a__SOW_1305M226Q0126.pdf
PDF 202 KB Posted
- Solicitation number
- 1305M226Q0126
About this file
Statement of Work Summary: FY26 Shipyard Services – NOAA Research Vessel STORM PETREL
This Statement of Work (SOW) Revision D, dated April 28, 2026, outlines shipyard maintenance and repair services for the NOAA Research Vessel STORM PETREL (hull number R5201), a 49.5-foot research vessel. The work must be performed at a contractor facility located within a 65-statute mile radius of Port Angeles, Washington, with an anticipated period of performance from June 8, 2026 to December 7, 2026 (6 months). All work shall comply with current American Boat and Yacht Council (ABYC) and U.S. Coast Guard Subchapter T regulations. The contractor assumes full responsibility for vessel safety, including fire protection, security, and water-tight integrity from arrival until NOAA personnel remove the vessel following inspection and acceptance. Firm-fixed pricing must be provided at the time of bid, with technical oversight provided by LTjg Jack N. Gerrior (jack.gerrior@noaa.gov, 781-217-1696).
The primary work (CLIN 1) comprises fourteen distinct tasks: hauling, blocking, cleaning, storage, and launch; hull overcoat with Trilux 33 antifouling paint; Prop-Speed coating renewal; inspection and lubrication of through-hull valves and seacocks; annual service of two Cummins QSC8.3 diesel engines and transmissions by certified technicians; annual service of one Onan diesel generator; inspection of cutlass bearings on four shafts; replacement of up to eight exterior hydraulic hoses; inspection and service of shaft and rudder packing glands; cleaning and inspection of two diesel fuel tanks; installation of replacement marine-grade decals; inspection and servicing of InterOcean hydraulic winches (conductive and hauling); preventative maintenance of an Ahead Tank MSD system; and welding of two new cleats to the A-Frame. A contingency line item (CLIN 2) provides for Condition Found Reports addressing discovered defects unrelated to the defined scope, requiring TPOC and Contracting Officer approval before additional work commences. All welding must be performed by certified welders using 5083 aluminum alloy plate and 5183 filler wire per approved procedures, with documentation from USCG, ABS, or nationally recognized authorities. The contractor bears all costs for facilities, labor, materials, tools, and services unless otherwise specified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_1305M226Q0126.pdf | ||
| b__Contractor_Past_Performance_Reference_Sheet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work – FY26 Shipyard Services NOAA Research Vessel STORM PETREL
Revision D 4/28/2026
A] GENERAL INFORMATION
1] This Statement of Work contains the requirements for shipyard services on the NOAA Research Vessel Storm Petrel, hull number R5201.
2] The general characteristics of the vessel are as follows:
Length: 49.5 feet Beam: 18.9 feet Draft: ~4.9 feet Displacement: ~26.5 long tons (full load)
3] All work shall be accomplished at the contractor’s facility. Contractor’s facility shall be located with a 65-statute mile radius of Port Angeles, WA. NOAA shall deliver the vessel to the contractor’s facility, and the vessel shall be returned to NOAA at the contractor’s facility.
4] Coordination of the work schedules shall be the responsibility of the contractor to avoid any delays or disruptions in order to meet the period of performance. The contractor shall provide all facilities, labor, materials, tools, and services required to complete the work unless stated otherwise in the tasks below.
5] Upon arrival at the contractor’s facility the contractor shall accept full responsibility for the safety of the vessel, including fire protection, security patrols, water-tight integrity, protection from adverse environmental conditions, etc. This responsibility shall terminate only after all work is complete, work is inspected and accepted by NOAA, and NOAA personnel remove the vessel from the contractor’s facility.
6] NOAA employees and contractors may be working on board the vessel during the contract period of performance on a not to interfere basis. During this period, these personnel shall be given full access to the vessel during normal working hours.
7] If the vessel is hauled from the water, the contractor shall ensure that all machinery and equipment used to haul the vessel is fully functional, suitable for the task, rated for loads at least 20% greater than the maximum weight of the vessel, and operated by trained, competent personnel. A docking plan for the vessel will be provided with this solicitation.
8] The government reserves the right to award some or all tasks defined herein, and to add tasks during the work period so long as cost and period of performance revisions, if any, are mutually agreed.
9] All work performed under this SOW (or added to it during the period of performance) shall meet or exceed all current requirements of ABYC and USCG (Subchapter T) as applicable to this size and type of vessel, in addition to any specific requirements stated below.
10] In the event defects or damage unrelated to the work tasks defined below are discovered, the contractor shall submit a Condition Found Report (CFR) to the Technical Point of Contact (TPOC). The CFR shall define corrective actions needed, the cost for that work (separated into labor, materials, services, and total), and the impact to the period of performance. No additional work shall be performed without prior approval by the TPOC or Contracting Officer.
11] If required, all welding done as part of the tasks shall be performed by certified welders working in accordance with approved weld procedures. Certifications and approvals by USCG, ABS, or another nationally recognized authority are acceptable, and copies of these shall be provided with the quote.
The new plate shall be 5083 alloy of the H321 or H116 temper, and of a thickness equal to the removed plate. Filler wire shall be 5183 alloy. Weld throat widths shall equal the original welds, and weld patterns (continuous, skip, etc.) will be the same as original patterns. After welding, the contractor shall remove all smoke, soot, and oxides with a wire brush, and de-burr all sharp edges.
12] All work performed on the vessel shall be accomplished as described below unless alternatives are presented in writing BEFORE the work commences, and are agreed to by NOAA. Any work that does not adhere to the descriptions shall be redone at the contractor’s expense within the defined period of performance.
13] A site visit is strongly encouraged. Bidders are strongly encouraged to inspect the vessel on which services are to be performed and to satisfy themselves as to all general and local conditions that may affect the cost of the performance of the contract, to the extent such information is reasonably obtainable. In no event shall a failure to inspect the vessel constitute grounds for a claim after award of the contract.
Address for site visit: 832 W Boathaven Drive, Port Angeles, WA 98362 Technical Point of Contact: LTjg Jack Gerrior, 781-217-1696, jack.gerrior@noaa.gov
14) In all cases where the government requires notification during the work, the government will respond within one business day of notification.
B] SPECIFIC WORK TASKS - CLIN1
1] Haul, Block, Clean, Store, Launch Remove the vessel from the water. Pressure-wash the entire hull from sheer line to keel removing all dirt, grime, and marine growth. Clean all surfaces within the tunnel. Clean all fittings below waterline, including propulsor components, struts, stern tubes, rudders, foils, fins, through-hulls, etc. Clean transducers with a non-metallic brush, taking care to not mar the emitting surface in any way. Clean all surfaces of all anodes with a wire brush unless they are to be replaced.
Block the vessel in a level attitude with the keels 36” minimum off the ground. Inspect the hull, coatings, and all attachments and report any damage or discrepancies to the TPOC in writing. During the cleaning process, temporarily shift individual blocks to ensure that all portions of the hull are cleaned. Provide electrical power to the vessel suitable for its shore power system.
Upon completion of all work done on the hard, launch the vessel, inspect all compartments for leaks, and secure it dockside. If dockside testing or underway trials are required after launch, provide prior notification to the TPOC so NOAA personnel can attend.
2] Overcoat Bottom Prepare the hull surfaces to be painted and apply one coat of Trilux 33 (YBA060 Blue) non-copper antifouling paint of the same color as existing paint. Provide an extra coat at the hull’s leading edges, including the hydrofoils, tracking fins, and each rudder. Paint will be applied in accordance with the coating manufacturer’s application requirements. During the coating process, temporarily shift individual blocks under the hull to ensure all portions of the hull are recoated. An OEM representative or certified technician will oversee the application process. Notify the TPOC after completion of painting.
3] Renew Prop-Speed coating Renew the Prop-speed coatings on all surfaces it is currently applied. Manufacturer procedures shall be used in all cases. Ensure that all environmental conditions are within the manufacturer's specified parameters prior to starting application of all coatings. Upon completion, schedule an inspection of the coating system by the TPOC.
4] Inspect and Lubricate All Through-hull valves Actuate, disassemble and visually inspect all seacocks in the hull bottom and topsides. Visually inspect all transducers installed in the hull. Provide a written report describing the location and condition of all seacocks and transducers to the TPOC. If required, present a CFR for all recommended repairs.
Reassemble seacocks, lubricating parts in accordance with manufacturer’s guidance. Upon reassembly, demonstrate proper operation of all seacocks. Once the vessel is returned to the water, inspect all seacocks and associated through-hulls to ensure they are leak-free.
5] Engines Annual Service, Port & Starboard Perform all maintenance and service of all items indicated by the manufacturer (engines have ~1500 hours and 5 years of service) for two (2) Cummins QSC8.3 diesel engines and associated transmissions.
Contractor to provide all parts and materials. If not specified by the manufacturer, also complete the additional tasks for each engine-transmission unit:
● Sample, test, and provide written report on the condition of the following to the TPOC before start of any work:
o Lube Oil o Transmission Oil o Coolant
● Inspect, remove, service, and reinstall IAW manufacturer’s instructions:
o Aftercooler o Heat exchanger
● Remove old and install new:
o Water pump kit o All seawater anodes (contractor to provide replacements) o Engine oil filter(s) o Fuel oil filter(s)
● Change (and dispose of old) engine oil
● Adjust cylinder head valves
● Inspect vibration dampers, engine mounts, and wiring harnesses. For Reference: coolant temp sensors are prone to leaking into harness and then to ECM.
● Inspect pulleys and belts
● Inspect and service transmission and connections to engine
● Report any deficiencies found to NOAA staff
● Conduct operational testing dockside (vessel waterborne) with trained Cummins technician, conduct and document assessment of engine performance including temperatures, pressures, and load levels, confirm that both engines perform within approved specifications
● Provide a written report describing all work performed
All work will be carried out by Cummins certified Technicians that are trained for the brands and models of machinery. Upon completion, NOAA staff will run each engine while the contractor records performance parameters and demonstrates that the machines are operating properly.
6] Generator Annual Service Perform all maintenance and service of all items indicated by the manufacturer (engine has ~1800 hours and 5 years of service) for one (1) Onan 21.5MDKDR78112A diesel generator set. Contractor to provide all parts and materials. If not specified by the manufacturer, also complete the additional tasks:
● Sample, test, and provide written report on the condition of the following to the TPOC before start of any work:
o Lube Oil o Coolant
● Remove old and install new:
o Water pump kit
● Change (and dispose of old) engine oil
● Generator bearing inspection
● Megger windings
● Visually inspect for signs of leaks and degradation
● Adjust cylinder head valves as needed
● Inspect:
o Coolant o All engine or generator mounts o Vibration dampers o Pulleys and belts o Bearings in generator end
● Report all adverse findings on the machinery to NOAA staff
● Conduct operational testing dockside. Run at maximum rated amps for 30 minutes. NOAA staff to assist as needed.
● Provide a written report describing all work performed
All work will be carried out by technicians trained for the brands and models of machinery. Upon completion, NOAA staff will run the generator while the contractor records performance parameters and demonstrates that the machine is operating properly.
7] Inspect Cutlass Bearings, Provide Report Measure the gaps between the shaft and bearing for all four (4) shafts (Port rudder, port propeller, starboard rudder, and starboard propeller). Take measurements at three (3) equidistant locations around the circumference of the shaft between the shaft and bearing (4 shafts x 3 places each = 12 locations). Determine if clearances meet or exceed bearing manufacturer tolerances. Provide written recommendations, including a CFR if bearing replacement is required, to NOAA staff.
8] Replace eight (8) Exterior Hydraulic Hoses.
Remove and replace up to eight (8) individual hydraulic hoses located on the vessel exterior. NOAA staff will identify exact hoses to be replaced. New hoses and fittings of equal or better pressure rating, bend radius, and weather-resistance will be provided and installed. Hose fittings and ferrules will be cadmium-plated steel, and be wrapped in Densyl tape after installation. Hose lengths will be replicated unless improved routing of the new hoses offers clear advantages and NOAA staff approve. If existing hoses have chafe or weather protection sleeves installed, those will be duplicated on the new hoses.
Take all precautions against spilling hydraulic fluid during replacement, and any drips or spills will be completely cleaned up. To the extent possible, new hoses will be charged with the same hydraulic oil that is currently in the hydraulic system. Upon completion, NOAA staff will operate the hydraulic equipment and the Contractor will demonstrate that no leaks are present. Provide a list of replaced hoses and fittings to the TPOC.
All work will be carried out by technicians trained to remove and replace hydraulic hose. Upon completion, NOAA staff will run the vessel’s hydraulic systems while the contractor records performance parameters and demonstrates that the system is operating properly.
9] Inspect and Service Rudder and Shaft Packing Glands (Port and Starboard) Conduct an inspection and service the vessel’s shaft packing glands (port and starboard) and rudder packing glands IAW manufacturer-recommended procedures and guidelines for units with 5 years of time in service. A written inspection report will be provided to the TPOC before any work commences.
Once approved by the TPOC, the port and starboard shaft and rudder packing glands will be serviced.
Final adjustments will be made by the contractor once the vessel is waterborne and in the presence of NOAA staff.
All work will be carried out by technicians trained for the type of work.
10] Inspection and Clean Fuel Tanks (Port and Starboard) Clean and inspect the interior of two (2) diesel fuel tanks, one at a time as follows. For reference, each tank has a maximum capacity of approximately 275 gallons, NOAA will deliver the vessel to the yard with no more than 30% fuel in the tanks.
A] Transfer all fuel to the tank not being inspected, contractor to provide pump, connections, and materials for safe transfer. Remove the fuel tank inspection plate, and dispose of any fuel remaining. If required, certify the tanks are gas-free. Clean the tank interior thoroughly and dry all surfaces. Inspect all interior surfaces for corrosion, and note any deficiencies and/or recommended additional service.
Provide a written report to the TPOC on the tank condition before replacing the inspection plate.
Reinstall the inspection plate with a new BUNA-N gasket. Transfer all fuel in the second tank to the cleaned tank and proceed with the cleaning and inspection of the second tank in the same manner described above.
B] Once both tanks are cleaned and inspected, demonstrate to the TPOC that the inspection plates in both tanks and any fuel system fittings disturbed in the work are secured fuel-tight with no leaks.
11] New Decals Provide replacement marine grade decals for the following:
1] Bicolor stripes on Port and Starboard house sides, 2] Letters and numbers on Port and Starboard bows, 3] Letters and numbers on transom.
Remove decals. Clean and degrease the areas where decals were previously installed. Install new decals same color and size at the same location as the ones removed. Contractor to provide all materials.
Government will provide color, size and OEM material information from the OEM ship builder (All American Marine) upon request.
12] InterOcean Hydraulic Winches: Inspection and Servicing Inspect and service the vessel’s InterOcean Systems conductive and hauling winches IAW with the manufacturer’s recommended guidelines for units at 5 years of service time. Provide a written list of recommended materials and service to the TPOC prior to moving forward with any additional work.
The maintenance items for each winch will include the following at a minimum:
A) Conductive Winch, Interocean Systems LLC, Dual Drum 76675-5HLW, Serial No.: 66751284, Mfg.
Date: May 2021
● Complete all work in accordance with OEM standards
● Inspect the winch drum, chains, and gears
● Sample winch gear oil and top up if required
● Inspect and test the slip-rings
B) Hauling Winch, Interocean Systems LLC, Dual Drum 10031-20HLW, Serial No.: 66751284, Mfg.
Date: May 2021
● Complete all work in accordance with OEM standards
● Remove line from drum
● Inspect the winch drum, chains, and gears
● Sample and top up winch gear oil if required
● Re-terminate drum-end of the hauling winch
● Reinstall Amsteel line under load
Upon completion of all work above, NOAA staff will operate both winches in the presence of contractor-designated personnel to demonstrate proper system operation. The winch controls will not be operated by anyone other than NOAA staff. A written record of all completed inspections and work will be provided to the TPOC after project completion.
13] Ahead Tank MSD System: Inspection and Servicing Conduct all preventative maintenance and service recommended by Ahead Sanitation Tank manufacturer for AT‐6T USCG Certified and IMO Approved 56 gal/day Type II Marine Sanitation Device.
This work includes the following requirements:
● Replace 56-Gallon tank bio media in the Clarification Chamber
● Flush system with freshwater and verify proper functionality IAW USCG certification
● Provide written report detailing inspection findings and completed work on the system
All work will be carried out by technicians trained for the brands and models of machinery. Upon completion, NOAA staff will run the MSD system and verify that it is operating properly.
14] Weld two (2) new cleats to A-Frame Add one 8” cleat to each inboard side of A-Frame as indicated by the TPOC. Weld the cleats and clean the welds as specified in paragraph A.11 of this document. Contractor to provide cleats and all materials.
C] CONDITION FOUND CONTINGENCY (CFRS) CLIN2
15] Contingency In the event defects or damage unrelated to the work tasks in this scope are discovered, the contractor shall submit a Condition Found Report (CFR) to the Technical Point of Contact (TPOC) for review. The CFR shall define corrective actions needed, the cost for that work (separated into labor, materials, services, and total), and the impact to the period of performance. No additional work shall be performed without prior approval by the TPOC and Contracting Officer.
D] OTHER INFORMATION
1] Period of Performance Date of Award through 6 months (Anticipated June 8, 2026 – December 7, 2026). Actual POP dates to be determined at time of award.
2] Place of Performance All work items requiring lifting of the vessel on to land will conducted at the vendor’s facility. If mutually beneficial to the Government and the Contractor, work items that can be accomplished while the boat is in the water may be conducted at Storm Petrel’s home dock or at the Contractor’s dock.
3] IT Security Requirements The Certification and Accreditation (C&A) requirements of 48 CFR 1352.239-73 do not apply, and a Security Accreditation Package is not required. The Contractor will not be accessing US government computers or IT systems for this effort. The Contractor will not be accessing any information that is not within the public domain for this effort. The contractor will not be processing, transmitting or storing privileged access information (i.e., non-public) in carrying out the tasks of this contract.
4] Pricing Contractor to provide firm-fixed pricing of all work list items at time of bid.
5] Technical Point of Contact
LTjg Jack N. Gerrior jack.gerrior@noaa.gov 781-217-1696 cell
6] Invoicing Point of Contact David Lott dave.lott@noaa.gov 831-241-3097 cell mailto:dave.lott@noaa.gov
File details come from the government source that posted it. Updated .