A.02 Repair Fire Suppression PWS W50S8W25Q0008 (007635).pdf
PDF 188 KB Posted
- Attached to
- Repair Fire Suppression
- Solicitation number
- W50S8W-25-Q-0008
- Issued by
-
Department of the Army National Guard
About this file
This Performance Work Statement (PWS) details a contract for repairing fire suppression systems at the Wyoming Air National Guard's 153d Airlift Wing located at the Cheyenne Regional Airport. The project requires a comprehensive inspection and repair of fire pump systems, including visual inspections of pump components, isolation of fire pumps during work, replacement of mechanical seals and solenoid valves, and thorough testing of system performance. The contractor must use manufacturer-recommended replacement parts, follow industry best practices, and conduct flow, pressure, and functionality tests, submitting all test results for client review and approval.
Key requirements include working during normal hours (7:00 am to 4:30 pm, Monday through Friday), providing all necessary equipment, maintaining strict safety protocols, and complying with base access and security procedures. The contractor will be responsible for cleaning up the work site, ensuring no damage to existing infrastructure, and coordinating all work with the Point of Contact (POC). The solicitation number is W50S8W-25-Q-0008, and the project is part of a sources sought announcement to identify potential small business contractors for future acquisition.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
WYOMING AIR NATIONAL GUARD
217 DELL RANGE BLVD. CHEYENNE, WYOMING
W50S8W-25-Q-0008
DPEZ252202
REPAIR FIRE SUPPRESSION SYSTEMS
PURPOSE:
Ensure the fire suppression system is fully functional and compliant with safety regulations, to maintain fire protection capabilities for our facilities.
LOCATION:
153d Airlift Wing, located at the Cheyenne Regional Airport, 217 Dell Range Blvd, Cheyenne, WY 82009.
COORDINATION:
The contractor shall coordinate all work with the POC.
Contact the POC five (5) working days in advance of mobilization on site and provide proper documentation to allow for processing of base access paperwork. This requirement includes deliveries of any kind. Same day request and access is not always possible.
DAMAGE:
The Contractor shall be responsible for any damages caused to any existing work areas during the entire performance of this project. The Contractor shall be responsible to rectify or replace any equipment damaged without additional expense to the Government.
ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES:
Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Point of Contact (POC). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
All commercial, contractor, and sub-contractors vehicles are subject to random inspections each time they enter the base.
If badges will be issued, they will be issued by the 153d Security Forces Squadron (SFS) to the contractor through the 153 CES POC. Badges shall be issued, tracked, and collected in accordance with instructions from Security Forces.
The following are the requirements and procedures for the contractor: Contractors working in Controlled or Restricted areas or any area on the flight line must be issued a specific contractor identification badge or be escorted. (This project is not located on the flight line).
HOURS OF WORK:
Normal hours of operation for service are 7:00 am through 4:30 pm Monday through Friday, excluding any federally recognized holidays.
Requests to work outside the normal work hours must be made to the POC at least three working days in advance. The POC may reject requests at the convenience of the government. Failure to make requests at least three (3) working days in advance may result in being denied base access or being required to leave the base.
CLEAN-UP:
The contractor shall clean up and remove from the site all rubbish, which has resulted from any contract work and shall leave the premises in a clean, orderly and safe condition, acceptable to the POC.
Equipment:
1. The Contractor will supply all necessary equipment and tools to complete the project. Any costs for procuring equipment and tools must be included in the bid.
2. The Contractor will not utilize any government equipment or tools.
DESCRIPTION OF WORK:
Fire Pump Inspection and Isolation
• Contractor shall perform a visual inspection of the fire pump(s), including but not limited to:
o Pump casing for signs of leaks, cracks, or corrosion o Pump shaft and bearings for signs of wear or damage o Suction and discharge valves for proper operation o Pressure gauges and flow switches for proper function
• Contractor shall isolate the fire pump(s) from the fire suppression system, ensuring the system remains operational through backup or temporary means during the work.
• Contractor shall obtain client approval before proceeding with any work.
Seal and Solenoid Replacement
• Contractor shall replace the following components on each fire pump:
o All mechanical seals o All solenoid valves
• Contractor shall use only new, manufacturer-recommended replacement parts.
• Contractor shall clean and inspect all mating surfaces before installing new seals and solenoids.
• Contractor shall follow manufacturer specifications and industry best practices for installation and torquing procedures.
Clean Up and Demobilization
• After replacing the seals and solenoids, the contractor shall reinstate the fire pump(s) into the fire suppression system.
• Contractor shall perform a comprehensive test of the fire pump(s) and associated systems, including but not limited to:
o Flow tests to verify pump performance o Pressure tests to verify system integrity o Alarm and control system functionality
• Contractor shall record and submit all test results to the client for review and approval.
Safety
The Contractor shall be solely responsible for the safety of its employees and subcontractors. The Contractor shall comply with all applicable safety regulations and provide appropriate personal protective equipment (PPE) for all workers.
POINT OF CONTACT:
All questions shall be submitted by E-mail. Questions will be answered no later than 10 days following receipt. Unless otherwise stated, all questions will be routed through the Contracting Officer and the Contracting Officer Representative.
217 DELL RANGE BLVD. CHEYENNE, WYOMING
File details come from the government source that posted it. Updated .