A00801-616286.pdf

PDF 694 KB Posted

Attached to
616286 CHESTERFIELD-HINSDALE-MIDDLEFIELD-PITTSFIELD Maintenance and Preservation of Municipal Brid
Solicitation number
BD-27-1030-0H100-0H002-131513
Issued by
Berkshire County, Massachusetts

About this file

Summary

This is a Special Provisions document for Proposal No. 616286-135582 issued by the Massachusetts Department of Transportation Highway Division for maintenance and preservation of municipal bridges at multiple locations across five municipalities: Chesterfield, Hinsdale, Middlefield, and Pittsfield. The project encompasses bridge repairs at five specific locations, including Indian Hollow Road in Chesterfield (Bridge C-12-019), Old Windsor Road in Hinsdale (Bridge H-16-006), two bridges on Town Hill Road in Middlefield (Bridges M-19-003 and M-19-004), and Holmes Road in Pittsfield (Bridge P-10-001). Work activities include removal and replacement of hot mix asphalt wearing surfaces, full and partial depth deck repairs, joint replacements, substructure repairs, and cleaning and painting of structural steel. The contractor must comply with the 2026 Standard Specifications for Highways and Bridges, provide labor participation goals of 15.3% for minorities and 6.9% for women, and coordinate extensively with municipalities regarding traffic control, lane closures, detours, and staging. Construction in Chesterfield is restricted to October 1 through April 30 due to campground operations, while Pittsfield work must occur between June 25 and August 20 to avoid school bus traffic. Detours and lane closures shall not exceed six weeks, with specific access restraints and work restrictions outlined for each bridge location.

The contractor is responsible for all coordination costs with no separate payment provided for traffic control, staging, or access requirements. All work must be performed within existing roadway layouts with no private property entry rights acquired. The contractor must conduct pre-construction utility surveys within 30 calendar days of commencing work, notify the Engineer of any utility conflicts, and maintain detailed documentation of utility coordination. Holiday work restrictions apply to major arterial and local roadways, with specific prohibitions outlined for federal and state holidays. Environmental requirements include protection of northern long-eared bats and tricolored bats under the Endangered Species Act, with tree cutting prohibited from April 15 to October 31 unless determined otherwise. The contractor must comply with National Defense Authorization Act prohibitions on specified telecommunications and video surveillance equipment, manage hazardous materials and lead paint removal according to Subsection 961 standards, and implement an integrated cost and schedule controls program with monthly progress reports. All questions must be submitted by 3:00 P.M. on the Tuesday prior to the bid opening date to massdotspecifications@dot.state.ma.us.

View the file

Other files

File Type Posted
616286 - Notice to Contractors.pdf PDF
A00871-616286.pdf PDF
A00820-616286.pdf PDF
A00804-616286.pdf PDF
A00875-616286.pdf PDF
616286 - Plan Holders List 8-11-2026.pdf PDF
A00803-616286.pdf PDF
616286 Bid Items List.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Massachusetts Department Of Transportation Highway Division Proposal No. 616286-135582

A00801 - 1

DOCUMENT A00801

SPECIAL PROVISIONS

CHESTERFIELD-HINSDALE-MIDDLEFIELD-PITTSFIELD

Maintenance and Preservation of Municipal Bridges at Multiple Locations (D1 Contract 2)

Labor participation goals for this Project shall be 15.3% for minorities and 6.9% for women for each job category. The goals are applicable to both Contractor’s and Subcontractor’s on-site construction workforce. Refer to Document 00820 for details.

SCOPE OF WORK

All work under this Contract shall be done in conformance with the 2026 Standard Specifications for Highways and Bridges, the Supplemental Specifications contained in this book, the Construction Standard Details in effect as of May 2026, the 1990 Standard Drawings for Signs and Supports, the 2015 Overhead Signal Structure and Foundation Standard Drawings, the 11th Edition of the Manual on Uniform Traffic Control Devices (MUTCD) and the January 2026 Massachusetts Amendments to the MUTCD, the 1968 Standard Drawings for Traffic Signals and Highway Lighting, the latest edition of The American Standard for Nursery Stock, the Plans and these Special Provisions.

The work to be done under this Contract consists of removal and replacement of hot mix asphalt wearing surfaces, full and partial depth deck repairs, joint replacements, substructure repairs, cleaning and painting of structural steel and structural steel repairs.

The scope of work also includes maintenance of traffic during all operations according to the Temporary Traffic Control Plans as well as all other items of work as may be indicated on the plans or within these specifications.

The extent of the work is location dependent; locations of work are listed below under the heading “Location of Work”.

All work shall be performed within, and accessed by, existing State, City or Town roadway layouts. No rights to enter on or occupy private property have been acquired for this project.

A00801 - 2

LOCATION OF WORK

The following specific bridges are to have worked performed as follows.

BRIDGE

NO. CITY / TOWN

FACILIT

Y

CARRIED F

E

A T

U R

E

IN

T E

R

SE

C T

E D

A

PP

R O

A C

H R

O A

D W

A Y

W

A

R

IN

G S

U R

FA

C

D

C K

R E

PA

IR

S

JO

IN

T R

E

PA

IR

S

O R

PL

A C

E M

E N

T

SU

B

ST

R

U C

T U

R E

R E

PA

IR

S

C L

E A

N

IN

G

P A

IN

T

IN

G

C L

E A

N A

N D

P R

IM

E

E X

IS

T

ST

E

L (G

A L

V . R

E

PA

IR

S)

ST

U C

T U

R A

L S

T E

L

PA

IR

S

C-12-019

(0GA) CHESTERFIELD

INDIAN

HOLLOW

ROAD

CHAUNCEY

BROOK YES NO YES YES

H-16-006 (04Y)

HINSDALE

OLD

WINDSOR

ROAD

WINDSOR

BROOK YES YES YES NO YES

M-19-003

(05P) MIDDLEFIELD

TOWN

HILL

ROAD

FACTORY

BROOK YES YES NO YES YES

M-19-004

(05Q) MIDDLEFIELD

TOWN

HILL

ROAD

FACTORY

BROOK YES YES

NO

YES YES

P-10-001

(01W) PITTSFIELD HOLMES

ROAD

HOUSATONIC

RIVER YES YES YES NO YES YES

CONTRACTOR QUESTIONS AND ADDENDUM ACKNOWLEDGEMENTS

Prospective bidders are required to submit all questions to the Construction Contracts Engineer by 3:00 P.M. on the Tuesday of the previous week before the scheduled bid opening date. Any questions received after this time will not be considered for review by the Department.

Contractors should email questions and addendum acknowledgements to the following email address massdotspecifications@dot.state.ma.us The MassDOT proposal number and municipality is to be placed in the subject line.

mailto:MassDOTSpecifications@dot.state.ma.us

A00801 - 3

NONCONFORMING COMPRESSIVE STRENGTH OF CEMENT CONCRETE

Concrete with compressive strength test results failing to attain the limits specified in Table 901.64-3 of 901.64.B: Acceptance Testing shall be evaluated for structural adequacy and serviceability at the Contractors’ expense. The Department will review all production records, the concrete test records, petrographic analysis report, field notes, and the placement records for the concrete in question. If the Engineer determines the material is found to be adequate to remain in place, payment shall be adjusted in accordance with the following formula:

𝑃𝑃 =

2(𝑓𝑓𝑓𝑓 − 𝑓𝑓′𝑐𝑐)(𝑈𝑈𝑈𝑈)(𝑄𝑄)

𝑓𝑓′𝑐𝑐

Where:

𝑃𝑃 = 𝑝𝑝𝑝𝑝𝑝𝑝 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑓𝑓𝑓𝑓𝑓𝑓 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐

𝑓𝑓′𝑐𝑐 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 28 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑓𝑓𝑓𝑓 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 56 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑄𝑄 = 𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝑏𝑏𝑏𝑏 𝑡𝑡ℎ𝑒𝑒 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝑈𝑈𝑈𝑈 = 𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑜𝑜𝑜𝑜 𝑡𝑡ℎ𝑒𝑒 𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑠𝑠𝑠𝑠𝑠𝑠 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑝𝑝𝑝𝑝𝑝𝑝 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦 𝑓𝑓𝑓𝑓𝑓𝑓 𝑡𝑡ℎ𝑒𝑒 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝

HOLIDAY WORK RESTRICTIONS

(Supplementing Subsection 7.09)

The District Highway Director (DHD) may authorize work to continue during these specified time periods if it is determined by the District that the work will not negatively impact the traveling public. DHD may allow work in those areas on a case by case basis and where work is behind barrier and will not impact traffic

Below are the holiday work restrictions:

New Years Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.

Martin Luther King's Birthday (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.

President's Day (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.

Evacuation Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.

A00801 - 4

HOLIDAY WORK RESTRICTIONS (Continued)

Patriot's Day (State Holiday) Work restrictions will be in place for Districts 3 and 6 along the entire Boston Marathon route and any other locations that the DHD in those districts determine are warranted so as to not to impact the marathon. All other districts work restrictions will be as per DHD.

Mother’s Day No work on Western Turnpike and Metropolitan Highway System from 5:00 AM on the Friday before, until the normal start of business on the following day.

Memorial Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.

Bunker Hill Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.

Juneteenth No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.

Independence Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.

Labor Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.

Columbus Day (Federal Holiday) No work on major arterials from 5:00 AM on the Friday before, until the normal start of business on the following day

Veterans' Day (Federal Holiday) No work restrictions due to traffic concerns.

Thanksgiving Day (Federal Holiday) No work on major arterials from 5:00 AM two days before until the normal start of business on the following Monday.

Christmas Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day.

A00801 - 5

SOIL STOCKPILING DIRECTIVE P-22-001

Any stockpiling of soil must be performed in compliance with Policy Directive P-22-001, Off- Site Stockpiling of Soil from MassDOT Construction Projects. This directive limits the allowable locations for off-site stockpiling of soil generated during MassDOT projects and includes various requirements that must be satisfied by the contractor prior to off-site stockpiling. The Contractor is responsible for identifying a suitable stockpile location.

SUBSECTION 8.02 SCHEDULE OF OPERATIONS

Replace this subsection with the following:

An integrated cost and schedule controls program shall be implemented by the Contractor to track and document the progress of the Work from Notice to Proceed (NTP) through the Contractor Field Completion (CFC) Milestone. The Contractor’s schedules will be used by the Engineer to monitor project progress, plan the level-of-effort required by the Department’s work force and consultants and as a critical decision-making tool. Accordingly, the Contractor shall ensure that it complies fully with the requirements specified herein and that its schedules are both accurate and updated as required by the specification throughout the life of the project. Detailed requirements are provided in Division II, Section 722 Construction Scheduling.

TRUCK SAFETY DEVICES

(Supplementing Subsection 7.04: Motor Vehicles)

All motor vehicles subject to Section 7 of Chapter 90 to be operated under this Contract shall be equipped with safety devices as provided therein and in 540 CMR 4.00.

The Contractor shall certify to the Registry of Motor Vehicles, in a manner prescribed by the Registrar, that all applicable vehicles are equipped with Lateral Protective Devices, Convex Mirrors, Cross Over Mirror(s) and Back Up Cameras in accordance with the requirements of 540

CMR 4.00.

The Contractor shall provide evidence satisfactory to the Department to demonstrate compliance with the above certification requirement for all applicable vehicles operated under this Contract by the Contractor and its subcontractors and vendors in a manner set forth by the Department.

Thereafter, the Contractor shall have an affirmative obligation to continue to provide such evidence of compliance on an ongoing basis and no later than 7 days after certification with the Registry of Motor Vehicles of any additional vehicles operated under this Contract by the Contractor and its subcontractors and vendors.

Non-compliance with respect to a vehicle that is subject to 540 CMR 4.00 may subject the Contractor to statutory fines as established in M.G.L. c. 90, § 7 and/or contractual remedies up to and including termination of the Contract.

A00801 - 6

SUBSECTION 8.14 UTILITY COORDINATION, DOCUMENTATION, AND

MONITORING RESPONSIBILITIES

A. GENERAL

In accordance with the provisions of Section 8.00 Prosecution and Progress, utility coordination is a critical aspect to this Contract. This section defines the responsibility of the Contractor and MassDOT, with regard to the initial utility relocation plan and changes that occur as the prosecution of the Work progresses. The Engineer, with assistance from the Contractor shall coordinate with Utility companies that are impacted by the Contractor’s operations. To support this effort, the Contractor shall provide routine and accurate schedule updates, provide notification of delays, and provide documentation of the steps taken to resolve any conflicts for the temporary and/or permanent relocations of the impacted utilities. The Contractor shall provide copies to the Engineer of the Contractor communication with the Utility companies, including but not limited to:

• Providing advanced notice, for all utility-related meetings initiated by the Contractor.

• Providing meeting minutes for all utility-related meetings that the Contractor attends.

• Providing all test pit records.

• Request for Early Utility work requirements of this section (see below).

• Notification letters for any proposed changes to Utility start dates and/or sequencing.

• Written notification to the Engineer of all apparent utility delays within seven (7) Calendar

Days after a recognized delay to actual work in the field – either caused by a Utility or the Contractor.

• Any communication, initiated by the Contractor, associated with additional Right-of-Way needs in support of utility work.

• Submission of completed Utility Completion Forms.

B. PROJECT UTILITY COORDINATION (PUC) FORM

The utility schedule and sequence information provided in the Project Utility Coordination Form (if applicable) is the best available information at the time of the bid and has been considered in setting the contract duration. The Contractor shall use all of this information in developing the bid price and the Baseline Schedule Submission, inclusive of the individual utility durations sequencing requirements, and any work that has been noted as potentially concurrent utility installations.

C. INITIATION OF UTILITY WORK

The Engineer will issue all initial notice-to-proceed dates to each Utility company based on either the:

1) Contractor’s accepted Baseline Schedule

2) An approved Early Utility Request in the form of an Early Utility sub-net schedule (in accordance with the requirements of this Subsection)

3) An approved Proposal Schedule

C.1 - BASELINE SCHEDULE – UTILITY BASIS

The Contractor shall provide a Baseline Schedule submission in accordance with the requirements of Subsection 8.02 and inclusive of all of the information provided in the PUC Form that has been issued in the Contract documents. This is to include the utility durations, sequencing of work, allowable concurrent work, and all applicable considerations that have been depicted on the PUC Form.

A00801 - 7

SUBSECTION 8.14 (Continued)

C.2 – EARLY UTILITY REQUEST – (aka SUBNET SCHEDULE) PRIOR TO THE BASELINE All early utility work is defined as any anticipated/required utility relocations that need to occur prior to the Baseline Schedule acceptance. In all cases of proposed early utility relocation, the Contractor shall present all known information at the pre-construction conference in the form of a ‘sub-net’ schedule showing when each early utility activity needs to be issued a notice-to-proceed. The Contractor shall provide advance notification of this intent to request early utility work in writing at or prior to the Pre-Construction meeting. Prior to officially requesting approval for early utility work, the Contractor shall also coordinate with MassDOT and all utility companies (private, state or municipal) which may be impacted by the Contract. If this request is acceptable to the Utilities and to MassDOT, the Engineer will issue a notice-to-proceed to the affected Utilities, based on these accepted dates.

C.3 – PROPOSAL SCHEDULE - CHANGES TO THE PUC FORM

If the Contractor intends to submit a schedule (in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02) that contains durations or sequencing that vary from those provided in the Project Utility Coordination (PUC) Form, the Contactor must submit this as an intended change, in the form of a Proposal Schedule and in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02. These proposed changes are subject to the approval of the Engineer and the impacted utilities, in the form of this Proposal Schedule and a proposed revision to the PUC form. The Contractor shall not proceed with any changes of this type without written authorization from the Engineer, that references the approved Proposal Schedule and PUC form changes. The submission of the Baseline Schedule should not include any of these types of proposed utility changes and should not delay the submission of the Baseline Schedule. As a prerequisite to the Proposal Schedule submission, and in advance of the utility notification(s) period, the Contractor shall coordinate the proposed utility changes with the Engineer and the utility companies, to develop a mutually agreed upon schedule, prior to the start of construction.

D. UTILITY DELAYS

The Contractor shall notify the Engineer upon becoming aware that a Utility owner is not advancing the work in accordance with the approved utility schedule. Such notice shall be provided to the Engineer no later than seven (7) calendar days after the occurrence of the event that the Contractor believes to be a utility delay. After such notice, the Engineer and the Contractor shall continue to diligently seek the Utility Owner’s cooperation in performing their scope of Work.

In order to demonstrate that a critical path delay has been caused by a third-party Utility, the Contractor must demonstrate, through the requirements of the monthly Progress Schedule submissions and the supporting contract records associated with Subsection 8.02, 8.10 and 8.14, that the delays were beyond the control of the Contractor.

A00801 - 8

SUBSECTION 8.14 (Continued)

All documentation provided in this section is subject to the review and verification of the Engineer and, if required, the Utility Owner. In accordance with MassDOT Specifications, Division I, Subsection 8.10, a Time Extension will be granted for a delay caused by a Utility, only if the actual duration of the utility work is in excess of that shown on the Project Utility Coordination Form, and only if;

1) proper Notification of Delay was provided to MassDOT in accordance with the time requirements that are specified in this Section

2) the utility delay is a critical path impact to the Baseline Schedule (or most recently approved Progress Schedule)

E. LOCATION OF UTILITIES

The locations of existing utilities are shown on the Contract drawings as an approximation only.

The Contractor shall perform a pre-construction utility survey, including any required test pits, to determine the location of all known utilities no later than thirty (30) calendar days before commencing physical site work in the affected area.

F. POST UTILITY SURVEY – NOTIFICATION

Following completion of a utility survey of existing locations, the Contractor will be responsible to notify the Engineer of any known conflicts associated with the actual location of utilities prior to the start of the work. The Engineer and the Contractor will coordinate with any utility whose assets are to be affected by the Work of this Contract. A partial list of utility contact information is provided in the Project Utility Coordination Form.

G. MEETINGS AND COOPERATION WITH UTILITY OWNERS

The Contractor shall notify the Engineer in advance of any meeting they initiate with a Utility Owner’s representative to allow MassDOT to participate in the meeting if needed.

Prior to the Pre-Construction Meeting, the Contractor should meet with all Utility Owners who will be required to perform utility relocations within the first 6 months of the project, to update the affected utilities of the Project Utility Coordination Form and all other applicable Contract requirements that impact the Utilities. The Contractor shall copy the Engineer on any correspondence between the Utility Owner and the Contractor.

H. FORCE ACCOUNT / UTILITY MONITORING REQUIREMENTS

The Engineer will be responsible for recording daily Utility work force reports. The start, suspension, re-start, and completion dates of each of the Utilities, within each phase of the utility relocation work, will be monitored and agreed to by the Engineer and the Contractor as the work progresses.

I. ACCESS AND INSPECTION

The Contractor shall be responsible for allowing Utility owners access to their own utilities to perform the relocations and/or inspections. The Contractor shall schedule their work accordingly so as not to delay or prevent each utility from maintaining their relocation schedule.

A00801 - 9

COMPLIANCE WITH THE NATIONAL DEFENSE AUTHORIZATION ACT

(Supplementing Subsection 7.01)

On all projects, the “Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment” Regulation (2 CFR 200.216) prohibits the Contractor from using or furnishing the following telecommunications equipment or services:

• Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities).

• For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities).

• Telecommunications or video surveillance services provided by such entities or using such equipment.

• Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.

This prohibition applies to all products manufactured by the aforementioned companies, including any individual components or parts.

By submitting a bid on a project, the Contractor certifies that all work will be in compliance with the terms of 2 CFR 200.216. The Contractor shall submit a COC indicating compliance with the above provisions for all telecommunications equipment or services included in the Contract.

Payment for the item in which the materials are incorporated may be withheld until these COCs are received. Any cost involved in furnishing the certificate(s) shall be borne by the Contractor.

PROPRIETARY PRODUCTS

A letter discussing the HILTI HIT RE-500V3. ADHESIVE ANCHOR as a proprietary specification pursuant to M.G.L. c. 30, sec. 39M(b) has been placed in the Project file. The HILTI HIT RE-500V3, ADHESIVE ANCHOR shall be manufactured by HILTI CORPORATION or approved equal.

CONTRACTOR ACCESS

Contractors shall be aware that there are multi-span bridges with abutments located away from the road. No compensation will be made for access roads to get equipment or personnel to the work site. In addition, no compensation will be made for staging to access repair areas, etc.

A00801 - 10

SCHEDULE OF WORK

The Contractor shall coordinate all construction operations with the municipalities of Chesterfield, Hinsdale, Middlefield (two bridge locations), and Pittsfield, including traffic control, lane closures, detours, staging, and work hours. A minimum of 14 calendar days written notice shall be provided to the municipalities and the Engineer prior to any traffic control setup, lane closure, detour, or staging change, and a minimum of 72 hours notice shall be provided for short-duration or temporary changes unless otherwise approved by the Engineer. No night work shall be permitted unless approved in writing by the Engineer. The Middlefield bridges will not be under construction concurrently since they provide the detour for the adjacent bridge.

All detours and lane closures shall be in place for a maximum of six (6) weeks.

The Contractor shall coordinate with local police, fire, and emergency services to maintain emergency access at all times and shall maintain access to residences, businesses, and abutting properties at all times unless otherwise approved by the Engineer.

For work in Chesterfield, construction activities shall be prohibited from May 1 through September 30 when the Indian Hollow Campground is open to the public; work may proceed between October 1 through April 30 unless otherwise directed by the Engineer. The Contractor shall coordinate all operations with the adjacent property owner to maintain access and operational needs, and shall maintain steel plates on-site or readily available to provide temporary access during deck repair operations as directed by the Engineer. The Contractor shall designate a single point of contact for coordination and provide contact information to the Engineer and municipalities prior to commencement of work.

No separate payment will be made for work required under this provision; all costs shall be included in the Contract prices for the applicable items.

MassDOT has determined that the Contractor shall schedule work to expedite bridge work with a minimum disruption to road users and minimal impact to environmental resources while providing work zone safety. As a result, the Contractor is encouraged to perform concurrent work to facilitate on-time, on-budget project completion.

The Contractor shall schedule work to ensure the final coat of paint is not damaged by other operations. Any damage to coatings due to other Contractor’s operations shall be repaired at the Contractor’s expense.

The Contractor shall schedule the work with consideration that zinc primer alone left exposed may deteriorate over a season. If the zinc primer is left exposed the contractor will be responsible for any surface preparation or rework needed prior to the application of the intermediate and final coats. Consideration should be given to applying the full three-coat system in a single season in all areas that do not require steel repairs, to limit rework as much as practical.

The Contractor shall schedule operations such that any beam requiring temporary support or jacking shall be performed efficiently and will be paid once per location. This may require concurrent substructure and superstructure repairs.

A00801 - 11

SCHEDULE OF WORK (Continued)

Any jacking and shoring reused at the same bridge crossing shall be considered a remove and reset.

Jacking and shoring transported to a new location will be considered a new payment of the jacking and shoring item.

The Project involves bridge preservation at multiple locations. Concurrent traffic control shall be restricted as follows:

Bridges No. M-19-003 and M-19-004 topside traffic control cannot occur simultaneously as each bridge provides the detour route for the other bridge.

The Contractor shall pursue all reasonable means to minimize road closures by ensuring that all required work is being performed simultaneously.

SUBSECTION 8.06 LIMITATIONS OF OPERATIONS

Add/amend the following at the end of the Section:

Access Restraints:

An Access Restraint is a restriction of physical work, of a specific area or operation in the Contract, to allow all bidders to evaluate anticipated work restrictions, equally, during the pre-bid planning stages.

This Contract contains the following Access Restraints that shall be included in the Contractor’s Baseline Schedule submission, in accordance with the terms and conditions of the contract that identifies the Access Restraints noted below:

• AR#1 – Access Restraint #01: The Contractor shall detour traffic for construction for Bridge Structure Number C-12-019 (0GA), Indian Hollow Road in Chesterfield. The daily bridge closure is only allowed between October 1 to May 1 when the Indian Hollow Campground is closed. The contractor to retain steel plates on site to plate over work as required for access to the abutting residence. Daily bridge closures are only allowed to be in place no longer than 6 weeks.

• AR#2 – Access Restraint #02: The Contractor shall detour traffic for construction for Bridge Structure Number H-16-006 (04Y), Old Windsor Road in Hinsdale. Detour is exempt from the 6-week closure restriction.

• AR#3 – Access Restraint #03: The Contractor shall detour traffic for construction for Bridge Structure Number M-19-003 (05P), Town Hill Road in Middlefield. Detour for this bridge cannot occur while bridge M-19-004 is closed. Detour to be in place no longer than 6 weeks.

A00801 - 12

SUBSECTION 8.06 LIMITATIONS OF OPERATIONS (Continued)

• AR#4 – Access Restraint #04: The Contractor shall detour traffic for construction for Bridge Structure Number M-19-004 (05Q), Town Hill Road in Middlefield. Detour for this bridge cannot occur while bridge M-19-003 is closed. Detour to be in place no longer than 6 weeks.

• AR#5 – Access Restraint #05: The Contractor shall use one lane alternating staged construction for Bridge Structure Number P-10-001 (01W), Holmes Road in Pittsfield.

Contractor to perform end diaphragm work under existing lane configuration. Contractor’s equipment to be staged off the bridge during this phase and no equipment to travel in the closed zones of the bridge without approval of the Engineer. After end diaphragms have sufficiently cured, contractor to complete work with daytime closures under police details.

Road to be opened at night so contractor to stage work to only what can be completed in a day. The City has requested the work be performed between June 25th and August 20th when the contractor’s operations will not affect school bus traffic. The contractor to coordinate with the City for approval of any work outside this window.

Work Restrictions:

Additionally, this contract contains the following work restrictions:

• Bridge Structure Numbers C-12-019 (0GA), H-16-006 (04Y), M-19-003 (05P), and M-19- 004 (05Q) shall be closed to traffic, to accomplish the work described to repair and reopen the bridge to traffic.

• No temporary traffic control other than daily traffic setups are to be in place during winter shutdowns.

• All work must be scheduled and coordinated with the respective municipalities. The municipalities must be notified a minimum of 30 days prior to the work commencing.

• Each long term temporary traffic control shall be in place no longer than 6 weeks.

A00801 - 13

PREPARATION OF CONCRETE SURFACES:

All concrete surfaces to be patched shall be roughened, cleaned of all laitance, dirt, grease, oil, other contaminants, and all standing water. All reinforcing steel encountered in the excavation shall be thoroughly cleaned by abrasive blasting before being covered with new concrete.

With approval of the Engineer the Contractor may choose one of the following surface preparation methods. In bonding new concrete to already set concrete the surface of the concrete shall be thoroughly cleaned and roughened then

A) Wetted with clean water and then flushed with a mortar composed of equal parts of the cement and sand specified for the new concrete, before new concrete is placed adjacent thereto. New concrete shall be placed before mortar has taken initial set.

B) Wetted with clean water, and then an epoxy adhesive suitable for bonding fresh concrete to hardened concrete for load bearing applications may be used. The epoxy adhesive shall conform to AASHTO M 235M/M 235 Type V and shall be applied in accordance with the manufacturer’s recommendations.

C) Ponded with clean water to achieve Saturated Surface Dry (SSD) condition then it shall be blown off with oil free compressed air.

NOTICE TO OWNERS OF UTILITIES

(Supplementing Subsection 7.13)

District 2 Utility/Constructability Engineer Paul Kelly Paul.Kelly@DOT.state.ma.us

If available, existing plans indicate the location of the existing known utilities in the vicinity of the work. As the accuracy and completeness of the plans are not guaranteed in any manner, it is the Contractor’s responsibility to make their own investigation to assure that no damage to existing structures, drainage lines, traffic signal conduits, etc., will occur.

Written notice shall be given by the Contractor to all public service corporations or officials owning or having charge of publicly or privately owned utilities of the Contractor’s intention to commence operations affecting such utilities at least one week in advance of the commencement of such operations and the Contractor shall at that time file a copy of such notice with the Engineer.

A list of public and private utilities can be found on the MassDOT website at:

https://www.mass.gov/info-details/utility-contacts-by-district-and-municipality Select District Select the City/Town, and then locate the utility The utility contact list is for guidance only and is not guaranteed to be complete or up to date.

mailto:Paul.Kelly@DOT.state.ma.us https://www.mass.gov/info-details/utility-contacts-by-district-and-municipality

A00801 - 14

EVERSOURCE EMERGENCY TELEPHONE NUMBERS

ELECTRIC:

Outage/ Emergency: 800-592-2000 or 844-726-7562 New Service: 1-888-633-3797 (1-888-need pwr) Customer Support: 1-800-340-9822

BERKSHIRE GAS EMERGENCY TELEPHONE NUMBERS

GAS:

Outage/Emergency: 1-800-292-5012 or 413-499-1680 New Service: 1- 800-297-7144 Customer Support: 1-800-292-5012

NOTIFICATION OF PUBLIC OFFICIALS

Town officials are shown at website https://www.mass.gov/lists/massachusetts-cities-and-towns and select the required City/Town website.

State Police are shown at website https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries. Select the area of jurisdiction to find the local station.

The Contractor shall be responsible for informing the following officials in each area that he is assigned to work in:

Superintendent, Department of Public Works, or Town Engineer. Superintendent, Water Department, Superintendent, Sewer Departments. Police Department, Fire Department, Electric Company, Railroads.

GENERAL REQUIREMENTS FOR DEMOLITION AND

WORK INVOLVING PAINTED STEEL

(02/06/2020)

Demolition and work involving painted steel shall conform to the requirements of Subsection 961 of the Standard Specifications.

Work Involving Painted Steel

Hazardous materials shall be removed in the immediate area of any intended welding, heating, saw cutting or burning of steel. Hazardous material removal is required to allow the demolition of structural steel, railings, drainage systems, utility supports, steel lamp posts, etc.

The contractor shall assume that the coatings on the steel contain lead (Pb), unless otherwise determined by testing. The contractor shall certify in writing to the Engineer the results of all testing, and shall also certify that any lead (Pb) coated steel removed from the project was not reused or buried, but was sent to a scrap metal recycling facility.

https://www.mass.gov/lists/massachusetts-cities-and-towns https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries

A00801 - 15

WORK INVOLVING PAINTED STEEL (Continued)

Implement and maintain programs and procedures, which comply with the requirements of this specification and all applicable standards and regulations. Comply with all applicable regulations even if the regulation is not specifically referenced herein. If a state or local regulation is more restrictive than the regulation of this specification, follow the more restrictive requirements.

This requirement is intended only for the demolition and preparation prior to repair and does not include provisions for recoating of steel.

Environmental

All applicable portions of Subsections 961.65 “Worker Protection” and 961.66 “Environmental Protection and Monitoring” shall be followed when performing this work.

During chemical stripping a hand washing facility may be used in lieu of a decontamination/changing facility.

Hazardous material shall be collected during the disassembly and disposed of as outlined in Subsection 961.68 “Handling of Hazardous Waste and Reporting Release Programs”.

The applicable submittals shall be according to Subsection 961.69 “Submittals”.

Cleaning/Removal

Cutting Or Burning Of Steel

All surfaces to be welded, heated, saw cut or burned shall be cleaned so as to remove all contaminants and/or hazardous materials, which could be discharged to the environment as a function of the subsequent operations.

Lead paint shall be removed in its entirety in an area prescribed by a 6 inch (15 cm) minimum offset from the required work. The paint removal operation may be dry abrasive blasting, wet abrasive blasting or chemical stripping.

Proper level of containment shall be used when performing this work in accordance with Subsection 961.67 “Containment”. Full containment is not required during chemical stripping operation however; the Contractor shall install proper shielding and/or tarpaulins under the chemical stripping operations in order to catch all debris generated during this procedure. A cleaned area must be inspected and approved before the demolition operations are started.

During cleaning operations the Contractor shall be required to furnish and erect temporary floodlights illuminating the steel surface at a minimum of 30-foot candles. This lighting shall be used in areas where there is insufficient lighting for proper cleaning operations and inspection.

The Contractor shall supply electrical power.

A00801 - 16

WORK INVOLVING PAINTED STEEL (Continued)

The Contractor shall provide support for interim and final inspection of the bridge during cleaning operations. This support shall include the necessary traffic controls and safe access to the work.

Mechanical Disassembly Of Steel

All surfaces to be mechanically disassembled by shear cutting or removing bolts or rivets shall not require deleading. When shear cutting or removing bolts or rivets, the Contractor shall not use any method that will cause dust and/or particles to be emitted and/or dispersed into the environment to an extent that would expose the workers above the Action Levels of 30µg/m3.

For purposes of limiting the lead (Pb) dust, the Contractor will be required to dampen the lead paint work areas.

The contractor shall install a proper shielding and/or tarpaulins under all lead-paint-coated surfaces to be shear cut or bolts or rivets ordered removed in order to catch any loose lead paint chips, dust or particles.

PIGEON WASTE

The Contractor shall remove and dispose of the pigeon waste and any other debris accumulated on the steel members and bridge seats in areas where work is being performed. Pigeon waste and debris material contaminants will require special handling and disposal in accordance with all Federal, state, and local requirements. No separate payment will be made for removal and disposal of pigeon waste. Cost shall be incidental to the contract pay items.

EMERALD ASH BORER ADVISORY

To the extent possible, all trees and brush shall be disposed on site, typically chipped and spread in place. When trees or brush must be removed, such as in urban, or otherwise populated areas, Contractor shall identify proposed location for disposal, and provide written notification to the Engineer for approval. Disposal shall be in city or town of project, or at minimum, within county, of construction operations.

SUPPLEMENTAL REQUIREMENTS FOR NON-BID ITEMS

(Supplementing Subsection 3.04) services and specialty services required to perform the work plus (10%) percent, plus actual increased bond premium. The Contractor shall be required to furnish certified paid receipts for additional artisans, equipment rental, materials, engineering services and specialty services that are required to perform the work prior to payment by the Department. Increased bond premium for additional artisans, equipment rental, materials, engineering services and specialty services will be paid after a certified paid receipt is submitted showing payment of the increased bond

A00801 - 17

CONTAMINATED MATERIALS

When generation of hazardous wastes and/or excavation may be conducted within a contaminated area, this information is to be communicated to the Resident Engineer (RE), District Environmental Engineer (DEE), or the project designee prior to initiating the work. The RE, DEE, or project designee is responsible for assisting in the development of the required management procedures for hazardous/regulated wastes that may be generated during the project (including personal protective equipment, generation of manifests, collection/storage of wastes, transfer/disposal of wastes, and tracking manifest documentation). The work will be paid under Non-Bid Items as required by the Engineer. No Assignment of work will be allowed without the approval of the Engineer.

NORTHERN LONG-EARED BAT AND TRICOLORED BAT PROTECTION

The northern long-eared bat (Myotis septentrionalis; NLEB) and tricolored bat (Perimyotis subflavus; TCB) are listed as federally endangered or proposed endangered, respectfully, under the Endangered Species Act (ESA). The U.S. Fish and Wildlife Service (USFWS) developed this guidance to address ESA compliance and promote conservation of NLEB and TCB. As there is no Federal nexus (Federal funding or permits) for this project, Section 7 consultation was not required or conducted. However, Section 9 of the ESA prohibits anyone from “taking” or harming an endangered species, and the below language shall be adhered to in order to maintain compliance with the ESA.

If any of the project locations require work within U.S. Army Corps of Engineers (ACOE) jurisdictional wetlands, the ACOE will be the lead federal agency for ESA consultation with the U.S.

Fish & Wildlife Service (USFWS). Most consultations for the NLEB take 30 days.

The following Avoidance and Minimization Measures (AMMs) must be strictly adhered to in order to protect NLEB and TCB and to be in compliance with the ESA. Contact MassDOT Environmental Services - Wildlife & Endangered Species Unit Supervisor (David Paulson, david.j.paulson@dot.state.ma.us, 857-262-3378) for questions about project limits, restrictions, or conservation measures.

The Resident Engineer can check on the status of AMM applicability by sending a locus map of the proposed work to MassDOT Highway Division’s Environmental Services Section - Wildlife & Endangered Species Unit Supervisor for review and a determination if some of the AMMs and TOY restriction can be waived.

Required AMM for all projects:

• The Contractor shall ensure all personnel working in on the project site are aware of all environmental commitments related to NLEB and TCB, including all applicable AMMs. NLEB Bat information (https://www.fws.gov/midwest/endangered/mammals/nleb/ and https://www.fws.gov/species/tricolored-bat-perimyotis-subflavus) shall be made available to all personnel.

mailto:david.j.paulson@dot.state.ma.us https://www.fws.gov/midwest/endangered/mammals/nleb/

A00801 - 18

(Continued)

If temporary lighting is proposed within the project scope, the following AMM is applicable:

Lighting AMM:

• Direct temporary lighting away from suitable habitat during the active season: April 15 to

October 31.

If the Removal of Trees and/or Woody Vegetation >3-inch in diameter is proposed within the project scope, the following AMMs are applicable:

Tree AMMs:

• If additional cutting is proposed by the Contractor that is outside the scope of this contract, additional review is required by the MassDOT Highway Division’s Environmental Services Section, and additional review and restrictions may be required by the USFWS.

• Ensure tree removal is limited to that specified in project plans and ensure that contractors understand clearing limits and how they are marked in the field (e.g., install bright colored flagging/fencing prior to any tree clearing to ensure contractors stay within clearing limits).

• In order to protect northern long-eared bats and their young during their active season, no tree cutting shall be conducted during the Time of Year (TOY) restriction of April 15 to October 31.

• Do not remove documented or NLEB roosts that are still suitable for roosting, or trees within

0.25 miles of roosts, or documented foraging habitat any time of year (http://www.mass.gov/eea/agencies/dfg/dfw/natural-heritage/species-information-and-conservation/rare-mammals/northern-long-eared-bat.html).

• The Contractor shall ensure all personnel working in on the project site are aware of all environmental commitments related to NLEB and TCB, including the TOY restriction.

If the Bridge Work is proposed within the project scope, the following AMMs are applicable:

Bridge AMMs:

• Bridge AMM 1 - To completely avoid direct effects to roosting bats, perform any bridge removal, replacement, and/or maintenance work during the winter hibernation period unless a hibernating colony of bats is present (contact your local USFWS Field Office for exact dates).

Also, follow Bridge AMM 4.

o Note: Bridge AMM 1 is an avoidance measure for direct effects; the full implementation of which may not always be practicable. If bridge removal, replacement, and/or maintenance work must be performed outside of the winter hibernation period, then follow Bridge AMMs 2-4.

http://www.mass.gov/eea/agencies/dfg/dfw/natural-heritage/species-information-and-conservation/rare-mammals/northern-long-eared-bat.html http://www.mass.gov/eea/agencies/dfg/dfw/natural-heritage/species-information-and-conservation/rare-mammals/northern-long-eared-bat.html

A00801 - 19

(Continued)

• Bridge AMM 2 - Colony or Assuming Presence of Bats o If assuming presence of bats or if bridge assessment or P/A surveys suggest presence of a colony of bats, and work is conducted during the active season, ensure activity will not disturb bats. The following types of bridge work can generally be conducted with the presence of bats:

above deck work where construction equipment or materials do not extend to the underside of deck where bats may be located (e.g., materials that may drip down to underside of deck), or does not include percussives (vibration) or noise levels above general traffic (e.g., road line painting, wing-wall work).

below deck work that is conducted away from roosting bats and does not involve percussives or noise level above general traffic (e.g., wing-wall work, some abutment, beam end, scour, or pier repair).

• Bridge AMM 3 - Small Number of Bats o If bridge assessment or P/A surveys suggest presence of a small number of bats (<5 – not a colony), and work is conducted during the active season, the following types of bridge work can generally be conducted with the presence of bats:

above deck work where construction equipment or materials do not extend to the underside of deck where bats may be located (e.g., materials that may drip down to underside of deck), or does not include percussives (vibration) or noise levels above general traffic (e.g., road line painting, wing-wall work).

below deck work that is conducted away from roosting bats and does not involve percussives or noise level above general traffic (e.g., wing-wall work, some abutment, beam end, scour, or pier repair).

any other bridge removal, replacement, and/or maintenance work (which may include activities with percussives) conducted in the evening while the bats are feeding, starting one hour after sunset, and ending one hour before daylight excluding the hours between 10 p.m. and midnight and keep the light localized.

• Bridge AMM 4 - If assuming presence of bats, or if bridge assessment or P/A surveys suggest presence of bats, ensure suitable roosting habitat is maintained. Suitable roosting sites may be incorporated into the design of a new bridge.

A00801 - 20

ITEM 101.01 CLEARING AND GRUBBING AT BRIDGES SQUARE YARD

The work under this item shall conform to the relevant provisions of Subsection 101 of the Standard Specifications and the following:

The work to be done under this item consists of clearing trees and shrubs outside the proposed parapet face of the wingwall and other selected areas directed by the Engineer to provide access for repair and inspection work.

Areas along the wingwall, abutments, and along the ten (10) feet of approach sidewalks or curblines of the bridges shall be cleared and grubbed for a width of fifteen (15) feet from the face of feature or to the edge of the right of way if less than fifteen (15) feet from the face of feature and as directed by the Engineer.

All debris shall be removed and properly disposed from the site.

METHOD OF MEASUREMENT

Item 101.01 will be measured for payment by Square Yard, by the horizontal plane area.

BASIS OF PAYMENT

Item 101.01 will be paid for at the contract unit price per Square Yard, which price shall include all labor, materials, equipment, removal of all brush, trees, stumps and roots within the designated area, and incidental costs required to complete the work.

No separate payment will be made for any individual trees or stumps removed within the area.

A00801 - 21

ITEM 102. SELECTIVE CLEARING AND THINNING ACRE

Work under this Item shall conform to the relevant provisions of Subsection 101, and the following:

For Bridge P-10-001 (Holmes Road over the Housatonic) all areas along the wing walls and abutments shall be selectively cleared and thinned a minimum 10 feet wide. Only small trees (diameter less than 3-inches), hazard trees, shrubs, and limbs shall be removed for the purpose of contractor inspection and access. The selective clearing and thinning shall only occur using hand tools or via machinery located on the existing roadway. All felled debris must be removed from the area immediately and stockpiled on existing paved areas if needed. Any chipping or mulching of the woody vegetation shall occur on existing paved areas. No ground disturbance may occur.

Should woody vegetation be removed not as specified or ground disturbance occur, the Massachusetts Natural Heritage and Endangered Species Program (NHESP) may issue a cease work order for the contractor and the project will be in violation of the Massachusetts Endangered Species Act (MESA).

A00801 - 22

ITEM 106.493 POLYESTER POLYMER CONCRETE SQUARE YARD

FOR TOPSIDE DECK REPAIRS

The work under this Item consists of using polyester polymer concrete (PPC) for patching the topside of bridge decks and concrete joint headers.

The work shall follow the provided contract drawings where the deck patch does not exceed 2” in depth and shall be as required by the Engineer. The final surface shall meet the existing profile and existing cross slopes.

MATERIALS

The PPC shall consist of polyester resin binder and aggregate as specified below. It shall also include a compatible primer which when mixed with other specified ingredients and applied as specified herein, is capable of producing a PPC meeting the requirements of this specification. All components must be supplied as complete system by same provider referred to as the System Provider.

Polyester Resin Binder. Polyester resin binder shall have the following properties:

(1) Be an unsaturated isophthalic polyester-styrene co-polymer. The resin content shall be 12% +/-1% of the weight of the dry aggregate.

(2) Be used with a promoter that is compatible with suitable methyl ethyl ketone peroxide and cumene hydroperoxide initiators.

(3) Have the values for the material properties shown in the table below:

(4) Accelerators or inhibitor may be required to…

This is the start of the file's text. The full file is on GovTribe.