work plan in addition to the project schedule required in SECTION 01 13 20 to sequence all work in compliance with the requirements of the plans and specifications and with the following paragraphs. The Contractor shall submit this detailed work plan with the project schedule submittal to the Government for approval before commencement of any work. The work plan shall be in written narrative format and include, but not be limited to, description and sketches/drawings to adequately communicate anticipated construction methods for ALL work items and sequencing requirements of all activities. This work plan shall also specifically include coordination with the Government for bulkhead handling and placement.

b. The Lock and Dam shall remain in operation during the construction period except as noted on the construction drawings or in the specifications, or as directed by the Contracting Officer's Representative. Lock and Dam operation takes precedence over construction Contractor operations. The Contractor shall coordinate all work with the Contracting Officer's Representative and the

DOCUMENT 00 08 00 Page 7

Lockmaster, including the setting and removal of tainter gate bulkheads by the Government. The Contractor shall conduct its operations to not interfere with the functions of the Government personnel and the use of the lock by river traffic.

c. The Contractor will not be given priority over other waterway users for lockages. The Contractor shall adhere to normal queuing procedures as required unless otherwise permitted by the Lockmaster.

d. The Contractor shall be advised that no river based operations and/or gate work will be permitted under this contract during the time period of 1 December to 23 February due to cold temperatures and ice on the river. The Contractor shall remove floating plant from the immediate work site during this period (1 Dec to 23 Feb). The Government will remove bulkheads during this period. Any work started on any gate(s) prior to these dates shall be complete by 30 November such that all gates are fully operational during the period of 1 December to 23 February. The upstream emergency bulkheads may be utilized to control flow during the months outside of the previously identified restricted months of 1 December to 23 February. If the Tainter Gates are adequately supported and a work platform is used, construction could be completed during the winter months at the approval of the Government. Since there is only one set of upstream emergency bulkheads, only one gate bay shall be out of service at a time. Work on the monorail structures or tainter gate bulkheads during the aforementioned timeframe, that is not dependent on the use of a floating plant, will be considered by special request to the Contracting Officer for his approval.

e. Not more than one tainter gate shall be out of service for rehabilitation at any one time. At the request of the Contractor, the gate on the other side of the bulkheaded gate may be adjusted by the Government to the extent permissible for the flow conditions at the time in an attempt to minimize turbulence below the gate being rehabilitated. The Contractor shall be responsible for monitoring water currents within work areas to maintain worker and equipment safety and coordinate all requirements for possible adjacent gate closures with the Government. All requests by the Contractor, with respect to gate settings, will be coordinated with the Lockmaster.

The Lockmaster is responsible for maintaining safety and operability of the lock and dam and will only concur and direct gate change settings as determined safe by the Lockmaster.

f. All work required in this contract, including proper containment and disposal of debris, shall be accomplished in place at the Contractor's expense.

g. The Contractor shall design and detail a method to support the tainter gates during removal of structural components detailed on contract drawings. The support system shall be designed and stamped by a licensed Professional Engineer. The support system shall ensure the structural integrity and stability of the tainter gates and surrounding dam components during the duration of work. Damage to the tainter gates and surrounding dam components caused by the shoring method utilized shall be at the Contractor's expense. The tainter gate support method shall be submitted to the Government for approval prior to commencement of any work. The downstream bulkhead slots may be utilized by the Contractor to position a floating plant or barge during repairs. Damage to the downstream bulkhead slots and/or any

DOCUMENT 00 08 00 Page 8 surrounding dam components caused by using the slots during this contract shall be at the Contractor's expense.

h. In order to perform required work on tainter gates as specified in this contract, it will be necessary to close off flow to the gate bay. Emergency bulkheads for closing off the flow to the gates are stored in the storage yard at the west end of the dam. The Government will be responsible for transporting bulkheads from the storage yard, placement and movement of bulkheads. The Contractor shall schedule work within the following parameters:

1) The Government monorail bulkhead crane shall not be available to the Contractor for any type of use. The Government will utilize the monorail bulkhead crane for placing bulkheads.

2) The Contractor shall coordinate all requirements related to movement and placement of bulkheads with the Contracting Officer's Representative and the Lockmaster. The Contractor shall notify the Contracting Officer's Representative and Lock master a minimum of five (5) days prior to the need for movement of any bulkheads. The Government will not be available on weekends and Federal Holidays for bulkhead operations.

3) Prior to the removal of a tainter gate from service by placement of bulkheads, all materials and equipment needed to complete the required contract work on that gate shall be available on-site and ready for installation.

i. If Option 4 or Option 5: Repairing, Blasting and Painting of the Monorail Structure is awarded by the Government, this work shall not be completed until after the Tainter Gate Repairs and Painting has been complete. An in service monorail system will be needed to deploy bulkheads during the tainter gate repairs and painting.

j. If Option 6: Blasting and Painting of Upstream Bulkheads is awarded by the Government, this work shall not be completed until after the tainter gate repairs and painting has been complete. In service bulkheads will need to be deployed during the tainter gate repairs and painting.

k. All tainter gate movements and machinery equipment operations will be conducted by the Government for the Contractor. The Contractor shall schedule any required gate movement within the following parameters:

1) Gate operations will only be performed during the day shift, 0800 to 1600 hours, Monday thru Friday, excluding Government holidays.

2) The Contractor shall provide a minimum 24 hour advance notice to the Contracting Officer's Representative for all gate operations. Notice shall provided on a working day (working day = Monday thru Friday, excluding holidays).

3) Flow conditions permitting, prior to placement of bulkheads, the Government will flush water under the gate for a minimum of 4 hours.

4) The Contractor shall allow four hours for the Government to

DOCUMENT 00 08 00 Page 9 complete requested gate position changes.

5) The Government will operate for any purpose, including testing, only one gate at a time.

l. All work by the Contractor shall be done with a floating plant or on a fixed platform. Spuds shall not be lowered onto the apron/stilling basin or anywhere revetment exists. Spuds are not permitted within 300 ft. upstream and 300 ft. downstream of the dam.

The floating plant may be located upstream or downstream of the dam but must be tied off at a Government approved location or held in place by a tow. The Contractor may perform work from a floating plant located upstream of the bulkheads with some additional restrictions.

The minimum distance between the edge of floating plant and bulkheads shall be 3'. The Contractor shall not tie off to the bulkheads in any way. The Government will restrict floating plant use upstream of bulkheads during high flow stages. During the repairs of one Tainter Gate, the adjacent gate bay flow has historically caused turbulent flows downstream of the dam causing movement to the floating plant or barge. The Contractor should anticipate long delays due to unsafe and/or difficult working conditions when flow conditions induce excessive movement to a floating plant or barge if utilized during this contract. The Lockmaster has the authority to determine what flows the Contractor is able to safely operate the floating plant.

Additionally, the floating plant shall be powered by a vessel with no less than 1100 horsepower in order to safely maneuver the floating plant upstream of the dam.

m. The Contractor shall monitor fluctuations of tailwater elevation and make tie off adjustments such that the floating plant shall not damage the piers. Adequate protection between the barge and pier shall be provided by the Contractor at all times to prevent damage to the pier concrete surfaces. The Contractor shall be required to have a safety boat in accordance with Corps of Engineers safety requirements. At all times when work is not in progress, the Contractor shall be required to have a 24 hour telephone number where the Government may reach a representative of the Contractor to notify of any problems with the floating plant. The representative must be available to be on site to attend to work barge(s) within 60 minutes of a phone call from the Government 24 hours a day, 7 days a week.

The Contractor shall post and keep current telephone numbers for emergency action. The Contractor shall submit the contingency plans for addressing headwater and/or tailwater fluctuations to the Contracting Officer for approval at least 7 days before mobilization.

n. The Contractor shall keep the top of the dam clear of debris and equipment at all times during the tainter gate work and the Contractor shall not restrict the movement of the traveling monorail crane along the length of the entire dam and shall maintain monorail walkway access (both on the upstream and downstream monorail) along the entire length of the dam for daily dam gate setting operations, unless noted otherwise. During Contractor work on the monorail bridge deck, all equipment placement and operations on the deck should be minimized and shall be coordinated with the Lockmaster.

o. The Contractor shall protect the existing piezometers on the dam piers from damage. Repair to any damage to existing piezometers shall be responsibility of the Contractor.

DOCUMENT 00 08 00 Page 10

p. The Contractor will not be allowed access to the lock and dam control station other than for coordination purposes.

q. The Contractor shall furnish all electrical power or other required utilities required for construction activities. No temporary hookups to existing lock facilities will be allowed unless stated otherwise in this specification. The Contractor will be responsible to provide a source of emergency backup power for the Contractor's operations to ensure critical operations can continue in the event of an electrical power disruption.

r. At least 30 days prior to mobilization, the Contractor shall submit the plan for storage of materials and equipment at the site to the Contracting Officer for approval.

s. Construction limits will extend as shown on the drawings.

Contractor personnel may cross the navigation lock upper and/or lower miter gate when the gates are closed to gain access to the construction limits. Only hand carried equipment shall be brought across the miter gates and the dam by Contractor personnel. The Contractor shall be provided one keycard to open the front gate, to be used by the QC Superintendent during working hours. The keycard can be checked out from Lock personnel at the start of the work week and checked in at the end of the work week. The QC Superintendent shall be the sole person allowed the keycard and shall be responsible for contractor personnel access through the gate during working hours. If the Contractor works multiple shifts, the Government will allow a different, similar method for keeping the keycard.

t. The Contractor's employees will be required to park personal vehicles at a designated Contractor Parking Area shown on contract drawings.

u. Potable water and portable toilet facilities for Contractor use shall be provided by the Contractor.

v. Size restriction of floating plant moored at Contractor staging area shall be a maximum combined width of seventy (70) feet.

w. If river levels are forecasted such that the bulkheads may be overtopped by pool during allowable work periods, the Contractor shall remove all floating plant from dam piers, both in the pool and the tailwater, and moor plant off site or to the back side of the Downstream Floating Guidewall for the duration of the high water event.

x. Utilities not shown or identified in the plans or specifications may be encountered by the Contractor during construction activities.

If encountered, the Contractor shall submit plan to relocate and restore utilities as required for approval by the Contracting Officer's Representative.

y. Security fencing and hand railing may be removed in work areas during construction as long as safety and security is maintained and replacement made to its original location and condition, including an approved method and type of touch up painting as necessary.

Contractor proposals for modifying fencing and handrails shall meet requirements in EM 385-1-1 and be submitted for approval.

DOCUMENT 00 08 00 Page 11

z. Floating plant and personnel shall comply with the applicable U.S. Coast Guard regulations and licensing requirements. Floating plant equipment shall meet the applicable requirements of 46 CFR Chapter 1 Subchapter E and 46 CFR 44.05-10. Floating vessels operating on the Kaskaskia River and its tributaries must be operated in accordance with 33 CFR 207.3, "Ohio River, Mississippi River above Cairo, Ill., and their tributaries; use, administration, and navigation." The Contractor's methods for disposal of sanitary sewage, and bilge water accumulated aboard floating plant, shall meet applicable local, state, and federal requirements.

aa. All elevations and dimensions shall be verified in the field before work begins. The Contractor is responsible for confirming all dimensions prior to shop drawing preparation and material fabrication.

bb. Various structures identified for work activities contain lead based paint. For structures that are to be painted, all spent abrasive blast material and removed paint shall be contained and disposed of properly. See specification sections for lead based paint removal, containment, and disposal requirements.

cc. Materials which are not salvaged by the Government shall be disposed of in accordance with contract specifications.

dd. The Contractor is advised that the upstream bulkheads may not completely seal while holding back pool. The leakage is variable with water height and seal condition. Due to potential leakage from the bulkheads, the Contractor may find it necessary to install measures in order to facilitate work behind the bulkheads in the gate bays to prevent leakage. Measures to prevent leakage shall be performed at no expense to the Government and shall be submitted for approval by the Contracting Officer's Representative.

ee. The Contractor shall provide measures to protect all new and existing operating machinery and electrical components adjacent to the work areas from contamination by surface preparation, abrasive blast debris, power spraying, weld splatter, concrete splatter, paint overspray, dust or other related debris during performance of the work. Items to be protected include, but are not limited to, tainter gate hoists and appurtenant equipment including electrical panels.

The Contractor shall be responsible for any repairs resulting from damage to all new and existing operating machinery and electrical components. If contamination occurs, the Contractor shall adjust the protection to eliminate contamination at other areas as work progresses.

ff. Gate settings on limit switches shall be recorded on each gate immediately prior to commencement of work on that gate. After work is complete on a gate, the limit switches on that gate shall be reset by the Contractor. The limit switch settings shall be verified by the Contracting Officer's Representative and the Lockmaster prior to initially removing the gate from service and prior to bulkhead removal for that gate.

gg. Any metallic surfaces of the dam which receive overspray from the painting operations shall be repainted with the appropriate paint system as directed by the Contracting Officer at no additional cost to the Government. The Contractor shall protect the concrete surfaces on the dam piers from overspray. If any overspray reaches concrete

DOCUMENT 00 08 00 Page 12 surfaces, the Contractor shall remove it with a method as approved by the Contracting Officer's Representative. All costs associated with overspray removal shall be at the Contractor's expense.

hh. The Government will verify, for every gate that has been rehabilitated, that the gate can operate through the entire service range while the bulkheads are still in place for that gate. This will be verified to the satisfaction of both the Contracting Officer's Representative and the Lockmaster prior to returning the gate to service. If the gate does not operate to the satisfaction of the Government, the Contractor will correct the problem at their expense.

After removal of bulkheads, each gate will be operated through its full range in order to verify seal performance against a head of water.

ii. There is one set of upstream tainter gate bulkheads currently at Jerry F. Costello Lock and Dam and a single pick-up beam available.

The single set of upstream tainter gate bulkheads is limited to closing off one gate bay at a time to Elevation 370.0. The downstream tainter gate bulkheads located at the project have been deemed unfit for service and are not to be used. Handling and placement of bulkheads will be by the Government. Cofferdams or barriers downstream of the tainter gate bays are not permitted.

jj. The staging area for the contract shall be the area by northwest of the control house as shown on contract drawings. No loading or unloading of materials and supplies shall be permitted from the lock walls or guide walls.

kk. The Contractor will be allowed to use the riverside of the downstream floating guidewall for mooring floating plant. Size restriction of floating plant moored to riverside downstream floating guidewall is shown on the contract drawings.

ll. If Option 2 or Option 3: Gate hitch block assemblies connecting the wire rope to the Tainter gate shall be replaced as required.

Tainter gate wire ropes shall be re-tensioned to verify load is distributed equally.

mm. The Contractor shall provide the Contracting Officer and the Lockmaster or the designated representatives a minimum of a two (2) week initial notification and a final 48 hour advance notice prior to commencement of any work. The Contractor shall also coordinate access to the construction area with the Contracting Officer and Lockmaster or designated representatives at the contact information provided below:

Travis Little, Lockmaster 4800 Lock and Dam Rd.

Modoc, IL 62261-1216 618-284-7160

1.21 SUBMITTALS

Additional submittals for this contract that are not listed within individual technical provisions are listed below. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in

DOCUMENT 00 08 00 Page 13 accordance with Section 01 33 00 - SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Accident Prevention Program; G Statements of Required Insurance; G Work Plan; G Contingency Plans; G Storage Of Materials And Equipment; G Modifying Fencing And Handrails; G

SD-05 Design Data

Tainter Gate Support Method; G Relocate And Restore Utilities; G Measures To Prevent Leakage; G

1.22 MEANS OF ESCAPE FOR PERSONNEL QUARTERED OR WORKING ON FLOATING PLANT

Two means of escape shall be provided for assembly, sleeping, and messing areas on floating plants. For areas involving 10 or more persons, both means of egress shall be through standard size doors opening to different exit routes. Where 9 or fewer persons are involved, one of the means of escape may be a window (minimum dimensions 24-inch by 36-inch) which leads to a different exit route. Refer to Section 19 of EM 385-1-1.

1.23 EMERGENCY ALARMS AND SIGNALS

a. Alarms. Emergency alarms shall be installed and maintained on all floating plant requiring a crew where it is possible for either a passenger or crewman to be out of sight or hearing from any other person. The alarm system shall be operated from the primary electrical system with standby batteries on trickle charge that will automatically furnish the required energy during an electrical-system failure. A sufficient number of signaling devices shall be placed on each deck so that the sound can be heard distinctly at any point above the usual background noise. All signaling devices shall be so interconnected that actuation can occur from at least one strategic point on each deck.

b. Signals.

(1) Fire Alarm Signals. The general fire alarm signal shall be in accordance with para 97.13-15b of the Coast Guard Rules and Regulations for Cargo and Miscellaneous Vessels, Subchapter I, 1 Sep 77 (CG 257).

(2) Abandon Ship Signals. The signal for abandon ship shall be in accordance with paragraph 97.13-15c of reference cited in (1) above.

(3) Man-Overboard Signal. Hail and pass the word to the bridge.

All personnel and vessels capable of rendering assistance shall respond.

c. Mooring Lines. Eye loops on mooring lines will be equipped with beckets or handling ropes to protect the hands of deckhands.

DOCUMENT 00 08 00 Page 14

1.24 USE OF MECHANIZED EQUIPMENT ON FLOATING PLANT

When mechanized equipment is operated on floating plant the Contractor shall provide positive and acceptable means of preventing this equipment from moving or falling into the water. The type of equipment addressed by this clause includes front-end loaders, bulldozers, trucks (both on- and off-road), backhoes, track hoes, and similar equipment. If the Contractor plans to use such equipment on floating plant, an Activity Hazardous Analysis must be developed for this feature of work. The plan must include a detailed explanation of the type or types of physical barriers, curbs, structures, etc., which will be incorporated to protect the operator and prevent the equipment from entering the water. Nonstructural warning devices may be considered for situations where the use of structural barriers is determined to be impracticable. The Activity Hazard Analysis must thoroughly address the procedure and shall be submitted to the Contracting Officer for review and acceptance prior to start of this feature of work.

1.25 OBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991) DFARS 252.236-7002

a. The Contractor shall--

(1) Promptly recover and remove any material, plant, machinery, or appliance which the contractor loses, dumps, throws overboard, sinks, or misplaces, and which, in the opinion of the Contracting Officer, may be dangerous to or obstruct navigation;

(2) Give immediate notice, with description and locations of any such obstructions, to the Contracting Officer, and

(3) When required by the Contracting Officer, mark or buoy such obstructions until the same are removed.

b. The Contracting Officer may--

(1) Remove the obstructions by contract or otherwise should the Contractor refuse, neglect, or delay compliance with paragraph (a) of this clause; and

(2) Deduct the cost of removal from any monies due or to become due to the Contractor, or

(3) Recover the cost of removal under the Contractor's bond.

c. The Contractor's liability for the removal of a vessel wrecked or sunk without fault or negligence is limited to that provided in Sections 15, 19, and 20 of the River and Harbor Act of March 3, 1899 (33 U.S.C. 410 et.seq.).

1.26 SIGNAL LIGHTS

The Contractor shall display signal lights and conduct its operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the

DOCUMENT 00 08 00 Page 15 passing by other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International-Inland (Comdtinst M16672.2) or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.

1.27 INSPECTION FACILITIES

a. In order to facilitate inspection, the Contractor will be required, without additional cost to the Government:

(1) To furnish, on the request of the Contracting Officer or any inspector, the use of such boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew of the plant as may be reasonably necessary in inspecting the work.

(2) To furnish, on the request of the Contracting Officer or any inspector, suitable transportation from all points on shore designated by the Contracting Officer to and from the various pieces of plant.

b. Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor.

1.28 CONTRACTOR PERFORMANCE EVALUATIONS

In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor's performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $100,000.00, the USACE will evaluate contractor's performance and prepare a performance report using the Contractor Performance Assessment Reporting System (CPARS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of 30 days. Accessing and using CPARS requires specific software, called PKI certification, which is installed on the user's computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor.

Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.navy.mil/. If the Contractor wishes to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.

1.29 SECURITY REQUIREMENTS

a. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of

DOCUMENT 00 08 00 Page 16 completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:

http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.

b. All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

c. The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

d. All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training.